1 Case Road Sewer Joe Mouawad, P.E. October 27, 2016

2 Background An existing 12-inch sewer along G Street and Case Road within the City of Perris is operating above the District’s capacity criteria Staff proposes to install a parallel sewer along G Street and Case Road to increase capacity or an alternative longer alignment with financial participation by local developers The shorter alignment option will require trenchless construction methods to cross under the Metrolink rail line Staff will evaluate alternate alignments to avoid the Metrolink rail line crossing Case Road Proposed Sewer Metrolink

3 Project Constraints Trenchless construction method is required to install sewer across the Metrolink rail line Metrolink & Riverside County Transportation Commission (RCTC) approvals will be required District’s master license agreement with RCTC will need to be amended Alternate sewer alignments to avoid the Metrolink crossing will be evaluated during preliminary design effort Outreach to local development community needed to assess whether project partners may be available to share the cost of an alternative approach

4 Scope of Work for Engineering Consultant
Preliminary Design Report Evaluation of alternatives and outreach to local development community Assistance with obtaining approvals from Metrolink & RCTC Assistance with obtaining encroachment permit from City of Perris Survey, Geotechnical Investigation & Utility Search Final Design Contract Document Preparation Bidding Services

5 Consultant Selection Process
Issued Request for Proposals August 31, 2016 Evaluation Criteria Past Performance and qualification of the proposed team Familiarity with project and capacity to handle all aspects of the work Proposed approach, scope, manner, and thoroughness in which it is presented in the proposal Local office presence Firm’s level of effort and fee

6 Consultant Selection Summary
Firm Technical Proposal Ranking (5.0 Max) Proposal Fee (2) Final Ranking Albert A. Webb Associates (3) 4.52 $114,900 (1) 1 Krieger & Stewart Engineering Consultants 4.35 $115,600 2 Cozad and Fox, Inc. 3.24 $126,509 3 Original proposed fee was negotiated to include sufficient effort to complete services through bidding. Optional services for groundwater sampling and testing have been excluded from proposal fees. Geotechnical sub-consultant: Converse Consultants

7 Next Steps Start Final Design Nov 2016
Approvals from Metrolink & RCTC Mar 2017 or developer cost sharing agreement Complete Final Design Aug 2017 Bid Review Sep 2017 Advertise Construction Project Oct 2017 Award Construction Contract Dec 2017

8 Recommendations Execution by the General Manager, or his designee, of the District’s standard form of contract with Albert A. Webb Associates for the final design of Case Road Sewer Project in the amount of $114,900; Execution by the General Manager, or his designee, of the District’s standard form of necessary contracts and agreements including administrative award of contracts for the completion of the final design of the project; and Additional appropriation of $211,600 to fund project costs through the Bid/Award Phase.

9 Contact Information Joe Mouawad, P.E. Senior Director of Engineering (951) Ext. 4463