1 Resource Registration Update
Dana Showalter June 9, 2008

2 Resource Registration
Current activities Contacting all Resources regarding RARF corrections and clarifications targeting EDS needs Continuing efforts scoring the RARF submittals Continuing efforts scoring the Resource mapping submittals Populating database for internal ERCOT use Establishing process for internal ERCOT RARF review/acceptance to populate ERCOT systems Future activities Finalize review/acceptance of RARF data by ERCOT data consumers Begin scoping MP RARF interface project Resource Registration

3 Resource Registration – RARF Call Campaign
Reached over 77% of registered capacity within ERCOT Tab by tab review targeting the following areas Format of data, including blanks and removal of text in value fields Review of RUC parameters and ramp rates Review of seasonal parameters and resource limits Did not get into the details for network modeling, planning, and protection Target turnaround by MP was typically established to be two days Resource Registration

4 Resource Registration - Concerns
Network Model information alignment for equipment owned by Resource Entities RARF (should replace Transmission Data Forms after Single Model Entry) Transmission Data Forms for MP10 Information in existing model not currently reviewed Needing information missing from existing model not being requested Quality of data, such as impedances, incomplete or inaccurate will negatively affect network model and planning efforts Changes to Nodal systems may require corrections to RARF Private Network LRL should be zero, but HRL should encompass generating capabilities Normalizing the Resource registration process Resource Registration

5 Review/Validation process and timing
MP11 Status Review/Validation process and timing First step consists of a business review by WCS; may need immediate corrections by MP in order to load into RARF database Temporary step consists of EDS critical data review Formal process includes technical review by data consumers within ERCOT Submittals 99.4% of registered capacity accounted for on RARFs Contacted 77% of registered capacity for improvements to data and have been receiving corrections Some of these still need to be re-scored A few Resource Entities still have trouble with TML submittal Resource Registration

6 MP11 Status Resource Registration

7 MP10 forms were due to ERCOT by April 15, 2008
MP10 Status MP10 forms were due to ERCOT by April 15, 2008 Initiation of network model change process (Transmission Data Forms as needed) target date of two weeks of ERCOT request Submittals to include MP10 Form Check boxes if approved If not approved, briefly write issues on MP10 form If ERCOT model change required: Complete ERCOT Transmission Data form Send correct updated operational (non-relaying) oneline for facility Status of 172 sites (removed DG and obsolete sites): 61% are complete 20% need to submit Transmission Data Forms or review corrected packages 12% are waiting on feedback/corrections by ERCOT 7% are non-responsive Resource Registration

8 MP10 Status

9 Metric Revisions Needed?
Redefine or clarify the metrics? MP11 Some options may include: Closure of metric, but continue a report card of RARF status until approved for Nodal systems Set new goal and continue efforts until approved for Nodal systems Some effort will still be needed by MP and ERCOT until testing is complete MP10 Stop phase 1 and begin phase 2 when NMMS is able to export the Nodal information Continue phase 1 until corrections to current model are complete and begin phase 2 when NMMS is able to export the Nodal information Beneficial to complete this now to reduce the effort on phase 2 New sites and private networks registering additional generators will be part of phase 2

10 Questions? Send questions to or call ERCOT Client Services at Resource Registration