Download presentation
Presentation is loading. Please wait.
Published byMarie-Jeanne Després Modified over 6 years ago
1
SPS EYETS 2016/2017 Planning meeting (No.17) 01/03/17
David Mcfarlane EN-ACE D. Mcfarlane
2
Extended YETS Reference time: 3.5 Weeks left of access into the SPS EDMS: EN-ACE D. Mcfarlane
3
Key dates Beam off at 06:00 on Monday the 12th December
Access into BA7, TI2, TAG41, TAG42 & TI8: Monday the 12th December until Friday the 24th March 2017. 13 weeks of access. Access into BA3,4,5 & 6: Thursday the 15th December until Friday the 24th March 2017. 12.4 weeks of access. XMAS holidays: Thursday the 22nd December to Wednesday the 4th January inclusive Access into BA1 & BA2: Thursday the 5th January until Friday the 24th March 2017. 11.4 weeks of access. 4 weeks foreseen for EPC tests and cold-checkout by OP. SPS will take beam from the PS on Monday the 24th April 2017, followed by 1 week for beam setup. SPS ready to give beam to the LHC on Monday the 1st May 2017! EN/ACE/OSS BE/OP EN-ACE D. Mcfarlane
4
SPS Water Availability
Location De-min Circuit stop date Primary Water Off De-min Circuit start date Comments BA1 20/12/16 09-13/01/17 27/02/17 (Main Magnet & Power supplies for Kickers) Remaining circuit 13/03/17 BA2 14/12/16 (end) 06-10/02/17 20/02/17 Available for users from 06/03/17 BA3 19/12/16 27/02-03/03/17 (inc BEQ2 & BEQ3) 13/03/17 BB3 16-20/01/17 (except RF Skid) BA4 15/12/16 (end) 09-13/01/17 (Coldex) 17/02/17 (Main Magnet & Power supplies for Kickers) Remaining circuits 13/03/17 BA5 16/12/16 (end) 16-20/01/17 BA6 14/12/16(end) 16/12/16 – 16/01/17 (SF1) 27/02/17 Available for users from 13/03/17 BA7 12/12/17 EN-ACE D. Mcfarlane
5
EN-NC-CV-2017-057 - PREVESSIN - Distribution Eau Déminéralisée - Le 02
EN-NC-CV PREVESSIN - Distribution Eau Déminéralisée - Le de 12h30 à 17h Veuillez prendre connaissance de la note de coupure : PREVESSIN - DISTRIBUTION EAU DEMINERALISEE Installation d'un compteur ED Prévue le jeudi 2 mars de 12h30 à 17h EN-ACE D. Mcfarlane
6
Lift & Monte-charge Maintenance February & March
EN-ACE D. Mcfarlane
7
Access restrictions to areas of the SPS
Zone Dates of restricted access Comments TI2 (LHC side) 10th February to 13th March LHC cool down in sector 1-2 TT20 6th March onwards EPC tests in TT20 TAG41/TAG42 24th February to 12th April Laser tests in the AWAKE area TI8/TJ8 Access via TAG41,42 will be affected. Access via TT40 ok. EN-ACE D. Mcfarlane
8
Change of access mode in TAG41
On 24/2 PM, Vitor/Didier will perform the maintenance of the access system and put the TAG41 area in key access. From this moment on, and until 24/3 the following applies: Keys will only be given and people will only be allowed to enter during working hours and on working days (Mon-Fri, 8h-18h). No more than 24 persons can be in TAG41 at the same time. To obtain a key and access TAG41, the intervener does NOT use the intercom, but phones the CCC (SPS) directly on As the intercom still connects to the CSA (guards), the CSA guard on duty will be asked to respond to any call with the request to the intervener to phone the CCC. Signs will be put up at the turnstile with the same message. To open the material door, the same applies: phone directly the CCC. There is no on-call service for the access team or the CCC-SPS and their availability during working hours is on a best-effort basis. This means that any issue with access or laser mode occurs late afternoon (for example, when a door is forced and laser test mode is lost), the issue will only be dealt with the next day. There will be a patrol by the CCC (plus laser expert) on 28/2 PM. If a patrol needs to be redone at a later stage, it can be performed by the laser expert as was the case last year. The laser permit, currently in circulation, will need to be signed before the area can be put in laser test mode, ideally on 1/3. From 24/3, the entire SPS complex will move to key access mode, meaning all TAG41 intercom calls will be transferred automatically to the CCC, who will be available Mon-Fri 7h-20h. From 21/4 on, the SPS complex (including AWAKE) will have a 24h 7 days a week CCC support. EN-ACE D. Mcfarlane
9
Test AUG/ Access Tests (Access will be blocked)
