1 NMMU Upgrade Integrator 3 Integrator UG 2014 Greg Saunders NMMU ICT Services

2 Introduction Approached By Adapt IT August 2012 Formal Proposal
Agreement from Key Stakeholders September 2012 Request for Strategic Funding to MANCO Aug Agreement from MANCO December 2012 Discussions with Adapt IT Re Services and Costs Formal Project Management Approach Adopted 7 Month Project Planned From Integrator 1 to Integrator 3

3 Project Timeline Kick off Meeting February 2013
Project Charter Agreed by 7 April 2013 Install 16 April 2013 Local Software conversions April to July 2013 Internal Staff and Adapt IT Staff Training of Users May 2014 Business Acceptance Testing July 2013 Go Live 9 August 2013 Final Sign off October 2013

4 Process Followed At NMMU
Formal Project Management Approach Steering Committee and Operational Committee Buy in of All users at all levels critical Broad Teams Student HR/Payroll Financial General Technical /Local Software Business Analysts from ICT – Sub Project Managers Tried to Test Business Processes as well Review by External Auditors Internal Development responsible for Local Software along with Adapt IT

5 Internally Project Managed
Project Management Issues Found Internally Project Managed Not Ideal – Project Manager had to deal with technical issues as well – not recommended Will recommend external Project Administration and Management next time, Independent of NMMU Difficult to keep track of issues and assist users at the same time Budget for Additional Costs other than NMMU and Adapt IT for Example External Audit Costs Difficult to convince non IT People regarding the reasons for upgrade at start Under estimate time to implement new features

6 Change to UTF 8 meant a lot of SQL Changes to local software
Technical Issues Change to UTF 8 meant a lot of SQL Changes to local software Changing some of local software time consuming Complexity of User Restriction changes in Finance underestimated Led to Major Speed issues with the iEnabler after go live Certain Components had to be re-written by Adapt IT R/D Team reacted quickly

7 Benefits of Integrator 3 and Beta Site
Latest Version of the software Major cost reduction Improved relationship with Adapt IT Increased knowledge for users Reduction in Local Software e.g. HR Web Appointments Receipting System NMMU ideas integrated into std system e.g. web registration and Pre-requisites

8 Lessons Learned Do not skip a major version of the software release
Keep better track of issues Budget more time for training of users Get help with configuration of system e.g. setups budget time for this especially during go live Cannot Test for all eventualities Communication important Appreciate the knowledge and experience of Colleagues Learn to have a good Laugh

9 Considerations going Forward
ADF new challenge Integrator 4 Form partnerships within the user community Retain knowledgeable staff Skills are scarce Doing more will less Process Automation Impact of Higher Education Changes HEQF Centralized Student Financial Aid CAS Final Thanks to all involved for a successful Project