Presentation is loading. Please wait.

Presentation is loading. Please wait.

LHC-EYETS 2016/17 Coordination meeting #18

Similar presentations


Presentation on theme: "LHC-EYETS 2016/17 Coordination meeting #18"— Presentation transcript:

1 LHC-EYETS 2016/17 Coordination meeting #18
14th February, 2017 EYETS follow up – Marzia Bernardini

2 LHC machine Schedule for LHC EYETS EDMS 1756963; INDICO 613945
EYETS : General infos LHC-EYETS completed on Sunday 30th April. All the activities must be completed by Friday 14th April IMPACT: intervention period EYETS-LHC-2016/17 Phone ‘piquet’: OSS website (planning, constraints, …): INDICO: The access during the AUG test is according to a list  any access IN SURFACE need to be declared  NO access underground except EN-EL and EN-CV Unlock out W14 (3rd April - 7th April) LHC back to BE-OP on Friday 14th April LHC machine Schedule for LHC EYETS EDMS ; INDICO

3 Validation of level gauge klystron/RF cryo-module
Proposed dates from coordination  week 8 Proposed date from TE-CRG  15th February (Tomorrow) NO ACCESS between green doors Activities schedule: Depressurising line C from 8:30 to 10:00 to 1.1b and then keeping line C to that pressure (return flow line D) Lock out of CV933 removed (only this valve) (1/2h) Then CV933 will be opened slowly to equilibrate pressure if any..(1/2h) Then positioner will be replaced + a ‘re-initialisation’ will be done (2-3h) And finally valve will be lock out again. IMPACT on BE/BI activities  BSRT LHC machine Schedule for LHC EYETS EDMS ; INDICO

4 Fire detection and ODH flash
Fire detection in RA67  Installation of a fire detection tube, needed: VIC Work authorisation (Helium spill risk) Electrical lock out Cryogenics lock out ODH flash replacement in UJ14, ITs area  Move position in the transport zone? LHC machine Schedule for LHC EYETS EDMS ; INDICO

5 Survey measurement w/o ventilation s.7-8
Test performed yesterday Shielding in UJ 84 closed Ventilation doors in LSS7R opened residual air flow 0.4 m/s Request from EN-ACE-SU to CLOSE the ventilation door in LSS7R  Safety authorisation required LHC machine Schedule for LHC EYETS EDMS ; INDICO

6 LHC machine Schedule for LHC EYETS EDMS 1756963; INDICO 613945
New request, BGI in LSS4R Replacement of BGI in LSS4R - Following the lasted investigations on the BGIs, it might be suggested that the 2 BGI chambers in 4 Right (D5R4) are replaced with drift tubes as done for D5L4. Please, can you let us know: 1. Are the replacement chambers ready of installation? If not, what is that status and when could they be installed? 2. What would be the impact on the planning if these BGIs were replaced with drift tubes? - Warm magnet lockout needed LHC machine Schedule for LHC EYETS EDMS ; INDICO

7 LHC machine Schedule for LHC EYETS EDMS 1756963; INDICO 613945
Non conformities BI in UJ22 Un diamond BLM a été installé durant un des TS-2016, selon ECR LHC-BLM-EC-0005 Il avait été validé que ce BLM soit installé coté passage. Il a finalement été installé à l’arriere, sous le BLM existant. BI RA43 Le BGV et ses accessoires ont été installés durant le LS1, selon ECR LHC-BGV-EC Les 2 tuyaux d’alimentation en gaz, reliant le rack en UA43 a la boite en RA43, n’ont pas été installés comme prévu ce qui obstrue la visée géomètres. Les 2 tuyaux reviennent à plat a 2390 du sol, soit au travers toujours de la même visée. Enfin, les 2 tuyaux remontent plus tôt que prévu, juste en face et tres proche du soufflet de la QRL, et le support au plafond n’a pas été intégré, et 1 de ses branches ne sert à rien. BLM on D1 in LSS1 and LSS5  decision to NOT re-install the BLMs LHC machine Schedule for LHC EYETS EDMS ; INDICO

