Presentation is loading. Please wait.

Presentation is loading. Please wait.

Process Air Compressor Knockout Replacement

Similar presentations


Presentation on theme: "Process Air Compressor Knockout Replacement"— Presentation transcript:

1 Process Air Compressor Knockout Replacement
Presented By: Saud Saleem Designation: App. Engineer(Mech)

2 Overview: Introduction Project Handling Cost estimation Problem Area

3 Introduction: Knockout? A knockout drum is used whenever a process requires droplets to be separated from a vapor stream. T1 Inter Cooler Condensate causing Corrosion Condensate Removed and Drained Out Main Suction T2 T3 Where T2 > T1 Where T3 < T2 Condensed Vapors Knockout Drum

4 Working Principle of Vane Pack:
Flow Vane Pack

5 Introduction: Background: Existing knockouts were replaced in 1987.
Upon inspection in TA-07, heavy corrosion and cracks was observed on impellers. PECO (Original Vendor) informed that knockouts are undersized

6 Project Handling: Steps taken sequentially Planning and Scheduling
Engineering Procurement Execution

7 Project Handling: PLANNING & SCHEDULING:

8 Percentage scope of each section:
Project Handling: Percentage scope of each section:

9 Cost Estimation: Rs. 60.4 MM Rs.17.0 MM Rs. 1.54 MM Rs. 1.39 MM
Cost Basis 30-Sep-2007 Foreign Component Cost of Internals € 90,178 Cost of Instrumentation € 100,000 Local Component Cost of Vessels Rs MM Cost of piping+ Civil works Rs MM Custom 5% Rs MM Sales Tax Rs MM Cost of Construction Rs MM Total Local Component Rs MM (€ 1.1 MM) 10% € MM Total Cost In Euro € MM

10 Project Handling: Engineering: Process Design Mechanical Design
Civil Design

11 Project Handling: Procurement: Mechanical equipments: Instrumentation:
Knockout vessels Internals Glass Level Gauges Flexibility bellows Hanger supports Instrumentation: Level transmitter Level Controller Control valves

12 Mechanical Equipment:
Upstream Gas Distribution Plate & YORKMESHTM Agglomerater FLEXICHEVRON Vane Pack Tower Attachements Knockout Vessel

13 Comparison of total procurement by each section:

14 Project Handling: Procurement Status: Material procured
Internals Material under procurement Knockout vessels Pending materials Expansion bellows Control valves Glass Level Gauges Spring hanger support

15 Project Handling: Execution: Mechanical
Installation of New Interconnecting Piping Re-routing of existing piping Erection of KO vessel Installation of Internals Installation Of Glass Level Gauges

16 C-111A C-109A AVAILABLE SPACE FOR C-111A NEW C-111A NEW C-108A
NOZZLE SIZE INCREASED NEW PIPING Ø 12” C-109A

17 Project Handling: Execution: E&I Installation Of Control Valves
Installation Of Level Transmitters Installation Of Switches

18 Project Handling: Execution: Civil Structure Foundation

19 Problem Areas: Procurement of knock out vessels.
Procurement of control valves. Procurement of Flexible bellows. Project time line.

20 Thank You

21 Questions?


Download ppt "Process Air Compressor Knockout Replacement"

Similar presentations


Ads by Google