1 TVB TVB X 14 TRIG40 (tell40 structure) Selection board in barrack
(1MHz) L0DU TRIG40 (tell40 structure) X 14 ECAL crate (front view) Upgrade: Calo Trigger Study

2 Actual calorimeter trigger design
Backplane link 2M cable 15M cable Calorimeter detector 20 Link = 4 copper wire Serial LVDS 280Mhz Front-end boards Trigger Validation Board (TVB) Optic Mezzanine rubbon of 12 fiber 32 Link = Optic fibre 1.6 Ghz Selection Board (SB) Upgrade: Calo Trigger Study

3 Tell 40 system with 1.6 GHZ inputs
Upgrade – setup Calorimeter detector 20 Link = 4 copper wire Serial LVDS 280Mhz Front-end boards Optic Mezzanine rubbon of 12 fiber Trigger Validation Board (TVB) 32 Link = Optic fibre 1.6 Ghz Tell 40 system with 1.6 GHZ inputs Selection Board (SB) 108x32 Link = Optic fibre ~infiniband rate To Be Define 1,6Ghz or 4,8Ghz or… To farm DAQ To SuperODIN(LLT) Upgrade: Calo Trigger Study

4 Previsionnal Tell40 design (2010 study)
Upgrade: Calo Trigger Study

5 Upgrade: Calo Trigger Study

6 Upgrade: Calo Trigger Study

7 Upgrade: Calo Trigger Study

8 Upgrade: Calo Trigger Study

9 Upgrade: Calo Trigger Study

10 2 TRIG40 = full Calo trigger upgrade
7000€ 7000€ 7000€ 7000€ 5000€ Total installation cost = 8 x x 2000 = € + common ATCA Crate with SuperODIN Upgrade: Calo Trigger Study

11 devellopment schedule
ATCA Crate (15 slots) ATCA manager board: Commercial + CCPM part First final board Start of 2012 > CCPM (Marseille) CCPM debugging First board available for LAPP: End of 2012 Upgrade: Calo Trigger Study

12 First possible LAPP devellopment setup
Small ATCA Crate (2 slots) Commercial ATCA Carrier board Commercial ATCA manager board 7000€ 3500€ 3500€ 2000€ Computer With tools 4000€ First cost = = € Upgrade: Calo Trigger Study

13 « upgrade Calorimeter LHCb »:
Next meeting « upgrade Calorimeter LHCb »: 21 and 22 july 2011 Upgrade: Calo Trigger Study