Table (3.1)- the averages of the 10 models costs

Similar presentations


Presentation on theme: "Table (3.1)- the averages of the 10 models costs"— Presentation transcript:

1 Table (3.1)- the averages of the 10 models costs
% of total cost Description item 15.10 Brick work 1 15.00 R.C slabs 2 11.03 Tiles 3 9.53 R.C foundation 4 9.50 Sanitary work 5 9.14 Carpentry &joinery 6 8.10 electricity 7 6.60 Plaster work 8 4.47 Painting work 9 3.50 Excavation & B.F 10 2.30 Plain concrete 11 Roof treatment 12 1.98 RC column 13 1.45 RC staircase 14

2 Cost model Project name: Merowi Dam project .
Type of building: housing type (A) No. of stories: 2 Total built area: 410 m2 . Total building cost: 40,723,508 .

3 Table (3.2)- Typical cost model
% of total cost Cost in S.D Description item 11.05 Brick work 1 17.42 R.C slabs 2 13.25 Tiles 3 9.91 R.C foundation 4 5.16 Sanitary work 5 11.72 Carpentry &joinery 6 8.40 electricity 7 6.18 Plaster work 8 5.23 Painting work 9 4.86 Excavation & B.F 10 1.77 722808 Plain concrete 11 2.20 899500 Roof treatment 12 1.78 723250 RC column 13 1.O3 420000 RC staircase 14 40,723,508 TOTAL COST

4 Table (4.1)- Elements and their costs percentages
% of total cost Cost in S.D Description item 11.05 Brick work 1 17.42 R.C slabs 2 13.25 Tiles 3 9.91 R.C foundation 4 5.16 Sanitary work 5 11.72 Carpentry &joinery 6 8.40 electricity 7 6.18 Plaster work 8 5.23 Painting work 9 4.86 Excavation & B.F 10 1.77 722808 Plain concrete 11 2.20 899500 Roof treatment 12 1.78 723250 RC column 13 1.O3 420000 RC staircase 14 40,723,508 TOTAL COST

5 Table (4.3)- Pareto Analysis Results
% of total cost Class total cost Class Element Class 63,36 25,803,700 Brick work R.C slabs Tiles R.C foundation Carpentry &joinery A 29.85 12,154,250 Sanitary work electricity Plaster work Painting work Excavation & B.F B 6.79 2,765,558 Plain concrete Roof treatment RC column RC staircase C

6 Table (4.4)- Function Analysis
Class Function Element Item noun verb Basic load Carry /distribute RC footing 1 Basic secondary Load people Carry protect RC flat slab 2 Secondary secondary Partitions Privacy interiors Construct facilitate improve Brick work 3 Circulation Security privacy Facilitate Enhance Doors 4 Air light Refresh provide Windows 5 Appearance Cleaning walls Give protect Ceramic tiles 6

7 Table (4.5)- Proposed Alternatives
Element item 2 1 Hollow block slab Slab with beams RC flat slab TRI-DI panels walls Cement hollow blocks Brick work Steel doors& windows TIMBER DOORS& WINDOWS Alumni. Doors& windows 3 Cast insitu Terrazzo Terrazzo tiles Ceramic tiles 4

8 Table (4.6)- Actual Design Costs
Cost in S.D Element Item 7,095,000 R.C Flat slab 1 3,827,200 Brick work 2 4,775,750 Alumni. Door & windows 3 5,395,00 Ceramic tiles 4

9 Table (4.7)- Proposed Ideas Costs
Cost in S.D Element Item 4,370,000 RC slab with beams, using high tensile steel 1 3,093,000 Cement hollow block walls 2 5,291,000 Tri-Di panel finished walls 3 3,029,000 Timber doors & windows 4 Steel doors & windows 5 3,960,000 30×30 cm terrazzo tiles 6 4,322,500 Cast insitu terrazzo tiles 7

10 Table (4.8)- Presentation of savings
item Actual Design Proposals Savings S.D 1 R. concrete flat slab R. con. With beams (using high tensile steel) 2,725,000 2 Ordinary brick work A- cement hollow block B- using tri-di panel (eliminating plaster cost) 734,000 582,200 3 Alum. Doors &windows A- timber d & w B- steel d & w 1,746,750 2,445,450 4 Ceramic tiles A- terrazzo tiles B- cast in situ terrazzo 1,430,000 1,072,500