Location AUG test Access tests Global test access safety system SPS Auto Transfer Test 4th & 5th February 16th December (15:00 to 17:00) 23rd March (chain 1) 24th March (Chain 2,3,4,5) BA1 13th February 27th January (PM) BA2 15th February 23rd January (PM) BA3 16th February 24th January (AM) BA4 ECX4 TAG42 TAG41 28th February 24th January (PM) 25th January (AM) 25th January (PM) 3rd February (PM) BA5 ECX5/ECA5 1st March 26th January (AM) 26th January (PM) BA6 20th January 27th January (AM) BA7 TT61 10th January 23rd January (AM) 30th January (AM) BA80 4th April 3rd February (AM) 13th March (1 day) “Test interverrouillage ventilation”
10
Barriers blocking access
Veuillez prendre connaissance de la note de coupure : PREVESSIN - DISTRIBUTION EAU DEMINERALISEE Installation d'un compteur ED Prévue le jeudi 2 mars de 12h30 à 17h Example EN-ACE D. Mcfarlane
11
ENNC2017-046 - ELECTRICITE - SPS - ZONE 15 - BA5 - BB5 - le 01. 03
ENNC ELECTRICITE - SPS - ZONE 15 - BA5 - BB5 - le de 7h00 à 20h00 Veuillez prendre connaissance de la note de coupure "ELECTRICITE - SPS - ZONE 15 – BA5 – BB5 - Réseaux Stable, Pulsé et Onduleur - Tests annuels des arrêts d'urgence généraux (AUG)" prévue le mercredi 1er mars 2017 de 7h00 à 20h00 EN-ACE D. Mcfarlane
12
ENNC2017-039-V2 - ELECTRICITE - PREVESSIN - ZONE 10 - 04. 03
ENNC V2 - ELECTRICITE - PREVESSIN - ZONE de 7h00 à 20h00 Veuillez prendre connaissance de la note de coupure modifiée "ELECTRICITE - PREVESSIN - ZONE 10 - BAT. 867, 864 – 865 (blocs 1 & 2), 866 – 892 (blocs 3 & 4), 904, 927, 926, 933, 880, 881, Réseaux Normal, Secours et Onduleurs - Tests annuels des Arrêts d'Urgence Généraux (AUG)" prévue le samedi 4 mars 2017 de 7h00 à 20h00 (au lieu du suite à la demande de plusieurs utilisateurs du bât. 867) EN-ACE D. Mcfarlane
13
Consignations It is the responsibility of the Equipment owner to consign any equipment that they will be working on. Please ensure that The coordination team has a copy of all main consignations of the SPS. Do not assume something is consigned. Check first. EN-ACE D. Mcfarlane
14
All people who must enter in ECA5 will access by BA5.
Access into ECA5 While the shielding wall separating ECX5 and ECA5 is removed: All people who must enter in ECA5 will access by BA5. 12th December until 15th March. In order to keep the patrol and the integrity of the area safe, the lift in ECA5 should not be used during this period, only for evacuation. By accessing through BA5, we can guarantee that people are registered and they have their SPS safety courses. A security panel with a chain will be installed at the bottom of the lift : "Do not use the lift, only for evacuation" by the TSO (Franck Bais) If one of the 3 ECA5 doors at the top of the cavern is forced, the CSA will re-arm it at the end of the day. EN-ACE D. Mcfarlane
15
SPS cleaning campaign There will be a 3 week cleaning campaign in the SPS tunnel starting on the last week of February. The current schedule is as follows: Wk.1 (27th Feb to 3rd March) BA3 and then BA4 Wk.2 (6th March to 10th March) BA2 and then BA1 Wk.3 (13th March to 17th March) BA5 and then BA6 This will leave the final week as a back-up. EN-ACE D. Mcfarlane
16
Removal of the TIDVG3 7th of February 2017
17
Réinstallation aimants coating SPS
Demi-cellule Slot / position Code TREC/MTF Equipement stockés b.867 Equipement stockés sur place Installation aimant prévue 505 QD.50510 SPQM___FWP Quadrupole principal Done MDV BPV drift BPM + correcteur + chambre à vide drift 02-Mar 507 QD.50710 SPQM___FWP LOD.50702 SPLODN_FWP Octupole MDV BPV drift 420 LSF.42005 SPLSFN_FWP Sextupole 07-Mar MDH BPH.42008 BPM + correcteur 422 LOF drift SPLOFN_FWP CR Octupole + chambre à vide drift 06-Mar MDH BPH.42208 424 GNA (incl. LSEN LSF.42405) CR (incl. SPLSEN_FWP SPLSFN_FWP ) Poutre SSS avec 2 sextupoles MDH BPH.42408 426 LOF.42602 SPLOFN_FWP 03-Mar LSF.42605 SPLSFN_FWP MDH BPH.42608 428 LOF drift SPLOFN_FWP CR MDH BPH.42808 430 MDH BPH drift 432 LSF drift SPLSFN_FWP CR Sextupole + chambre à vide drift 01-Mar MDH BPH.43208 434 MDH BPH drift 500 LSF drift SPLSFN_FWP CR MDH BPH.43408 EN-ACE D. Mcfarlane
18
IMPACT Statistics (EYETS-SPS-2016/2017)
Number of IMPACTS “Waiting for Approval” Last week:28 Today:22 Number of IMPACTS “Approved” Last week:31 Today:29 Number of IMPACTS “In Progress” Last week:141 Today:145 Number of IMPACTs “Late” Last week:115 Today:120 Number of IMPACTs “Closed” or Finished” Last week:208 Today:228 Total Number of IMPACTs Last week:523 Today:544 EN-ACE D. Mcfarlane
19
Please fill out your IMPACTs correctly!!!!!
