Presentation is loading. Please wait.

Presentation is loading. Please wait.

Kell Hall Relocation Concept Plan

Similar presentations


Presentation on theme: "Kell Hall Relocation Concept Plan"— Presentation transcript:

1 Kell Hall Relocation Concept Plan

2 Kell Hall Relocations 1 Relocate Accounting Services and Budget & Planning from Sparks 4th floor to 75 Piedmont 12th floor. – December 2016 Relocate TRIO programs from Spark 1st floor to 75 Piedmont 3rd floor – December 2016

3 Kell Hall Relocations 2 Relocate Geosciences offices from Kell 3rd floor to Sparks Hall 4th floor – June 2017

4 Kell Hall Relocations 3 Relocate CoAS Administration offices from Langdale 4th, 6th, and 7th floors to 25 Park Place 26th floor – December 2017

5 Kell Hall Relocations 4 Relocate computer classroom (4 from Sparks 1st floor) and general classroom (10? From Sparks 4th floor) to Langdale Hall 4th, 6th and 7th floors – March 2018

6 Kell Hall Relocations 5 Renovate Sparks Hall 1st floor and relocate Geoscience labs and offices from Kell Hall 3rd floor – December 2018

7 Kell Hall Relocations 6 Relocate Physics and Astronomy Teaching Labs from Kell Hall 5th floor to 1 Park Place 6th and 7th floors (?) December 2017

8 Kell Hall Relocations 7 Relocate Biology and Chemistry Labs from NSC to new Classroom South Addition Phase 2 building. – December 2017

9 Kell Hall Relocations 8 Relocate Biology, Neuro and Chemistry Teaching Labs from Kell Hall to NSC and Science Annex Addition – June 2018

10 Kell Hall Relocations 9 Relocate Psychology from Kell Hall to Urban Life 12th floor (space vacated by Criminal Justice and Social Work)- December 2017

11 Kell Hall Relocations 10 Relocate SNHP (Nursing, Nutrition, Respiratory Therapy and Physical Therapy) from Kell Hall 1st and 7th floor to Sports Arena (space vacated by Athletics as they move to Football Stadium complex) – June 2018

12 Kell Hall Relocations 11 Relocate Post Office etc. from Kell Hall 1st floor to T Deck office space – June 2017

13 Kell Hall Relocations 12 Relocate Math Assistance Complex and Computer Lab from Kell Hall 1st floor to 25 Park Place Pavilion SB level area – June 2017

14 Kell Hall Relocations 13 Research Lab Relocation 14 Other Moves