1 ATF cable plan N. Blaskovic N. Blaskovic FONT Meeting

2 Contents List of available cables Cable plans for:
Extraction line, local control room, C-band hut IP, S-band hut N. Blaskovic FONT Meeting

3 Extraction line  LCR LCR  C-band hut C-band hut  S-band hut S-band hut  IP checked 10 Mar 2013 checked 9 Apr 2013 checked 13 Oct 2012 RG58 Heliax 1 A2 2 B1 3 B2 4 E 5 F 6 7 8 9 10 OK 11 Not tested 12 Broken N. Blaskovic FONT Meeting

4 Upstream cable plan Extraction line K1 K2 P1(X) P2(X) P3(X) P1(Y)
RG58 Heliax Upstream cable plan Extraction line feedforward cable K1 K2 P1(X) P2(X) P3(X) P1(Y) P2(Y) P3(Y) TMD TMD Phase shifters trigger signal monitors monitors monitors trigger signal Processors FONT5 boards 357 MHz 357 MHz LCR Fan Fan Clock distribution 714 MHz LO Ctrl 357 MHz 357 MHz C-band hut S-band hut Ring clock ATF trig 714 MHz 357 MHz 357 MHz 714 MHz ATF trigger Ring clock IPK trigger N. Blaskovic FONT Meeting

5 Homodyne 1st stage electronics TMD IP
RG58 Heliax Downstream cable plan feedforward cable Ref IPA(Y) IPB(Y) IPC(Y) IPA(X) IPB(X) IPC(X) IPK Homodyne 1st stage electronics TMD IP Homodyne 2nd stage electronics signal trigger monitors monitors I Q I Q I Q I Q I Q I Q Alternative LO FONT5 boards Fan Fan IP/S-band hut 357 MHz LO 357 MHz 714 MHz ATF trigger Ring clock S-band hut IPK trigger N. Blaskovic FONT Meeting

6 (Required numbers of cables exclude spares)
Summary Current Required RG58 Heliax extraction line LCR 8 13 12 C-band hut 3 2 S-band hut 6 7 IP 4 9 (Required numbers of cables exclude spares) N. Blaskovic FONT Meeting