8 LHC-EYETS: electrical constraints
AUG TEST Point Day LHC1 + ATLAS 6th January BA1 13th February LHC18 + SM18 10th January BA2 15th February LHC2 + ALICE 16th March BA3 16th February LHC3 + PM32 16th January BA4 + CNGS 28th February LHC4 8th Mars BA5 1st Mars LHC5 + CMS 5th January BA6 20th January LHC6 9th Mars BA7 LHC7 7th Mars LHC8 27th February PS + PSB 14th & 15th January Prevessin 18th February BA80 4th April Meyrin + Adm. 4th January BA81 5th April Meyrin W. + ISR 28th January BA 6th April No Access in the Surface, Underground Areas and Underground adjacent access points Under discussion TEST SECOURS (10min) AUTO TRANSFERT TEST All points on 9th January (6am – 6:10am) No access in LHC1, LHC18, BA6 & BA7 on 4th and 5th February (Saturday & Sunday) LHC machine Schedule for LHC EYETS EDMS ; INDICO

9 LHC-EYETS: Maintenance
CV Maintenance Point Weeks Start Finish LHC1 50 – 51 – 1 – 2 15th December 11th January LHC2 27th February 19th Mars LHC3 8 10 6th March 10th March LHC4 2 – 3 – 4 10th January 27th January LHC5 49 – 50 – 51 – 1 5th December 6th January LHC6 6 – 7 – 8 6th February 24th February LHC7 9 3rd March LHC8 3 – 4 – 5 16th January 3rd February Cryo Maintenance Point Weeks Start Finish LHC1 2 – 3 – 4 11th January 24th January LHC2 11-12 13th March 24th March LHC4 9 – 10 27th February 10th March LHC6 6 – 7 – 8 – 9 6th February 3rd March LHC8 7 – 8 13th February 24th February LHC machine Schedule for LHC EYETS EDMS ; INDICO

10 No Access in the Surface & Underground Areas
Safety Test & DSO Test No Access in the Surface & Underground Areas Point Week SAFETY TEST LHC1 + ATLAS 6 06/02/2017 LHC2 + ALICE 7 07/02/2017 LHC3 1 3/01/2017 LHC4 51 22/12/2016 LHC5 + CMS 52 28/12/2016 LHC6 27/12/2016 LHC7 4/01/2017 LHC8 + LHCb 2/01/2017 COMPLETED DSO TEST All points  7th & 8th April LHC machine Schedule for LHC EYETS EDMS ; INDICO

11 LHC-EYETS: constraints W7 and W8
LHC machine Schedule for LHC EYETS EDMS ; INDICO

12 LHC-EYETS: constraints W7 and W8
LHC machine Schedule for LHC EYETS EDMS ; INDICO

13 LHC-EYETS: constraints W7 and W8
LHC machine Schedule for LHC EYETS EDMS ; INDICO

14 Safety aspects: VIC follow up
Activity Group Location 7th February Cabling & Fibre EN-EL-FC Gael Girardot Antonio Gonzales LSS8 LSS5R LSS2R LSS6 LSS7 Arc 2-3 (for TE-MSC thermoswitch) VIC Approved VIC Approved VIC Approved VIC Approved VIC not needed VIC to be organised ALFA shielding installation EP- Alfa Mickael Lazzaroni LSS1 Magnet exchange MSC Sandrine Le Naour 31L2 Sensor Cracks SMB Richard Morton RB26 VIC waiting for approval Network cable pulling IT-CS Stephane Casenove UJ33 UD62 and UD68 activities EN-STI UD62 & UD68 DIMR completed MKI activities & Cabling EN-EL, TE-ABT UA63, UA67, RA63, RA67 Fire detection in RA67 BE-ICS RA67 VIC to be performed ODH flash in UJ14 UJ14 (ITs) LHC machine Schedule for LHC EYETS EDMS ; INDICO