Correct intervention period: DO NOT LEAVE IT BLANK!!!!!!! (EYETS-SPS-2016/2017) Do not leave proposed schedule Blank!!!! I am not psychic!!! If you clone an IMPACT: Check you have the correct responsible person!! Check the dates are correct Check the location is correct Check the description is correct (not just the title) Basically, CHECK EVERYTHING!!!! If you have already completed your IMPACT them please check that the dates in IMPACT match that of your planning and are also correct in the master schedule planning. If they are not then please contact me so that we can rectify the problem. WHEN YOU HAVE COMPLETED YOU WORKS DO NOT FORGET TO CLOSE YOUR IMPACT!!!!!!! EN-ACE D. Mcfarlane
20
Don’t forget to add Vacuum to your IMPACT if you need them.
Supervisor: Chiara Pasquino e-group: te-vsc-ivm-LS1 40-30: Alain Grimaud 40-30: Frederic Vial 40-30: Lindsay Morgan Fabre 40-30: Olivier Pangolin EN-ACE D. Mcfarlane
21
PLANNING EN-ACE D. Mcfarlane
22
SRRs and ECRs for the SPS
SPS planning and coordination meeting for EYETS 2016/2017 SRRs and ECRs for the SPS Sonia Bartolomé Jiménez EN-ACE-CL – 8th February 2017
23
SRRs and ECRs: reminder
All changes to the machine that will impact the beam shall be documented by SRRs/ECRs: SRR: Space Reservation Request (“light ECR”) ECR: Engineering Change Request Templates available on: To be sent to the SPS configuration manager: or Sonia Bartolomé Jiménez EN-ACE-CL – 8th February 2017
24
SPS ECRs for EYETS 2016/2017: status
LIU-SPS project EDMS Number Title Doc type EDMS Status Authors SPS-BCTW-EC-0001 SRR: New Fast BCT for SPS LSS5 (EYETS ) SRR Accepted (ECR) Lars Soby (BE/BI) SPS-V-EC-0005 Modification of the SPS sectorization in long vacuum sectors (arcs) ECR Chiara Pasquino (TE/VSC) SPS-VF-EC-0001 SPS flange impedance reduction in EYETS Jaime Perez Espinos (TE/VSC) SPS-BCTW-EC-0002 BCTW for LSS5 of the SPS ring (EYETS ) SPS-VC-EC-0001 SPS amorphous carbon coating in EYETS Mattias Van Gompel (TE/VSC) SPS-JHCAA-EC-0001 Construction of concrete support structure for new LIU beam dump in SPS ECX5 Approval Accepted Richard Morton (SMB/SE) SPS-BLMD-EC-0001 Installation of a Beam Loss Diamond Detector in SPS LSS1 during EYETS Lars Jensen (BE/BI) No Change SPS-JHCAA-EC-0001 and SPS-BLMD-EC-0001 approved at the 192nd IEFC meeting. Released version 1.0 being prepared. Sonia Bartolomé Jiménez EN-ACE-CL – 8th February 2017
25
Sonia Bartolomé Jiménez EN-ACE-CL – 8th February 2017
SPS ECRs for EYETS 2016/2017: status Non LIU-SPS project EDMS Number Title Doc type EDMS Status Authors SPS-LJ-EC-0004 Installation of a crab-cavity cryomodule and related infrastructure in LSS6 SRR Accepted (ECR) Giovanna Vandoni (BE/RF) ACC-RFB-EC-0001 New Table Format for Function Generator/Controllers (FGC) ECR Quentin King (TE/EPC) SPS-BSHV-EC-0002 Removal of the scraper BSHV from LSS5 of the SPS Edouard Grenier-Boley (EN/STI) SPS-LJ-EC-0006 HL-LHC Crab-cavity infrastructure in SPS: tunnel areas (EYETS ) SPS-TIDVG-EC-0001 Modifications to the TIDVG during 2016 Paula Rios Rodriguez (EN/STI) SPS-HJP-EC-0002 Installation of a protective barrier for SPS sectors 430 and 431 ground supports Roberto Salemme (TE/VSC) SPS-Y-EC-0001 Radiation monitor interlocks at the SPS Markus Widorski (HSE/RP) SPS-BLM-EC-0001 Pilot installation of Beam Loss Monitors along the COLDEX experiment SPS-B-EC-0004 Removal of obsolete BI equipment in LSS4 of the SPS Approval Accepted Enrico Bravin (BE/BI) SPS-QRWPU-EC-0001 Installation of two Helium 2K Pumping Units in LSS6 SPS (BA6) Under Approval Giovanna Vandoni (BE/RF) No Change New ECR (SPS-QRWPU-EC-0001) Under Approval describing the installation of two helium 2K pumping units and other equipment in BA6. Approval deadline: Sonia Bartolomé Jiménez EN-ACE-CL – 8th February 2017
