Cost overruns on transport infrastructure projects Marion Terrill

Similar presentations


Presentation on theme: "Cost overruns on transport infrastructure projects Marion Terrill"— Presentation transcript:

1 Cost overruns on transport infrastructure projects Marion Terrill
Project Controls Conference 2017

2 15 years 542 completed projects +294 cancelled projects $28 billion
The Grattan Institute has found that Australia has a cost overruns problem Roads to riches: Better transport investment Cost overruns in transport infrastructure 15 years 542 completed projects +294 cancelled projects Over... $28 billion 24% of promised costs Cost overruns cost…

3 90% of cost overruns are attributable to the 17% of projects with huge cost overruns
Frequency of cost overruns as a proportion of all projects, per cent Cost underruns On budget Cost overruns Value of cost overruns as a proportion of total cost overruns, per cent Notes: Australian transport projects completed between 2001 and “Cost differences” is defined to refer to cost underruns and cost overruns collectively. Source: Investment Monitor, Grattan analysis

4 Cost overruns are likely higher than we report
Average cost overrun rates as a proportion of initial costs by project stage, per cent Assuming the average rate of overrun where not observed directly Assuming no cost overrun occurred where not observed directly Notes: Australian transport projects completed between 2001 and Source: Investment Monitor, Grattan analysis

5 74% of cost overruns are attributable to the 32% of projects with costs announced prematurely
Projects with first cost announced during construction Projects with first cost announced alongside a budget commitment Projects with first cost announced prior to a budget commitment Notes: Australian transport projects completed between 2001 and Source: Investment Monitor, Grattan analysis

6 Projects announced earlier have larger cost overruns at all stages of the project lifecycle
Average project size of each cohort by project stage, $2016 millions Projects with first cost announced prior to a budget commitment Projects with first cost announced as a budget commitment, prior to construction commencing Projects with first cost announced during construction First public cost announcement Formal budget commitment Commencement of construction Completed Notes: Australian transport projects completed between 2001 and Source: Investment Monitor, Grattan analysis

7 Few projects are cancelled once announced
Proportion of projects cancelled at each project stage, per cent Notes: Australian transport projects completed between 2008 and Source: Investment Monitor; Grattan analysis.

8 Most cost overruns are not attributable to scope changes
Average proportion of cost overruns by cause, per cent 11% directly attributable to scope changes 89% attributable to other causes Notes: Australian transport projects completed between 2008 and Source: Grattan analysis of 51 projects valued above $100m

9 This report analyses nine times more completed projects than previous studies
Sample sizes of Australian studies on transport infrastructure cost overruns Notes: Australian transport projects completed between 2001 and Source: Investment Monitor, Grattan analysis and cited studies

10 Most money committed during the 2016 election was not for Infrastructure Australia approved projects
Proportion of transport infrastructure election commitments by IA approval status, per cent Not on IA priority list Yet to be assessed for IA priority list On IA priority list Notes: Includes projects where a specific dollar amount could be discerned from campaign material or, in the case of the Coalition, from the 2016–17 budget papers. Excludes projects for which construction had already commenced by June Source: Liberal Party (2016); Australian Labor Party (2016b); Australian Greens (2016a); Treasury (2016) Treasury (2014); Infrastructure Australia (2016d); Grattan analysis.

11 Experts systematically underestimate the likelihood of cost overruns
Average magnitude of cost overruns on Australian transport infrastructure projects completed between 2001 and 2015 by mode, per cent Underruns On budget Overruns Assumed prevalence Observed prevalence Notes: The assumed prevalence of cost overruns is inferred from the common representation of cost risk as symmetrically distributed in cost estimation guidance. See appendix B.2.5 of Terrill and Danks (2016) for further details. Source: Australian risk management guidelines listed in Appendix A.4 of Terrill and Danks (2016), and Investment Monitor; Grattan analysis.

12 Low provision for ‘worst case’ cost outcomes
Large projects currently under development or construction

13 Both road and rail projects suffer from cost overruns, but at different stages
Average magnitude of cost overruns on Australian transport infrastructure projects completed between 2001 and 2015 by mode, per cent Road projects Rail projects Contracted to completed First announced to contracted Overall Notes: Australian transport projects completed between 2008 and Source: Investment Monitor; Grattan analysis.

14 Big projects have larger cost overruns
Prevalence of cost overruns Magnitude of cost overruns

15 Australia’s guidelines on risk measurement do not recommend any approach consistently
Proportion of transport infrastructure risk assessment guidelines recommend the use of each key risk assessment tool, per cent Notes: Prevalence rates were calculated over the subsample of each of these guidelines which provided quantitative risk measurement guidance. Source: Australian risk management guidelines listed in Appendix A.4 of Terrill and Danks (2016), and Investment Monitor; Grattan analysis.

16 Small contingencies can achieve a lot when they are managed at the portfolio level
Value of the contingencies to ensure projects will finish within initial budget commitments with 90 per cent probability, per cent of initial project value 70% 24% 70% 24% Managed at the project level Managed at the portfolio level Notes: Australian transport projects completed between 2008 and Source: Investment Monitor; Grattan analysis.


Download ppt "Cost overruns on transport infrastructure projects Marion Terrill"