1
Recommendation of Texas Test Plan Team to RMS
May 15, 2003
2
TTPT is proceeding with two Test Flights for 2003
Flight for New Market Participants testing under TX SET Version 1.5 Pre-test activities for the Flight began on April 8, 2003 Deadline to Join Flight is still May 22, 2003 First test transactions flow on July 14, 2003 Flight Scheduled to End September 5, 2003 Flight 1003 for Existing and New Market Participants testing under TX SET Version 1.6 including transaction changes from COMET Flight will begin pre-test activities on July 23, 2003 Deadline to Join Flight September 4, 2003 First transactions to flow October 13, 2003 Flight Scheduled to End December 5, 2003 MIMO changes are to be incorporated into a test flight for TX SET Version 2.0 in early 2004.
3
Approved Flight Schedules for 2003
4
Next Steps for Test Flights in 2003
The TTPT adopted and published the test scripts for use in Flight 0703 The TTPT also revised the frame schedule in the scripts to streamline and improve the testing process TTPT adopted a schedule of 3 Frames of 2 weeks each instead of the prior schedule of 6 one week frames Initiating transactions and responses will be exchanged in Frame 1 Cancels, date changes and responses will be exchanged in Frame 2 Billing and usage transactions will be exchanged in Frame 3 Script changes were adopted to enable the test transactions to more closely resemble automated production systems
5
Next Steps for Test Flights in 2003 Continued
TTPT noted the successful completion of the Version 1.5 Test Flight, the first major market test to be completed on schedule!!! RMS and TAC gave preliminary approval for 2003 Flights ERCOT and the TTPT conducted the Market Orientation Meeting for Flight 0703 on May 13, 2003 Deadline to Register for Flight 0703 is still May 22, 2003 ERCOT, the Version 1.5 Coordination Team and the TTPT will conduct the joint “Lessons Learned Workshop” on May 27, 2003 TTPT to evaluate TX SET recommended roll out schedule and will consider Flights for 2004 in June
6
Proposed Resolution for Test Flights for 2003
RMS approves the revised Market Testing timelines for Flights 0703 and Flight 1003 as adopted by the TTPT, in particular the scope of Flight 1003, which will include TX SET Version 1.6 and COMET transaction changes. RMS further directs that any material changes to these timelines or changes in scope of the test flights must be approved by RMS.
7
Flight V1.5 Report of Texas Test Plan Team to RMS
2003 Market Test Time Line as revised 5/15/03 Successful Test Flight Completion April 17 Planned production roll out for Version 1.6 and COMET transaction changes Flight V1.5 Flight 0703 testing 1.5 for New Participants Flight /8 - 9/5 G I S B Flight 10/03 7/ /5 Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec 7/11/03 Flight Kickoff 10/10/03 Flight Kickoff Proposed GISB Conversion NOW - 5/14 Flight 1003 testing 1.6 for Existing and New Participants and COMET changes Successful Version 1.5 Production Roll Out April
8
Issues for Consideration by RMS and Request for Guidance
During the Version 1.5 Market Test, one of the existing market participants almost failed to gain their certification letter. The question posed to the TTPT is what does the market do: If a new TDSP fails to successfully complete a market test? If an existing large CR fails to successfully complete a market test? If an existing small CR fails to successfully complete a market test? Does a CR loose the ability to send new transactions? Does a CR loose the ability to do business at all? Do a CR’s customers get defaulted to another REP who passed the test? If the customers are transferred, how is that accomplished? Does the market wait to convert until all have passed?
9
Report of Texas Test Plan Team to RMS
Questions ?