Developing The Project Plan
The Project Network – A Flow Chart That Graphically Depicts The Sequence, Interdependencies, And Start And Finish Times Of The Project Job Plan Of Activities That Is The Critical Path Through The Network. • Provides the basis for scheduling labor and equipment. • Enhances communication among project participants. • Provides an estimate of the project’s duration. • Provides a basis for budgeting cashflow. • Identifies activities that are critical. • Highlights activities that are “critical” and cannot be delayed. • Help managers get and stay on plan.
3
Activities Relationships
4
Example
5
Example
6
Example
7
Logical Relationship Considering Resource Constraints
8
Create A WBS
9
Types Of Activities Relationships
10
Types Of Activities Relationships
11
Constructing A Project Network
12
Constructing A Project Network
13
Constructing A Project Network (Cont’d)
14
Constructing A Project Network (Cont’d)
15
Basic Rules To Follow In Developing Project Networks
16
Activity-on-node Network Fundamentals
17
Activity-on-arrow Network Fundamentals
18
Activity On Arrow Network (AOA)
19
Activity On Arrow Network (AOA)
20
Activity On Node Network (AON)
21
Questions?!
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.