Download presentation
Presentation is loading. Please wait.
1
25th ALICE RRB J. Schukraft
Collaboration News ALICE Status Hardware status Commissioning activities Planning CERN-RRB 12 Nov 2008 25th ALICE RRB J. Schukraft
2
Collaboration News Elections/Nominations New Institutes
Houston (USA) EMCAL, Computing Institutes leaving BARC Mumbai (India) leaving ALICE associate member, completed its technical contribution to the PMD electronics Ongoing discussions Comsats, Pinstec (Pakistan) Physics, computing Elections/Nominations Spokesperson: JS re-elected until end 2010 Deputy Spokesperson, P. Kuijer (NIKHEF/Utrecht), 2 years ( ) Resource Coordinator: C. Decosse (CERN) (J. de Groot decided to step down end 2008) Special thanks to J. de Groot, first (and only) RC since 1996 Run Coordinator: J. Rak (Jyvaskyula) year (2009) 12/11/ th RRB J. Schukraft
3
Funding UK : Continued support from STFC for ALICE
ALICE & STAR groups merged, will apply at next funding round for Nuclear Physics grant. CERN: ‘White paper money’ CERN share of 2.5 MCHF has been agreed to complete the ALICE detector restore full DAQ capacity, complete TRD/EMCAL services & infrastructure, repay loan to CF for ZDC vacuum chamber additional contributions received (or requested) from other FA MCHF TRD 8.0 5 MEUR, contribution from Germany, agreed early 2006 EMCal 10.0 Estimated CORE equivalent, agreed by US-DOE December 2007. 1.6 1 MEUR, France, IN2P3, agreed 1 MEUR, Italy, INFN, 2008 fraction agreed C/F, C&I 0.2 Extra contribution (.249 MCHF, paid 2007) from France IN2P3 PHOS 15.0 Extra funds for two PHOS modules requested (Russia); 610 kCHF allocated in 2008 to date 12/11/ th RRB J. Schukraft
4
ALICE Detector Installation mid 2008
Complete: ITS, TPC, TOF, HMPID, FMD, T0, V0, ZDC, Muon arm, Acorde Partial installation: 1/5 PHOS 4/18 TRD 9/48 PMD 0/6 EMCAL ~ 40% DAQ/HLT ALICE Status Installation targets met by mid 2008 12/11/ th RRB J. Schukraft
5
24 April: Insertion of final TOF super module
12/11/ th RRB J. Schukraft
6
Installation of final muon chamber
12/11/ th RRB J. Schukraft
7
Installation 1st PHOS module
12/11/ th RRB J. Schukraft
8
Formal end of ALICE installation July 2008
12/11/ th RRB J. Schukraft
9
Data Taking & Commissioning
Comissioning runs (24/7) Cosmics I (2 weeks, Dec 2007) local (individual detectors) and start of global (several detectors) commissioning Cosmics II (3 weeks, Febr/Mar 2008) local/global commissioning, first few days of alignment ‘test’ run, magnet commissioning TPC was turned off after ~ 1 week (Drift HV instability, now understood & corrected) Cosmics III (since 5 May 2008 continuous operation 24/7) global commissioning, calibration & alignment production runs Injection tests TI2 dump in June , injection tests August, first circulating beam September observed very high particle fluxes during dumps and even during injection through ALICE 10’s to 1000’s of particles/cm2 with beam screens in LHC and/or TI2 decided to switch off all sensitive detectors during injection SPD, V0 always on (trigger), SSD, SDD, FMD, T0, HMPID, muon trigger occasionally (beam was useful only for a subset of detectors !) > 6 months 24/7 running ~ 6700 shifts (~ 30 MY) + 2800 ‘on call’ 12/11/ th RRB J. Schukraft
10
Injection tests SPD hits versus bunch intensity (beam through ALICE)
FMD event display (1 bunch through ALICE, > hits) FMD hits versus SPD hits (beam through ALICE) SPD/SSD, Sunday, 15.6 Dump on TED 12/11/ th RRB J. Schukraft
11
First beam 10th September
SPD hits on , shortly after 9 am V0 hits on , shortly after 9 am 12/11/ th RRB J. Schukraft
12
Luminosity monitor (V0)
Double turn, beam 1 back at point 2 ! Single turn 12/11/ th RRB J. Schukraft
13
Auto-correlation for SPD trigger, with multi-turn correlations
