Download presentation
Presentation is loading. Please wait.
Published byDennis Wilcox Modified over 6 years ago
1
AMERICAN LINEAR COLIDER PHYSICS GROUP Impressions of the Dubna Site
Update on (ILC) CFS and Impressions of the Dubna Site V. Kuchler
2
Overview Brief Summary of Work Through the Reference Design Report (RDR) Description of RDR Sample Sites Other Sites Considered Prior to/During the RDR Process Dubna Site, DESY Site and Alternative Design Configuration Post RDR Plan Efforts Toward a “Uniform Design Solution”
3
How Did We Get to the RDR w/Respect to CFS
Global Design Effort Established at Snowmass, August, 2005 Conventional Facilities and Siting Group Established Site Criteria Matrix was Developed and Sample Sites were Identified in Each of Three Regions Baseline Configuration Document was Generated and Completed in December, 2005 Preliminary CFS Value Engineering Review was Completed at CALTECH in October, 2006 Reference Design Report Based on Three Sample Sites with Cost Estimate was Completed in February, 2007
4
What Does the RDR Represent
The RDR Design Represents a “Consensus Design” Based on Criteria Taken at Face Value from Most/All Technical Systems It is the Result of Minimal Value Engineering or Criteria Optimization All Sample Sites are Based on a Deep Twin Tunnel Configuration The RDR Design (and Cost Estimate) will Naturally Benefit from a More Comprehensive Value Engineering Process and Optimization of Technical Criteria
5
Asian Region Sample Site
Firm and uniform geology. Large enough area spanning over 50 km. Absence of active dislocations, wide faults in the neighborhood. Absence of epicenters of earthquakes exceeding M6 within 50 km from anywhere in the site since AD1500. Terrain uniformity to maintain the ILC Tunnel depths less than 600 m anywhere. Granite (compressive strength ~100 MPA) Excavation : TBM (~ 300 m/month) Finish : shotcrete (partially reinforced with rock-bolts) Access by sloped tunnel instead of vertical shafts
6
European Region Sample Site
Location : Proximity of CERN existing site with its 400 kV grid connection. Close to the city of Geneva with its international airport, railway and highway network connections. Geology : Solid and stable bedrock called “molasse” (sandstone), which stretches between the Jura mountains and the Lake of Geneva. A layer of moraines ranges from 0 to 50 m on top of the sandstone. Low seismic activity and no active faults. Depth of main tunnels : average ~ 100 m
7
Americas Region Sample Site
Loation : in solid rock, close to existing institute, close to the city of Chicago and international airport, close to railway and highway networks. Geology : Glacially derived deposits overlaying Bedrock. The concerned rock layers are from top to bottom the Silurian dolomite, Maquoketa dolomitic shale, and the Galena-Platteville dolomites. Depth of main tunnels : Average ~ 135 m
8
Other Sites Considered
Near Surface Solution Near FNAL Near Surface and Deep Tunnel Solutions in California as Part of the NLC Effort A Potential Site at the Hanford Laboratory in Washington State was Identified A Twin Tunnel Solution was Investigated at DESY Based on the RDR Criteria A Twin Tunnel Solution was Investigated at Dubna Based on the RDR Criteria
10
What We Were Supposed to/Are Going to Do
Begin with Existing RDR Design “Big Budget Bang” in December, 2007 Complete CFS Value Engineering, Revised Design Solution and Develop New Cost Estimate Identify CFS Cost Drivers and Resume Targeted Value Engineering and Alternative Design Options Develop Schedule Through Start of Construction and Bid to Host Documentation Initiate CFS Collaboration Efforts with CILC and XFEL Complete (EDR) Engineering Design Report in Late 2010 and Proceed to Start of Construction in 2012 Provide Input into the Technical Design Phase I (2010) & Phase II (2012) with Revised Criteria, Design Solutions and Cost Estimate
11
From B. Barish Dubna Talk (GDE Direction)
Program of ‘Value Engineering’, whereby an attempt is made to assure the highest value by delivering all required functions at the lowest overall cost. The TD Phase CFS activities are therefore focused on this activity and are broadly subdivided into three stages: a preparatory stage, during which the design criteria used to develop the Reference Design are revisited and analyzed; a Value Engineering review stage, where the functional requirements are compared one at a time with their respective cost and a small set of prospective improvements are proposed; an evaluation and design update stage during which the design is improved through adoption and analysis of the suggestions. Based on expected CFS engineering resources for the TD Phase, stages (1) and (2) above are expected to last about two and a half years.
