Building H0209A (G007) (GAP Thorsten Ziglasch, Ina Schurig)

Similar presentations


Presentation on theme: "Building H0209A (G007) (GAP Thorsten Ziglasch, Ina Schurig)"— Presentation transcript:

1 Building H0209A (G007) (GAP Thorsten Ziglasch, Ina Schurig)
Current Status Activities Communication

2 Overview Building Cable Planning CPS and UPS Air- and Water Cooling
Radiation Shielding Other Building Aspects Organization Aspects

3 3D model Building H0209A

4 E20 (3D)

5 E20 with Racks

6 E20 including racks (2D)

7 E10 (3D)

8 E10 including racks (3D)

9 E10 including racks (2D)

10 Building H0209A

11 Cable Planning All data is specified by the WPLs
includes starting point (component) ending point (power rack) cable type and cable class connectors electrical current and voltage thermal energy many other special requirements

12 Cable Database

13 Cable Database

14 Cable Database

15 Cable Database

16 Cuts for cable trays & surveying

17 External Cable Planning

18 Internal Cable Planning

19 CPS and UPS WPLs provided their requirements for CPS and
uninterrupted power supplies UPS All data ist collected to be able to combine the requested modules with the aim to limit the amount of CPS and UPS units process is still ongoing

20 Air- and Water Cooling

21 Radiation Protection E10

22 The Balcony

23 Cut Through The Balcony

24 Radiation Protection E20

25 Other Building Aspects

26 Other Building Aspects

27 Organizational Aspects
WPLs define: Change Requests for all relevant changes No direct communication with the external planners – communication is done via FAIR S&B or Marianna Frech (Drees & Sommer) every 2nd week „Technik AG“ to discuss general issues concerning buildings & machines cables electrical power & heat loss data technical gases nomenclature of components # of IT-network plugs and telephones


Download ppt "Building H0209A (G007) (GAP Thorsten Ziglasch, Ina Schurig)"