Beam pick-up T0 SPD V0 Auto-correlation for SPD trigger, with multi-turn correlations (3564 bunch crossings) Trigger timing (before alignment) versus bunch number single shot for SPD, V0, beam-pickup BPTX, T0 triggers 12/11/ th RRB J. Schukraft
14
First interactions 12th September
Circulating beam 2: stray particle causing an interaction in the ITS ITS tracks on 7 reconstructed tracks, common vertex 12/11/ th RRB J. Schukraft
15
TPC Commissioning TPC up and running since end 2007
chamber+FC, gas system, cooling, FEE, Laser, DCS, DAQ, HLT,… noise reduction: modify PS (some occasional excess noise remains in outer parts) replaced several faulty electronics components (FEE, RCU, ..) some IROC decoupling capacitors show leakage after months of operation already several replaced, currently 2 ‘weak’ left + 2 IROCs not operational difficult or no access to parts of the TPC => modify cabling during shutdown TDR: s ~ 1 measured: 12/11/ th RRB J. Schukraft
16
TPC Calibration Gain, drift velocity, ExB, alignment,…
Krypton Gain Calibration Gain, drift velocity, ExB, alignment,… Laser, Cosmics, Krypton, drift velocity monitor, gas composition, T/P sensors .. ExB scan (Laser tracks) Drift velocity from Laser (~ 2x10-4) Krypton Calibration chamber gain variation (s ~ 8%) 12/11/ th RRB J. Schukraft
17
TPC Performance First preliminary results from cosmics
Momentum Resolution (uncalibrated) First preliminary results from cosmics dE/dx resolution (PPR goal: ~ 5.5%) < 6% pt resolution (PPR goal: ~ 10 GeV) ~ 10 GeV w/o calibration Particle Identification 12/11/ th RRB J. Schukraft
18
Silicon: ITS & FMD status
all silicon detectors fully commissioned (Det.,DAQ, DCS, cooling, ..) pixel trigger worked ‘out of the box’ and was heavily used individual bad/noisy channels ~ within specs (<0.15% SPD, FMD, 1.5% SSD, 3% SDD) lost some modules/half-ladders (tracking is sufficiently redundant, so physics impact is minor) (ITS detectors could only be fully tested after cabling on miniframe, i.e. w/o access) SPD: 12.5% half-staves (2 connection, 13 insufficient cooling flow) plan to improve flow regulation for individual circuits next WS SDD: 5% modules (few can be recovered during shutdown) SSD: 3.8% modules, 9% half-ladders mostly Sintef ladders which developed excessive bias current (8/22) FMD: S/N ~ 30 FMD3-o SSD SSD: S/N ~ 40 FMD2-o FMD 1-i FMD 2-i FMD 3-i 12/11/ th RRB J. Schukraft
19
ALICE Inner Tracking System: Alignment with Cosmics
Silicon Pixel Detector (SPD): ~10M channels 240 sensitive vol. (60 ladders) Silicon Drift Detector (SDD): ~133k channels 260 sensitive vol. (36 ladders) Silicon Strip Detector (SSD): ~2.6M channels 1698 sensitive vol. (72 ladders) ITS total: 2.2k alignable sensitive volumes 13k degrees of freedom Alignment using tracks and Millepede program in a hierarchical approach ~50k cosmic for alignment collected since end of May (~0.1 Hz), using Pixel trigger ITS Event display Distribution of clusters in the 6 layers
20
ALICE Inner Tracking System: Alignment with Cosmics
Preliminary results for SPD (Pixels, ~ 80% prel. aligned): Residual misalignment < 10 m (detector resolution = 12 m in r ) SSD & SDD, as well as ITS/TPC alignment has started (smaller coverage) Track-to-“extra clusters” distance in transv. plane (sensor overlap) Track-to-track (top vs bottom) distance in transv. plane before alignment before alignment after alignment after alignment = 55 m (vs 40 m in simulation without misalignment) = 21 m (vs 15 m in simul. without misalignment)
21
Other Detectors TOF: 2/3 fully commissioned (3 finishing gas tests, several missing DC-DC converters) TOF trigger works very well (noise factor 2 better than in tests) TRD: 4 SM’s installed (2 final ones), noise and L1 trigger ok HMPID: fully commissioned, noise at specs PHOS: 1 module fully commissioned, trigger com. ongoing occasional noise pickup (depends on the day..) Muon tracking: ~ 70% commissioned, noise problem cured in all but station 3 Muon trigger, V0, T0, ACORDE, ZDC: all up and running TRD cosmic HMPID cosmic event (no calib/slewing, offset correction etc..) Oct 08 Jul 08 TOF raw spectra (no calib/slewing, offset correction etc..) 12/11/ th RRB J. Schukraft
