Presentation is loading. Please wait.

Presentation is loading. Please wait.

Eastern High School Baltimore, MD

Similar presentations


Presentation on theme: "Eastern High School Baltimore, MD"— Presentation transcript:

1 Eastern High School Baltimore, MD
Patrick Dempsey Mechanical Option

2 Project Background Renovation: Historical Building
Multi-Use Owner/Tenant: Johns Hopkins Project Team General Contractor: The Whiting Turner Construction Co. Architect: Kahn & Associates MEP Consultant: Schlenger/Pitz & Associates Structural Consultant: Skarda and Associates Developer/Owner: Johns Hopkins(DOME Real Estate) Cost: $22 million MEP Cost: $6 million

3 Existing Mechanical System
Design Objectives Lack of Basic Cooling System Limit the Ductwork Reserve as much tenant space as possible Energy Recovery Off Peak Air Conditioning: Ice Storage Components 4 pipe chilled water/hot water system 3 Weil McClain 588 Boilers(Fuel Oil fired) 2 Carrier water cooled screw chillers 2 Baltimore Air Coil Cooling Towers 1 Ice Storage Tank

4 Existing Mechanical System (cont.)
3. System Characteristics Ice Storage associated with lab/off peak space use Shell perspective: limited tenant information

5 Mechanical Redesign Redesign Objectives Pre-Cooling
Re-examine the loads/modeling Lighting Loads > 2.0 W/sq.ft Equipment Loads > 4.0 W/sq.ft Remodel the space using HAP Reduced the Peak Cooling Load Focused on cooling system Reduce the First Cost & Operating Cost Size down the Equipment Smaller Chillers: (211 ton < 246 ton) Smaller Cooling Towers: (227 ton < 272 ton) Less Ductwork Down-sized AHU’s Pre-Cooling Adjusted Method of Off Peak Air Conditioning

6 First Cost Analysis Savings garnered First Cost Existing: $ 1285453
First Cost Redesign: $ Difference: $ Adjusted(Baltimore): $ Savings garnered AHU’s saved $ Diffusers/Return Registers $ Ductwork 55000 lbs < lbs $

7 Annual Cost Analysis HAP Calculations (HVAC components only)
Baltimore Gas & Electric Rates Existing Annual Cost $ per year for HVAC costs Redesign Annual Cost $ per year Differential $ per year Lifecycle Cost Duration = 15 years Nominal Interest Rate = 5% $ saved (Present Value)

8 Pre-Cooling Methodology: Dr. Braun Building Candidacy Modeling
Cool the structure during off peak hours Float the temperature Control oriented Building Candidacy Significant Structure for thermal storage: Thick Walls Utility Rate that penalizes peak usage Mechanical system comfortable with off peak air conditioning Modeling Thermostat based ideally Setpoints 68 degrees Fahrenheit(unoccupied morning cooling) 75 degrees (occupied cooling) Issues: limited setpoints, temperature profiles Not feasible EQUEST HAP

9 Pre-Cooling Continued
How to model the pre-cooling effect Utility Based: Trying to Prove Annual Cost savings Peak shifts to the morning then scales back up in the afternoon Compare to the Ice Storage Setup Load profiling HAP thermostat schedules are limited to 2 setpoints HAP loading schedules can stagger the load as a percentage on an hourly basis Simulate the peak shifts using 3 load inputs Occupancy Lighting Equipment Keep the profiles close to equal(area under the curve) Adjusted the throttling range(float)

10 Ice Storage Profile

11 Pre-Cooling Profile

12 Load Profiling Results
Annual Cost Analysis(HVAC components only) Annual Cost of Redesign(Ice Storage): $89710 Annual Cost of Pre-Cooling System: $84915 Differential: $ 4795 Primary Area of Reduction: Cooling Air Fans, Heating, Pumps, Tower Fans: neglible total diff. Lifecycle Cost Duration= 15 years Nominal Interest Rate = 5% $ saved (Present Value)

13 Mechanical Redesign Summary
Remodeled building with lowered electrical loads Resized equipment using newer model saving roughly a quarter of a million dollars in first cost and saving roughly $15000 annually. Instituted a pre-cooling controlled system taking advantage of the existing off peak air conditioning apparatus. Pre-cooling saved nearly $5000 annually. Comparison between original system and smaller pre-cooled system results in nearly $20000 in annual savings. All savings were tabulated for HVAC costs only.

14 Electrical Impact Reduced lighting loads led to drastic reductions in the Non-HVAC annual cost Existing Original System Component Costs Lighting: $ Equipment: $ Ratios are off Equipment Reduction would be justifiable but the reduction in peak load was overly generous

15 Electrical Impact Redesign
Redesign Reduced Annual Cost Original Lighting Cost: $229807 Redesign Lighting Cost: $ Differential: $170358 Distribution Roughly $ Equipment Cost 4.0 Watts/sq.ft Savings support reduced loads Existing Annual Cost: $401122 Redesign: $236032 Differential: $165090 Illusory Reduced lighting actual loading Supports the rationale for reduction

16 Schedule Impact Smaller Mechanical System = Shorter Schedule
Major Components Air Handling Units Original Schedule: 25 days New Schedule: days Ductwork Original Schedule: 194 days New Schedule: 133 days Diffusers & Return Registers Original Schedule: 114 days New Schedule: 78 days Chillers & Towers: no real savings Difference: days Conservatively: days saved.

17 Conclusions Reduced MEP First Cost by roughly 20%
Saved $15000 annually just by reducing the lighting loads to accepted levels Saved another $5000 annually through pre-cooling Supported my reduced lighting loads by examining the annual costs of the electrical equipment Achieved a massive reduction in schedule, conservatively reduced to nearly 75 days

18 Acknowledgements Thanks to:
My sponsor, Jimmy Cachola, of Schlenger/Pitz Penn State AE Faculty Especially Dr. Mumma, Dr. Srebric, Dr. Freihaut, and Prof. Ling Prof. Parfitt & Jonathan Dougherty Special thanks to my thesis advisor: Dr. Bahnfleth Fellow AE’s Jason Borowski, Katie McGimpsey, Brad Cordek, Nicole Renno Family & Friends Any that I may have left out

19 Questions?


Download ppt "Eastern High School Baltimore, MD"

Similar presentations


Ads by Google