26
External Visitors If you have any external personnel needing to access the SPS for visits before starting works then you need to read the following document: "Etapes à suivre pour organiser des visites professionnelles dans les installations faisceaux" by CHRISTELLE GAIGNANT Link: EN-ACE D. Mcfarlane
27
Access rights and safety equipment
EVERYONE who enters the SPS MUST have the following: Completed the correct courses. (sir.cern.ch) CERN Safety Introduction. Electrical Safety Awareness. (19 choices) Self Rescue Mask Training. (4 choices) CERN – Beam Facilities. SPS – Machine. The correct access authorisation (via EDH). CHECK YOUR ACCESS RIGHTS HAVE NOT EXPIRED!!!! Zone Code “SPS” for access into the SPS Zone Code “NA_TARG” for access into BA80 Zone Code “TAG41 - AWAKE (ex-CNGS) (TAG41)” for access into the old CNGS areas Zone Code “SPS-KN-000” for “Autorisation conduite RTL” Zone Code “SPS-KN-001” for “SPS Shutdown Padlock” (only used during Long Shutdowns) Safety shoes. Biocell. Electronic dosimetre. Passive dosimetre. (All contractors must have an additional company passive dosimetre!!) Helmet plus Light. A valid approved IMPACT. (with their name included on this IMPACT) They must know the number of this IMPACT. Please note that personnel are not allowed to work in the tunnel alone!! EN-ACE D. Mcfarlane
28
Important Contacts Useful Contact Numbers SPS Coordination Team
David MCFARLANE Franck BAIS – Aurelio Berjillos BARRANCO Control Room SPS CCC – (70475 to access TAG41) TI CCC – 72201 CSA RP Christophe Tromel – Angelito Herve – Nadine Conan (BA1) – Kurt Weiss (BA7) EROS Engineering Referent for Operational Safety Emmanuel Paulat – John Etheridge EN-ACE D. Mcfarlane
29
Round Table (1) Group Contact Persons Comments EN/EL EN/CV EN/STI
Guillaume Gros Denis Ribiollet Jeremy Blanc EN/CV Bill Bannister (Water) Vivien Koutcheroff (Ventilation) EN/STI Jerome Lendaro Simone Montesano TE/MSC Jeremie Bauche Pascal Catherine TE/EPC Karsten Kahle (High power) Gilles Le Godec (Medium power) TE/VSC Jose A. Ferreira Anthony Harrison Chiara Pasquino TE/ABT Francesco Castronuovo (Kickers) Gael Bellotto Cedric Baud (Septas) BE/RF Eric Montesinos Christophe Renaud Gino Cipolla BE/BI Raymond Veness Morad Hamani BE/CO Magnus Bjork IT/CS Maryse Da Costa EN-ACE D. Mcfarlane
30
Round Table (2) Group Contact Persons Comments BE/ICS HSE/RP EN/ACE
Didier Vaxelaire (Access) Denis Raffourt (Fire detection) HSE/RP Christophe Tromel Angelito Herve EN/ACE Patrick Bestmann (Survey) Sonia Bartolomé (Integration) Fred Galleazzi (Intergration) Emmanuel Paulat (Safety) EN/HE Patrick Vallet (Transport) Nicolas Perez (Lifts) BE/OP James Ridewood Stephane Cettour Cave SMB/SE Alejandro Martinez Selles Crab Cavity Giovanna Vandoni EN-ACE D. Mcfarlane
31
A.O.B. EN-ACE D. Mcfarlane
32
Useful websites Link to SPS planning meetings on INDICO
Link to the SPS planning Roadmap: Schedule beyond LS1 Next meeting 08/03/2017 EN-ACE D. Mcfarlane
33
EN-ACE D. Mcfarlane
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.