Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project Cost Management

Similar presentations


Presentation on theme: "Project Cost Management"— Presentation transcript:

1 Project Cost Management

2 The Importance of Project Cost Management
IT projects have a poor track record for meeting cost goals Average cost overrun from 1995 CHAOS study was 189% of the original estimates; improved to 45% in the 2001 study In 1995, cancelled IT projects cost the U.S. over $81 billion

3 What is Project Cost Management?
Cost is a resource sacrificed or fore-gone to achieve a specific objective or something given up in exchange Costs are usually measured in monetary units like dollars Project cost management includes the processes required to ensure that the project is completed within an approved budget

4 Project Cost Management Processes
Cost estimating: developing an approximation of the costs of the resources needed to complete project activities Cost budgeting: aggregating the estimated costs of individual activities or work packages to establish a cost baseline Cost control: influencing the factors that create cost variances and controlling changes to the project budget

5 Cost Estimating Costs are estimated for all resources that are applied to the activity cost estimate, includes labor, materials, equipment, services, facilities, information technology, inflation allowance, cost contingency reserve It is also important to develop a cost management plan that describes how cost variances will be managed on the project

6 Cost Estimation Tools and Techniques
3 basic tools and techniques for cost estimates: analogous or top-down: use the actual cost of a previous, similar project as the basis for the new estimate or vendor bid analysis bottom-up: estimate individual work items at the lowest level of detail and sum them to get a total estimate parametric: use statistical relationship between historical data and other variable (cost rates, lines of code, etc) to calculate a cost estimate

7 Cost Budgeting Cost budget involves allocating the project cost estimate to individual work items and providing a cost baseline The cost baseline is a time-phased budget that is used as a basis against which to measure, monitor, and control overall cost performance on the project

8 Cost Control Project cost control is a process to determine the cause of a variance, the magnitude of the variance, and to decide if the variance requires corrective action Earned value management is an important tool for cost control

9 Earned Value Management (EVM)
EVM is a project performance measurement technique that integrates scope, time, and cost data Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals You must enter actual information periodically to use EVM. You must enter status date information

10 Earned Value Management Terms
The planned value (PV), formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is the percentage of work actually completed multiplied by the planned value Estimate to Completion (ETC), formerly called forecasting of the remaining budget of the project completion Estimate at Completion (EAC), formerly called projected total final budget of the project completion

11 Earned Value Formulas

12 Earned Value Calculations for One Activity After Week One
BCWP PV * % Complete BCWS ACWP BCWP - ACWP BCWP - BCWS BCWP/ACWP BCWP/BCWS

13 Rules of Thumb for EVA Numbers
Negative numbers for cost and schedule variance indicate problems in those areas. The project is costing more than planned or taking longer than planned CPI and SPI less than 100% indicate problems

14 Earned Value Chart example

15 Project Cost Management Processes

16


Download ppt "Project Cost Management"

Similar presentations


Ads by Google