20 Year Plan Target 300+ kV Solutions Broad Set of Futures:
Renewable Energy Penetration Load Growth Environmental Regulations Flexible to Evolve with Changing Landscape Categorized Upgrades: Reliability Upgrades Economic Upgrades Policy Upgrades
3
20 Year Plan Milestones Scope Development: 760 hours
Policy Survey: 190 hours Resource Plan: 1300 hours Siting Plan: 415 hours Benchmarking: 320 hours Constraint Assessment: 350 hours Economic Model Building: 1300 hours Economic Assessment: 489 hours Policy Assessment: 443 hours Reliability Assessment: 1030 hours
4
20 Year Plan Milestones Solution Development: 124 hours
Project Selection: 503 hours Portfolio Consolidation: 150 hours Stability Assessment: 230 hours Benefit Metrics: 2000 hours Sensitivity Analysis: 320 hours Report: 496 hours Study Management: 3000 hours TOTAL: hours
5
20 Year Plan Improvements
Scope Development: 4-5 months discussion with SPP Members Constraint Assessment: Add Generation Outlet Facilities analysis Economic Model Building: Build only 20 year model for each Future Portfolio Consolidation: Exclude this milestone and have one specific portfolio per Future
6
20 Year Plan Improvements
Stability Assessment: Wind transfer Benefit Metrics: Calculate APC only Calculate only one year B/C Solution Development: +300 kV solutions only Reliability Assessment: Exclude this milestone, focusing on economic and policy assessments