1 Project Headlands, Phases 1 and 2
Presentation to Sausalito City Council February 26, 2013 Preservation of 7 metal bridges

2

3 Phase1 Summary: Schedule: 2010-2011 – Complete Budget – 8.76 million
East, Conzelman, McCullough, Field Roads and Danes Drive Restoration of “erosion fingers” on Conzelman Construction of 5 overlooks on East Road and Conzleman Northwest Bridge and Battery Alexander parking lots Improved parking, bike, public transit and disabled access Schedule: – Complete Budget – 8.76 million

4 Watertower stabilization
Building 64 bridges Dock Guartower

5

6 $1,615,181.00 -steel replacement equipment issues -roof eave angle rework

7 7

8 $1,615,181.00 -steel replacement equipment issues -roof eave angle rework

9

10 $1,615,181.00 -steel replacement equipment issues -roof eave angle rework

11 $1,615,181.00 -steel replacement equipment issues -roof eave angle rework

12 $1,615,181.00 -steel replacement equipment issues -roof eave angle rework

13

14

15 PHASE 2 SCOPE Bunker, Old Bunker, Mitchell Roads: Resurfacing, Restoration and Rehabilitation Parking Lots – Smith Road, Fort Cronkhite Annex Lot, Fort Cronkhite Lot Fort Cronkhite Parade Ground Quarry Fort Cronkhite Dirt Overflow Lot restoration Guardrail replacement at East Bunker Road  Alexander Avenue Left turn lane extension/MSE wall installation

16 SCHEDULE BUDGET Bunker/Mitchell/Old Bunker: April 2013-June 2014
Alexander Ave/Quarry: April 2013-June 2013 BUDGET $11,257,789.00 Preservation of 7 metal bridges

17 Impacts:

18 Preservation of 7 metal bridges

19

20

21

22 Scoping, De-Scoping and Re-Scoping >>>Sequencing impacts
22

23 Traffic Control on Alexander Avenue
No road closures – 15 minute delays maximum Two way traffic maintained during non-work hours (22’ vehicles and bikes/3’ for peds) Priority given to vehicles exiting off of 101 Northbound Daytime work causing delays allowed 8am-5pm, except during paving (8am-6pm). Nightime work permitted upon approval by the CO Sunday-Friday, 9pm-6am Traffic Control Plan reviewed by FHWA, GGBHTD and NPS Alternate routes will be available and strongly suggested

24 Project Resources WEBSITE: www.projectheadlands.gov
TELEPHONE: David Dusterhoff, NPS Project Liaison


Download ppt "Project Headlands, Phases 1 and 2"