12
CFS Goals for the Dubna Workshop
Examine CFS RDR Requirements Develop Models for Alternate Tunnel Configurations and Siting Conditions (Shallow Sites and Single Tunnel Solutions) Examine CFS Support Systems, Identify Cost Drivers and Continue Value Engineering for Cost Reduction Opportunities Evaluate Possible Alternative Machine Layouts Which May Lead to Cost Reduction Discuss Siting Strategies Toward a “Uniform Site Solution”
13
Current Status The RDR Identified One Sample Site from Each of the Three GDE “Regions” Each Sample Site was a Deep Twin Tunnel Configuration The JINR/Dubna Site is a “Near Surface” Single Tunnel Configuration The DESY/TESLA Site can Also be Considered a “Near Surface” Single Tunnel Configuration The CLIC Collaboration with a Single Deep Tunnel Design will Also Provide Useful Input to the ILC Tunnel Configuration Value Engineering Effort The Dubna Site Solution the DESY Site Work and XFEL Design Construction will Provide Valuable Information for Alternatives to the Deep Twin Tunnel RDR Design
14
Alternative Tunnel Strategies
JINR Efforts at Dubna Looking at an Alternative to RDR Design Working with Russian State Project Institute (GSPI, Moscow) Near Surface Bored Tunnel with Surface Level Support Gallery Surface Buildings Spaced for Cryo Support Experience from the XFEL Project at DESY Renewed Efforts for Alternate Design at DESY Near Surface Bored Tunnel Taken from Original TESLA Profile Updated to ILC Criteria Collaboration with the CLIC Project Independent Tunnel Alternatives will Also be Reviewed as Part of the Generation of a “Uniform Design Solution”
15
Location Map of Dubna Site
16
The ILC linear accelerator is proposed to be placed in the drift clay at the depth of 20 m (at the mark of m) with the idea that below the tunnel there should be impermeable soil preventing from the underlying groundwater inrush. It is possible to construct tunnels of the accelerating complex using tunnel shields with a simultaneous wall timbering by tubing or falsework concreting. Standard tunnel shields in the drift clay provide for daily speed of the drilling progress specified by the Project of the accelerator (it is needed approximately 2.5 years for the 50 km tunnel). Dubna Profile
17
Tunnel Cross-Section Option 1
18
Tunnel Cross-Section Option 2
19
Tunnel Cross-Section Option 3
20
Location Map at DESY Site
21
DESY Site Detail and Profile
22
Full DESY Site Profile
23
RDR Design Solution Stability/Vibration + Egress +
Proximity of Equipment + Maintenance and Reliability + Installation + Cabling + Water Inflow + Wave Guide – Cost – Enclosure Access –
24
1 Tunnel Solution A Stability/Vibration ? Egress +
Proximity of Equipment - Maintenance and Reliability - Installation + Cabling - Water Inflow ? Wave Guide + Cost ? Enclosure Access –
25
1 Tunnel Solution B Stability/Vibration ? Egress -
Proximity of Equipment - Maintenance and Reliability - Installation - Cabling - Water Inflow ? Wave Guide + Cost + Enclosure Access –
26
Cut/Cover Solution Stability/Vibration - Egress +
Proximity of Equipment + Maintenance and Reliability + Installation + Cabling + Water Inflow - Wave Guide – Cost ? Enclosure Access +
27
The Post RDR Plan for CFS
Three Aspects Form the CFS Equation Amount of Work to be Completed Time Constraints and/or Guidance Resources Available Evaluate the Current and Near-Term Resource Profile at FNAL, SLAC, KEK, CERN and JINR Develop Firm Collaborations with XFEL and CLIC Design Efforts Develop a Prioritized Value Engineering Plan Develop Viable Alternate Design Configurations and Adjusted Technical Design Criteria for Review and Approval Generate a Revised Uniform Design Solution Take Full Advantage of the Opportunities Provided by the Collaboration with the CLIC Project and the Experience Gained in the Construction of the XFEL Agree on a Timeframe that Allows for the Completion of a Comprehensive Alternative Design Solution and an Effective ILC Siting Strategy
28
Schematic Path to a “Uniform Design” Solution
Value Engineering and Technical Criteria Review Alternate Configurations Identified Alternatives Ranked by Parameters (Cost) Qualifications and/or Required Criteria Adjustments for Optimum Alternatives Reviewed Optimized non-Site Specific Alternatives Combined into the “Uniform Design” Solution
29
So What is an “Optimized Design Solution”
Solution will not be Necessarily Site Specific It will Involve a Review of Existing Criteria and the Development of Alternative Configurations with Criteria Adjusted to Provide a More Straightforward and Cost Effective Tunnel Configuration, Mechanical Support System, Electrical Distribution, etc. The Combination of Individual Value Engineered Design Components will Provide a New Design Solution Optimized to the Parameter(s) Selected For the CFS Group Specific Priorities have been Identified: Tunnel Configuration Underground Space Process Cooling Water Systems Electrical Distribution
30
Near-Term Specifics Continue Value Engineering Effort Initiated in FY 08 as Resources Permit Initial Efforts will Focus on the Highest Level CFS Cost Drivers Tunnel Configuration Deep Twin Tunnel Deep Single Tunnel Near Surface Single Tunnel Near Surface w/ Utility Enclosure Cut and Cover Process Cooling Systems RDR Design All Chilled Water w/ LCW Skid All Process Water w/ LCW Skid and Process Water Fan Coil Units all Process Water w/ LCW Skids and Compressorized Fan Coil Units All Process Water for Klystrons Only Determine Specific Impacts on Technical System Criteria Generated by Alternative Design Solutions Together with Technical Groups and Project Managers, Review Impacts and Establish Preferred Optimized Alternatives Generate the “Uniform Design” Solution from Optimized Alternatives
31
Proposed CFS Plan for FY 09
Continued General Coordination of Global CFS Efforts Completion of the Process Cooling Value Engineering Efforts\ (Milestone for November GDE Meeting) Continuation of the Alternative Tunnel Review for the Main Linac (Milestone for Spring GDE/AAP Review Meeting) CFS Value Engineering Process (Initial Review) Underground Space Utilization Electrical System Design Review Development of Functional Requirements (TDP-1)
32
Summary We are Trying to Cope with Uncertain Funding Levels and Reconcile the Effort with GDE and Local Direction Value Engineering and Overall Criteria Review are a Natural Part of the Preliminary Design Process We will Leverage Other Projects Efforts from the CFS Perspective Progress will Continue, but at a Slower Pace than Originally Planned There are Several Chickens and Many Eggs
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.