15 Work authorizations (Helium spill risk) updated on 5th Jan. 2017
New: Campagne de mesure des géomètres sans ventilation dans l’arc 78 (EYETS 2016/17) under approval LHC machine Schedule for LHC EYETS EDMS ; INDICO

16 Lineal schedule Co-activity P1
LSS1L W6-7 Survey activities AFP activities W8 à ALFA shielding installation à NO co-activity W9-10 tomographies in sector 8-1 (no access)  W  AFP activities W14 à ALFA shielding installation à NO co-activity (3-4th April) LSS1R W6-7  Survey activities W  NO ACCESS FROM Wed. 15th FEB!!!  Cool down sector 12 W11 à ALFA shielding installation à Works on shift (6h-14h or 14h-22h) AFP activities à Works on shift (6h-14h or 14h-22h) W 12 à AFP activities W13  ALFA shielding installation à NO co-activity (27-28th Mars) W13-until the end of EYETS  NO ACCESS à ElQA test 12 Arc12 W  NO ACCESS  Cool down sector 12 W13-14 à NO ACCESS à ELQA test sector 12 W14-15 à NO ACCESS à Cool down sector 12 LHC machine Schedule for LHC EYETS EDMS ; INDICO

17 Personal ODH MANDATORY
LSS1L Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

18 Personal ODH MANDATORY
Point 1 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

19 Personal ODH MANDATORY
Point 18 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

20 Personal ODH MANDATORY
Arc 1.2 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

21 Personal ODH MANDATORY
LSS2L – P2 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

22 Personal ODH MANDATORY
LSS2R – Arc 2.3 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

23 Personal ODH MANDATORY
Point 3 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

24 Personal ODH MANDATORY
Arc LSS4L Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

25 Personal ODH MANDATORY
Point 4 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

26 Personal ODH MANDATORY
LSS4R – Arc 4.5 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

27 Personal ODH MANDATORY
LSS5L Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

28 Personal ODH MANDATORY
in the arc Point 5 LHC machine Schedule for LHC EYETS EDMS ; INDICO

29 Personal ODH MANDATORY
in the arc LSS5R LHC machine Schedule for LHC EYETS EDMS ; INDICO

30 Personal ODH MANDATORY
in the arc Arc 5.6 – LSS6L LHC machine Schedule for LHC EYETS EDMS ; INDICO

31 Personal ODH MANDATORY
in the arc Point 6 LHC machine Schedule for LHC EYETS EDMS ; INDICO

32 Personal ODH MANDATORY
in the arc LSS6R LHC machine Schedule for LHC EYETS EDMS ; INDICO

33 Personal ODH MANDATORY
in the arc Arc 6.7 LHC machine Schedule for LHC EYETS EDMS ; INDICO

34 Personal ODH MANDATORY
LSS7L Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

35 Personal ODH MANDATORY
Point 7 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

36 Personal ODH MANDATORY
LSS7R Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

37 Personal ODH MANDATORY
Arc 7.8 Personal ODH MANDATORY in the arc LHC machine Schedule for LHC EYETS EDMS ; INDICO

38 Personal ODH MANDATORY
in the arc LSS8L LHC machine Schedule for LHC EYETS EDMS ; INDICO

39 Personal ODH MANDATORY
in the arc Point 8 LHC machine Schedule for LHC EYETS EDMS ; INDICO

40 Personal ODH MANDATORY
in the arc LSS8R – Arc 8.1 LHC machine Schedule for LHC EYETS EDMS ; INDICO

41 Next Coordination meetings
Week 8  21st room Week 9  28th room LHC machine Schedule for LHC EYETS EDMS ; INDICO

42

43 LHC-EYETS: linear schedule Baseline
LHC machine Schedule for LHC EYETS EDMS ; INDICO

44 LHC-EYETS: Constraints
LHC machine Schedule for LHC EYETS EDMS ; INDICO


Download ppt "LHC-EYETS 2016/17 Coordination meeting #18"

Similar presentations


Ads by Google