Download presentation
Presentation is loading. Please wait.
Published byGriselda Strickland Modified over 6 years ago
1
Meeting for S1-Global module design Cryomodule and Cryogenics 20090107
ILC Cryomodule and Cryogenic Groups 2009/01/07 S1-Global module meeting & Cryomodule Cryogenics
2
S1-Global module meeting & Cryomodule Cryogenics
Agenda WPM analysis in STF cryomodule (Hitoshi Hayano) Pressure analysis in the vacuum vessel in case of cold trouble (Hirotaka Nakai) Progress of S1-G cryomodule CAD work (Norio Higashi, Norihito Ohuchi) WP of the cryomodule and cryogenics (Norihito Ohuchi, Tom Peterson) 2009/01/07 S1-Global module meeting & Cryomodule Cryogenics
3
3. Progress of S1-G cryomodule CAD work
It was pointed by the INFN group that the distance between the input couplers of Module-C was mm at 2K while this distance was mm at room temperature. The connection flange of input coupler on the vacuum vessel for XFEL is designed to locate at the distance of mm for the best condition at 2K. In the present drawing of S1-G cryomodule, this distance was mm. The distance of support legs on the gas return pipe was mm for XFEL. This distance was optimized at 2 K while the present distance in the S1-G module design was mm. The CAD data is being modified, and the modification will be completed in this week. The CAD works for the cooling pipes (5K forward and 2.2K), pipes for signals and WPM stages are on going, and they will complete in the next week. 2009/01/07 S1-Global module meeting & Cryomodule Cryogenics
4
S1-Global module meeting & Cryomodule Cryogenics
XFEL-vacuum vessel mm 2009/01/07 S1-Global module meeting & Cryomodule Cryogenics
5
S1-Global module meeting & Cryomodule Cryogenics
XFEL-gas return pipe 1385.6 2009/01/07 S1-Global module meeting & Cryomodule Cryogenics
6
4. WPs of cryomodule and cryogenics
TDP R&D plan update by PMs ID title Description 1.3.1. Standardization Establish basic design parameters, plug compatible interface conditions, and high-pressure gas code (regulation) issues. 1.3.2. Cooling pipe configuration and 5 K shield - Calculation of pressure drops, definition of the maximum pressure, cooling procedure, new piping on the module transverse cross section. - Calculation of thermal-balance with or w/o 5 K-shield Trade-off with cryogenics operation cost. 1.3.3. Quadrupole + BPM Assembly Quadrupole + BPM location, support, installation procedure, alignment, vibration, current leads. 1.3.4. Assembly Process & Engineering design with CAD - Study of Assembly procedure, fixtures, facilities, - Study of inter-connect procedure. - Systematic engineering design using 2D/3D CAD, - R&D for technically critical components such as Ti-SUS junction, vacuum components, etc. 1.3.5 Systematic performance evaluation Establish performance testing process, procedures and design the test facility and define its role during the mass production stage. 1.3.6. Transportation Seek transportable cryomodule (region to region) Investigate transportation down to the tunnel through vertical shaft, with inclination (to save shaft size). 1.3.7. Cost/Industrialization Cost estimate based on Baseline Configuration, and Industrialization effort (mass production and reducing the cost) 2009/01/07 S1-Global module meeting & Cryomodule Cryogenics
7
S1-Global module meeting & Cryomodule Cryogenics
Next meeting 20 January 2009 (Tuesday) 23:00 (KEK), 8:00 (FNAL), 15:00 (DESY, INFN) 2009/01/07 S1-Global module meeting & Cryomodule Cryogenics
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.