Building H0209A (G007) (GAP Thorsten Ziglasch, Ina Schurig)
Current Status Activities Communication
2
Overview Building Cable Planning CPS and UPS Air- and Water Cooling
Radiation Shielding Other Building Aspects Organization Aspects
3
3D model Building H0209A
4
E20 (3D)
5
E20 with Racks
6
E20 including racks (2D)
7
E10 (3D)
8
E10 including racks (3D)
9
E10 including racks (2D)
10
Building H0209A
11
Cable Planning All data is specified by the WPLs
includes starting point (component) ending point (power rack) cable type and cable class connectors electrical current and voltage thermal energy many other special requirements
12
Cable Database
13
Cable Database
14
Cable Database
15
Cable Database
16
Cuts for cable trays & surveying
17
External Cable Planning
18
Internal Cable Planning
19
CPS and UPS WPLs provided their requirements for CPS and
uninterrupted power supplies UPS All data ist collected to be able to combine the requested modules with the aim to limit the amount of CPS and UPS units process is still ongoing
20
Air- and Water Cooling
21
Radiation Protection E10
22
The Balcony
23
Cut Through The Balcony
24
Radiation Protection E20
25
Other Building Aspects
26
Other Building Aspects
27
Organizational Aspects
WPLs define: Change Requests for all relevant changes No direct communication with the external planners – communication is done via FAIR S&B or Marianna Frech (Drees & Sommer) every 2nd week „Technik AG“ to discuss general issues concerning buildings & machines cables electrical power & heat loss data technical gases nomenclature of components # of IT-network plugs and telephones