Activités SPS pour BE/ICS Systèmes d’Alarmes YETS 2017-2018
Nicolas Broca / Pierre Durand on behalf of AS Team 11/10/2017 EDMS: Nicolas Broca / Pierre Durand BE-ICS YETS 2017/2018 Coordination Meeting, 11th October 2017 BE/ICS/AS activities
2
Sommaire ODH DETECTION (Nicolas Broca) FIRE DETECTION (Pierre Durand)
Work for SPS Crab Cavity Test Stand FIRE DETECTION (Pierre Durand) Fire Detection and Evacuation Maintenances Sprinkler Maintenances Nicolas Broca / Pierre Durand BE-ICS YETS 2017/2018 Coordination Meeting, 11th October 2017 BE/ICS/AS activities
3
ODH Detection for SPS Crab Cravity Test Stand
Nicolas Broca / Pierre Durand BE-ICS YETS 2017/2018 Coordination Meeting, 11th October 2017 BE/ICS/AS activities
4
ODH Detection for SPS Crab Cavity Test Stand
Conceptual Design (integration ongoing) Installation of 18 ODH detectors and 23 Flashing lights panels in: BA6 lift area, 2 detectors + 2 flashs/sirens TA6 tunnel and technical gallery, 7 detectors + 7 flashs TS6+ from DCUM 6405, 6 detectors + 10 flashs TS6- to DCUM 6000, 4 flashs Planning to Validate & Resources 17 days of work – 2 FTE contract FSU GS04 Step 1, VIC scheduled on December 21st Step 2, Installation of equipment's – 10 days EN/EL pull our cables in parallel Step 3, Cabling of equipment's – 5 days Step 4, Tests and commissioning – 2 days Step 5, HSE acceptance test – ½ day 2 control racks to setup BA6 lift area 2 ODH flashs/sirens TA6 7 ODH + 7 flashs TS6- 4 flashs TS6+ 6 ODH + 10 flashs Nicolas Broca / Pierre Durand BE-ICS YETS 2017/2018 Coordination Meeting, 11th October 2017 BE/ICS/AS activities
5
ODH Detection for SPS Crab Cavity Test Stand
Planning Proposal (to validate with SPS coord, EN/EL and CC project) Installation of equipment's – from December 19th to January 15th Cabling of equipment's – from January 16th to January 22nd Depend on EN/EL campaign progress Tests and commissioning – from January 29th to January 30thnd HSE acceptance test – TBD Needs and Impacts EN/HE to help positioning racks in BA6 EN/EL to pull our cable asap Handling co-activity in CC area, shifted work Technical commissioning require to activate ODH flash Warning message in acces point sufficient or shifted work? HSE acceptance test require to activate evacuation siren No acces to PA6 for half day (4 to 6 hours) Nicolas Broca / Pierre Durand BE-ICS YETS 2017/2018 Coordination Meeting, 11th October 2017 BE/ICS/AS activities
6
Fire Detection Maintenances
Nicolas Broca / Pierre Durand BE-ICS YETS 2017/2018 Coordination Meeting, 11th October 2017 BE/ICS/AS activities
7
(VIC à réaliser, prévoir une journée pour l’ensemble du SPS )
Maintenance Fire detection & Evacuation Title Location Duration Planning Impact Needs PLAN Détection Incendie et évacuation des systèmes existants Maintenance annuelle (exigence légale) BA1 - SFDIN-00258, SESEV-00020 BA2 - SFDIN-00254, SESEV-00021 BA3 - SFDIN-00262, SESEV-00022 BA4 - SFDIN et 286, SESEV et 108 BA5 - SFDIN-00259, SESEV-00024 BA6 - SFDIN-00260, SESEV-00_025 BA7 - SFDIN-00261, SESEV-00026 SPS souterrain et TT, partout 5 semaines 1 équipe E095 Début YETS Test de sirènes tôt le matin ou le soir – sans personne dans la zone concernée (VIC à réaliser, prévoir une journée pour l’ensemble du SPS ) BA6 - SFDIN-00260, SESEV-00025 SPS surface: BA’s, BBs, etc. Nicolas Broca / Pierre Durand BE-ICS YETS 2017/2018 Coordination Meeting, 11th October 2017 BE/ICS/AS activities
8
Maintenance SPRINKLER
Title Location Duration Planning Impact Needs PLAN Systèmes Sprinklers existantes Maintenance bi-annuelle BA1 – SXSPR-00001 BA2 - SXSPR-00002 BA3 - SXSPR-00003 BA4 - SXSPR-00004 BA5 - SXSPR-00005 BA6 - SXSPR-00006 BA7 - SXSPR-00007 SPS BA’s et shafts 1/jour par BA Viansone Securiton YETS En dehors de la maint. détection incendie En dehors maint. eau incendie - CV Nicolas Broca / Pierre Durand BE-ICS YETS 2017/2018 Coordination Meeting, 11th October 2017 BE/ICS/AS activities