EC Activities Status for LIU September 2017

Similar presentations


Presentation on theme: "EC Activities Status for LIU September 2017"— Presentation transcript:

1 EC Activities Status for LIU September 2017
Roger Barlow, Etienne Carlier, Gregor Gräwer, Christophe Lolliot, Steven Pavis, Marco Pimentel, Pieter Van Trappen LIU and TE/ABT activities

2 PSB – BI.BSW All hardware @ CERN (including spare)
Christophe Lolliot All CERN (including spare) Ready for installation Integration with WIC defined DIC issued DEC for BI.SMH to be generated

3 PSB – BI.DIS All hardware @ CERN (including spare)
Roger Barlow All CERN (including spare) Ready for installation Test of individual electronics & controls sub-systems completed Migration from FID to FIDS ongoing (Q4-2017) 867 test bench “carbon copy” of operational installation Integration in control infrastructure ongoing (FESA) Coordination of installation activities in BCER to further progress (internal and external)

4 PSB – BI.KSW All hardware @ CERN (Including spare)
Gregor Grawer All CERN (Including spare) Installation of full system (electronics & controls, pulse generators & magnets) in 865 for validation of one complete system Required performance reached (400A +15% for high current & 40A +15% for low current) Reliability test ongoing Definition of API for integration in control infrastructure ongoing Dynamic waveform control under implementation Migration of low-level control from LabVIEW to Linux/FESA under study

5 PSB – BI.TKSTR All hardware @ CERN Ready for installation
Pieter Van Trappen All CERN Ready for installation

6 PS – PI.KFA45 Re-engineering completed
Steven Pavis Re-engineering completed Electronics and Controls architecture defined (including 5th generator system in 867) Work on functional specification ongoing Operational requirements under study Specification infrastructure started preDIC issued DIC/DEC in preparation CONS of key sub-components ongoing Power supplies, capacitor bank, fast interlocking… WU updated (to be uploaded)

7 PS – PI.SMH42 & PI.BSW42 Strategy defined
Marco Pimentel Strategy defined Added to ongoing PS-Complex Septa Electronics and Controls consolidation Functional specification available Production in progress WU updated (to be uploaded) DIC in preparation

8 SPS - SBDS Electronics & controls architecture defined
Pieter Van Trappen Electronics & controls architecture defined 75% of hardware reused from existing system Prototype of new hardware under test in 865 & 867 Power Trigger Module TSU with locking on SPS Frev (will be tested on SBDS1 during run) Series production scheduled for beginning (TSU, FIDS, PTM) Purchasing process started for key components Infrastructure work starting during YEST Kicker platform in ECA5 WU created (to be uploaded)

9 SPS – ZS Ion traps Design of new ZS ion traps completed
Roger Barlow Design of new ZS ion traps completed Prototype validated with beam in ZSTF Test on one LSS2 ZS during 2018 SPS run under consideration Industrialisation process for external production ongoing. Pre-series expected in Q Production planned for 2018. WU created (to be uploaded) BC shared with SE section

10 SPS – TPSC4 Functional specification available
Steven Pavis Functional specification available Reuse of same solution as for TPS15 validated Production in preparation DIC in preparation No integration issue WU created (to be uploaded) BC missing


Download ppt "EC Activities Status for LIU September 2017"