1 Program Shutdown Update
In Progress Review February 9, 2016 Mr. Lev B. Hind (Program Office)

2 Information briefing on Program Shutdown activities.
Purpose Agenda Information briefing on Program Shutdown activities. Management Contract Summary Hardware Disposition Status Data Disposition Status Government Facilities Summary Schedule Summary Financial Summary Security Summary Personnel Summary Remaining Tasks Issues

3 Management Lessons Learned documented and archived (2 Oct XXXX)
Program Historical Summary drafted (ECD 25 Nov XXXX) CPAR Close Out (ECD 25 Nov XXXX)

4 Contract Summary Govt Furnished Property/Facilities
Contract Principles PCO: Mr. No Hometown TCO: Ms. Ive Gachu PLCO: Mr. Count Em All Prime PCO: Mr Newto You Contract Status Stop Work (11 May XXXX) Contract Completion (30 Sep XXXX) Govt Furnished Property/Facilities GFP/RFNI Property transfers Remaining items dispositioned via PCARRS Contractor Developed HW/Data 5 Motors transferred Residual HW transfers to other organizations Fire Control: HW/SW transferred to another contract (29 Sep XX)

5 Hardware Disposition Status
Items Transferred via DD 1149 or Contract Mod Org A – 37 Misc. items – Items received Org B – 4 Widgits – Items received Org C – 5 Motors – Transfer in place Items Awaiting DD1149 signature Org 1 – Misc. HW (ECD 20 Nov) Remaining HW is in the process of being loaded into PCARRS

6 Data Disposition Status
Program Office Share Drive Unclas Data archived 3 Jul XXXX Classified Data archived 7 July XXXX Prime Contractor Data Data ordered 21 July XXXX Initial Delivery 29 July. Data archived 5 Oct XXXX Awaiting delivery of final documents (ECD mid Dec.) All data to be transferred to Electronic Management System (EMS) – ECD 31 Dec XXXX)

7 Government Facilities Summary
Test Range Exit Motors shipped from range 28 Aug XXXX Cleanroom re-installed 10 Sep XXXX Environment Close-Out Report Delivered 15 Oct XXXX

8 Schedule Summary

9 Financial Summary Govt $32.4 Prime KTR $209.9
FY XX Funding $320.6 Requirements Govt $32.4 Prime KTR $209.9 Remaining Property Disposition Bills $9.5 Funds Remaining $68.8

10 Security Summary Classified Documents Tail Sites COMSEC Equipment
All documents cleared from safes 31 Jul XXXX All electronic documents archived 22 Sep XXXX Tail Sites All Tail Sites transferred or cancelled 30 Sep XXXX COMSEC Equipment Equipment transferred from Prime has been received

11 Personnel Drawdown Plan

12 Remaining Tasks Input final CPAR
Complete processing of DD1149s to transfer GFE and Interceptor HW Receive and archive remaining data items Receive final approval of range facility Environment Assessment Finalize Historical Summary

13 Issues None at this time

14 Backup Slides Guidance Shutdown Conference Summary
Government Shutdown Activities Data Archiving Metric Personnel Summary Termination Cost Summary