1 Injector De-cabling Project
Coordination Meeting for the PSB and PS & TT2 Facilities YETS S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team

2 Contents Scope of the project Status by machine YETS Booster Identified issues Project Information Sharing

3 Scope of the Project To identify and remove obsolete cables within the injector complex, until end of LS2. First  priority:  Identification of obsolete cables in the  Booster and SPS BA5  Partial / total removal must be decided by end September 15’ Triggered by LIU needs (room in cable containment) Second priority: SPS (BA3) Third  priority:  Identification of obsolete cables in the PS, TT2, LINACs RUN 2015 YETS RUN 2016 EYETS RUN 2017 YETS RUN 2018 LS2 BOOSTER Cable identification IDENTIFICATION Cable labelling LABELLING Cable disconnection DISCONNECTION Cable removal REMOVAL SPS BA5 LEFT REMOVAL BA5 LEFT REMOVAL BA5 RIGHT & BA3 REMOVAL PS, TT2 & Linacs TO BE DEFINED

4 Status by machine BOOSTER: Machine/area
Total number of signal and control cables Identified obsolete cables on Sept. 21st Booster 12’000 3’000 (25%) SPS – BA5 ~ 6’500 3’250 (50%) SPS – BA3 ~ 8’000 PS – CENTRE RING ~7’000 963 (14%) TT2 ~3’000 72 (2.5%) BOOSTER: 3000 obsolete cables to be removed (consolidation budget) before LS2 2800 used cables to be removed and replaced during LS2 for LIU (LIU budget) 2 big cable campaigns for EN-EL (EYETS YETS17-18 / LS2) Strong commitment from all the equipment groups during identification and disconnection stages  resources to be secured for YETS15-16

5 YETS activities @ Booster
YETS 2015/2016 = 7-8 weeks to complete: Circuit lockout Cable identification Cable disconnection System tests Current proposal: Circuit lockout: 1-2 days (depending on equipment group decision) Cable identification and disconnection for separate systems . 2 weeks in 2 shifts Check of separate systems: 2 weeks in 2 shifts Cable identification and disconnection for communication system: 2 weeks in 2 shifts Check communication system : 1-2 week in 2 shifts Schedule being prepared Operators might help.

6 YETS activities @ Booster
Access 6.00 am to pm Booster Mon 07/12/15 Fri 12.00 PS Wed 16/12/15 Fri 12.00 TT2 Tue 15/12/15 Access Control transfer CCC  CSA Mon 06.00 Fri 06.00 Draft Planning YETS : PS&TT2 EDMS PSB soon Simon Mataguez EDMS

7 Identified issues: re-commissioning
Re-commissioning after disconnection/removal – Common procedure  a dedicated sub-WG has been launched Will address the following topics: List of tests to be achieved after disconnection Procedure for already disconnected cable Procedure for not yet disconnected cable Procedure for orphan cable

8 Identified issues: Lock-out
Lock-out of all services during identification and cable disconnection in conflict with some systems Identification and cable disconnection (YETS 2015) under the responsibility of the equipment group  Up to the equipment group to decide for the lock-out of its equipment Removal of the obsolete cables (EYETS ) under the responsibility of EN-EL  general lock-out is mandatory.

9 Project Information Sharing
E-groups InjectorDe-CablingProjectMembers (members of the Injector De-Cabling Project (equipment group)) InjectorDe-cablingProjectTeam (Project team for de-cabling activities in the injectors) Indico Sharepoint site

10 THANKS FOR YOUR ATTENTION !