Download presentation
Presentation is loading. Please wait.
Published byBarnaby Cooper Modified over 6 years ago
1
Status of straw production straw module assembling
and straw module assembling in Dubna Dubna straws: - manufactured - stored Assembly site: - Module #3 (Ch2(u,v)) status - wiring procedure Conclusion S.Movchan, Yu.Potrebenikov
2
Straw production status (08 April 2013)
Last serial straw # Stored at Dubna straws Necessary to produce - ~2700 straws Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
3
Module-3 assembly time line:
Dubna assembly site Module-3 assembly time line: Delivery to Dubna – September 2012 frame vacuum test – from 13/09/ weeks straw assembly (from 08/10/2012): gluing – finished at 07/02/ weeks bush cutting – finished at 20/02/ weeks module leak test – finished at 04/03/ weeks wiring: straw cleaning from dust – finished at 15/03/2013 wiring of 450 straws – finished at 03/04/ weeks (a half of the module) Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
4
Wiring preparation procedures Wiring procedure - vertical option
crimper certification straw cleaning end-plug sizing wire re-spooling Wiring procedure - vertical option the same wire tension (no friction) no scratches on straw cathode due to wire insertion Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
5
Crimpers and tested samples
2 pneumatic and 5 hand crimpers micrometer calibration Tested samples: Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
6
Crimper certification results
Crimped pin thickness Status Hand crimpers: Crimper # mm OK Crimper # mm BAD Crimper # mm OK Crimper # mm OK Crimper # mm OK Pneumatic crimpers: Crimper # mm OK Crimper NO# mm OK (working pressure dP=6 Bar) Reference doc: ALT-IT-QP-0052 (H.Danielsson) nominal crimped pin thickness h=( /-0.00) mm Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
7
Straw cleaning before wiring
Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
8
End-plug sizing WEB’s sides Opposite sides D=9.63 mm and 9.66 mm
Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
9
(to prevent wire sticking)
Wire re-spooling (to prevent wire sticking) Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
10
Wiring procedure Apr-8-13
S.Movchan, Yu.Potrebenikov Status of work in Dubna
11
WEB installation Apr-8-13
S.Movchan, Yu.Potrebenikov Status of work in Dubna
12
Tooling for unwind wire
(top of the module) Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
13
Insertion wire to a Teflon plug
Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
14
Fixation of a needle to the wire
(by cambric) Needle weight is about 0.7 gram Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
15
Insertion the needle into the straw
Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
16
Teflon plug fixation Apr-8-13
S.Movchan, Yu.Potrebenikov Status of work in Dubna
17
Move the wire inside the straw by the motor
Bottom part of the module No needle rotation and oscillation Across the straw axis Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
18
before removing the scotch
Pin insertion (top of the module) fix the wire by a scotch put on a pin on the wire Fix the wire before removing the scotch Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
19
Pin compressing & crimping, wire cutting
Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
20
A clip hanging before needle cutting
The needle cutting (bottom) A clip hanging before needle cutting Wire cutting Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
21
Pin insertion & wire tension with F=90 g
(bottom) Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
22
Pin crimping & wire cutting
Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
23
1 view - 450 straws – fully assembled
Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
24
Total: (9-14) min/wire => 10 min/wire
Wiring & crimping 2 technicians 48 wires per day (10 min/wire=6 wires/h=48 wires/shift) time scale check: - wire insertion – (5-8) min - crimping – (4-6) min Total: (9-14) min/wire => 10 min/wire straw by straw (baseline option) Rate - 3 cells per day (3 cells x 16 wires) Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
25
Conclusion Straw manufacture – ok!
1321 straws stored and ready for use Module #3 assembly: straw gluing – done straw cutting – done straw preliminary cleaning – done module overpressure test – done straw final cleaning – done ½ module wiring - done Next: wiring – in progress HV test - in preparation Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
26
Thank you! Apr-8-13 S.Movchan, Yu.Potrebenikov Status of work in Dubna
Similar presentations