Process Air Compressor Knockout Replacement
Presented By: Saud Saleem Designation: App. Engineer(Mech)
2
Overview: Introduction Project Handling Cost estimation Problem Area
3
Introduction: Knockout? A knockout drum is used whenever a process requires droplets to be separated from a vapor stream. T1 Inter Cooler Condensate causing Corrosion Condensate Removed and Drained Out Main Suction T2 T3 Where T2 > T1 Where T3 < T2 Condensed Vapors Knockout Drum
4
Working Principle of Vane Pack:
Flow Vane Pack
5
Introduction: Background: Existing knockouts were replaced in 1987.
Upon inspection in TA-07, heavy corrosion and cracks was observed on impellers. PECO (Original Vendor) informed that knockouts are undersized
6
Project Handling: Steps taken sequentially Planning and Scheduling
Engineering Procurement Execution
7
Project Handling: PLANNING & SCHEDULING:
8
Percentage scope of each section:
Project Handling: Percentage scope of each section:
9
Cost Estimation: Rs. 60.4 MM Rs.17.0 MM Rs. 1.54 MM Rs. 1.39 MM
Cost Basis 30-Sep-2007 Foreign Component Cost of Internals € 90,178 Cost of Instrumentation € 100,000 Local Component Cost of Vessels Rs MM Cost of piping+ Civil works Rs MM Custom 5% Rs MM Sales Tax Rs MM Cost of Construction Rs MM Total Local Component Rs MM (€ 1.1 MM) 10% € MM Total Cost In Euro € MM
10
Project Handling: Engineering: Process Design Mechanical Design
Civil Design
11
Project Handling: Procurement: Mechanical equipments: Instrumentation:
Knockout vessels Internals Glass Level Gauges Flexibility bellows Hanger supports Instrumentation: Level transmitter Level Controller Control valves
12
Mechanical Equipment:
Upstream Gas Distribution Plate & YORKMESHTM Agglomerater FLEXICHEVRON Vane Pack Tower Attachements Knockout Vessel
13
Comparison of total procurement by each section:
14
Project Handling: Procurement Status: Material procured
Internals Material under procurement Knockout vessels Pending materials Expansion bellows Control valves Glass Level Gauges Spring hanger support
15
Project Handling: Execution: Mechanical
Installation of New Interconnecting Piping Re-routing of existing piping Erection of KO vessel Installation of Internals Installation Of Glass Level Gauges
16
C-111A C-109A AVAILABLE SPACE FOR C-111A NEW C-111A NEW C-108A
NOZZLE SIZE INCREASED NEW PIPING Ø 12” C-109A
17
Project Handling: Execution: E&I Installation Of Control Valves
Installation Of Level Transmitters Installation Of Switches
18
Project Handling: Execution: Civil Structure Foundation
19
Problem Areas: Procurement of knock out vessels.
Procurement of control valves. Procurement of Flexible bellows. Project time line.
20
Thank You
21
Questions?