22
Online Continuous online operation since March (24/7)
DAQ: 40% HW installed, stable operation up to 500 MB/s transfer, data taking > 3 kHz complete HW for 2009 DCS/ECS: all essential functionality operational, continuous improvement in functionality some problems encountered with scalability (mostly resolved) CTP: some problems with spurious triggers resolved, running well HLT: 500 CPU’s, very successful operation (online reconstruction, data reduction) complete HW in 2009 Aggregated cumulative time in the global partition 12/11/ th RRB J. Schukraft
23
DAQ: Global Partitions
Number of detectors in the global partition Now also runs with large number of detectors run stable over hours with realistic trigger sequences ! (Useful cosmic data taking done for subsets of detectors working with different triggers) 12/11/ th RRB J. Schukraft
24
Offline & Physics ‘commissioning’
exercise data transfer to T0/T1, prompt reconstruction, prompt calibration, data Q/A Concentrating on early physics at 900 GeV and 10 TeV global event features, pt spectra, particle rations, baryon transport, …. detailed trigger & data taking scenario elaborated fast calibration/alignment/reconstruction prepared daily meetings of ‘first physics task force’ to exercising analysis until mid Sept. 12/11/ th RRB J. Schukraft
25
Computing Computing Resources (updated after CRSG review)
ALICE deficit in 2009 : ~ 25 CPU% , 60% Disk (error found by CRSG), 50% Tape ‘optimistic running scenario’ 107 s, but ALICE pp data depends much less on it ! need 109 pp MB events/year, i.e. Hz or Hz addressing the shortfall adding resources: partially successful and ongoing in discussion with a number of specific partners redistribution of existing resources between experiments (integral LHC resources much more adequate than differential distribution) CRSG: ‘A very limited degree of redistribution of resources may be advisable in 2009’ ‘living with less’: scenarios & physics impact under discussion with LHCC a modest shortfall may be accommodated with a modest loss of physics … 24/10/ rd RRB J. Schukraft 12/11/ th RRB J. Schukraft 25
26
Planning Until 12 October Medium term (until LHC restart in 2009)
continue cosmic running & consolidation of online software Medium term (until LHC restart in 2009) ‘shutdown mode’, start with activities planned for winter shutdown re-arrange cabling on mini-frame (ITS,TPC) to allow better access to electronics major activity, requiring > 4 months of work both underground & surface detector consolidation TPC capacitors; recover some ITS modules, improve SPD cooling, … detector installation (TRD, PHOS, PMD, EMCAL), … 3 PHOS, 6-8 TRD modules, 2 EMCAL modules, complete PMD Long term: complete detector PMD (2008), DAQ/HLT(2009),TRD (2009), PHOS (2010/11), EMCAL (2010/11) 12/11/ th RRB J. Schukraft
27
Summary Installation: Commissioning and initial calibration/alignment
met all installation goals by mid 2008 Commissioning and initial calibration/alignment went rather well, sometimes even better than expected (e.g. TPC, SPD alignment + trigger) some (mostly minor) hickups / problems (noise, lost channels) / bug fixing to be improved: access to TPC for repairs/FEE exchanges cooling flow of SPD Detector performance better – within - very close to specs (at least as far as could be verified with cosmics) After > 15 years of designing & constructing ALICE we do have a working experiment ready for physics. Thanks to all the Funding Agencies who have made this possible with their strong support over 1½ decades ! 12/11/ th RRB J. Schukraft
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.