San Mateo Bridge Replacement Project Caltrain Replaces Four 100-Year-Old Rail Bridges
May 2, 2013
2
The Four Bridges
3
Why do these bridges need to be replaced?
Rapidly aging 100-year-old rail bridges Do not meet current seismic safety standards Increased height requirements for vehicle clearance
4
When will this work begin?
Site Clearing: Start: November 2013 Duration: 3 months Construction: Start: April 2014 Duration: 2 years Road Closures: Start: Late 2015 into 2016 Duration: 8 weeks per street
5
Station Topics Project Overview Bridge/Berm Construction Phasing
Vegetation Impacts Construction Impacts