PROGRESS REPORT AS OF: END JULY 2017

Similar presentations


Presentation on theme: "PROGRESS REPORT AS OF: END JULY 2017"— Presentation transcript:

1 PROGRESS REPORT AS OF: END JULY 2017
CADANGAN TAMBAK LAUT SELUAS 66 EKAR UNTUK TUJUAN PEMBANGUNAN DI ATAS TANAH KERAJAAN KAWASAN BANDAR XL, DAERAH MELAKA TENGAH, MELAKA PHASE I – PLOT I AND E PHASE II – PLOT F, G, J, K, L PROGRESS REPORT AS OF: END JULY 2017

2 Executive Summary: Developer :- Egah Group Sdn Bhd
Main Contractor :- Gold Palm Global Bhd Contract :- Execution & Completion Of Reclamation Works, Revetment Works & All Related Works Contract Period :- 15 September 2015 to 14 July (10 months) LAND RECLAMATION WORKS PLOT PLOT AREA (m2) AREA DONE (m2) PROGRESS (%) E 96.47% F 94.15% SL1 0.00 0.0% G 50.73% I 86.79% SL2 83.59% SL3 J SL4 K L 2918 TOTAL m2 TOTAL AREA DONE m2 OVERALL RECLAMATION PROGRESS : 55.85% REVETMENT WORKS PLOT TOTAL LENGTH (m) ACTUAL DONE (m) PROGRESS (%) E 339.63 290 85.38% F - SL1 14.628 G I 81.23% SL2 20.319 100% SL3 30.676 J SL4 31.089 K TOTAL m TOTAL DONE m OVERALL REVETMENT PROGRESS : 40.13%

3 Layout of 66 Acres

4 Work Progress

5

6 Mud Clearance using Longarm excavator at Plot I on 5/7/2017

7 Mobilizing Excavator to Plot I on 8/7/2017

8 Surveying Works for Revetment Repair at Plot I on 15/7/2017

9 Revetment Repair in progress at Plot I on 17/7/2017

10 Revetment Repair in progress at Plot I on 18/7/2017

11 Revetment Repair in progress at Plot I on 19/7/2017

12 Revetment Repair in progress at Plot I on 20/7/2017

13 Revetment Repair in progress at Plot I on 21/7/2017

14 Revetment Repair in progress at Plot I on 22/7/2017

15 Surveying Works for Revetment Repair at Plot E on 26/7/2017

16 Revetment Repair in progress at Plot I on 29/7/2017

17 Revetment Repair in progress at Plot I on 30/7/2017