LSST Commissioning Kevin Reil LSST Commissioning Camera Rep
LSST Commissioning Kevin Reil LSST Commissioning Camera Rep. August 15, 2016
2
LSST Commissioning: Camera
Commissioning Planning Time Frame Camera Team Input Initial Plans Logistics Discussion
3
LSST Commissioning: Camera Time Frame
4
Commissioning Planning Time Frame: Camera
Camera commissioning scope estimate - non-MIE (2*) Camera shipping plan (1) Camera on summit re-verification plan (2) Camera summit facility build-out plan (2) Detail tests with ComCam for Early System AI&T (same 2) Detail Science Camera tests for Full System AI&T (3) Non-MIE Camera supplied hardware design, costing and BOEs (10 in parallel with above) This is list from Chuck with number of weeks allotted to get it done in parenthesis
5
Commissioning Planning Time Frame: Camera
Camera commissioning scope estimate - non-MIE (2*) Camera shipping plan (1) Camera on summit re-verification plan (2) Camera summit facility build-out plan (2) Detail tests with ComCam for Early System AI&T (same 2) Detail Science Camera tests for Full System AI&T (3) Non-MIE Camera supplied hardware design, costing and BOEs (10 in parallel with above) Bold is fairly well covered in I&T scope (but full team feedback needed) Regular is maybe covered at some level by I&T and SE Faint is covered no where in MIE as far as I can tell.
6
LSST Commissioning: Camera Team
7
3.01 3.02 3.08 LSST Camera 3.06.05 Utility Trunk
Corner Raft Tower Science Raft Tower 3.03 Sensors 3.01 3.02 3.08 Aux Electronics Cryostat L3 Lens Assembly Camera Body Filters (6) I show this quickly to remind people we are a big team and I need input from everyone. (I’ve started collecting info but have a lot more to do). Filter Exchange System Shutter DAQ L1-L2 Lens Assembly Camera Control System
8
I&T -> Commissioning
I&T planning summarized: LCA-40 Integration and Test Plan LCA-283 Camera Verification Test Plan LCA Survey and Alignment Plan Documentation eTraveler summaries, NCRs, as built docs, etc Characteristics Data Delivered with the Camera Information delivered to Data Management Iterated several times and under change control, LSE-130 Details of vendor test data will be added as they are determined Includes: As-built position information from I&T FEA distortion models Sensor and optics characteristics (from test plans) Filter and lens vendor test results Optical model as-built inputs/updates to support integrated observatory modeling Shutter motion profiles and shadowing model as a function of position measurements Thermal model to interpolate temperature measurements Configuration
9
Summary of inputs from camera team
Camera Management Need to clearly understand colors of money ($$$) and properly manage boundaries. Create BOEs and resource loaded schedule. Camera Systems Engineering While camera fully verified at camera preship review questions will (almost certainly) come up during commissioning What role is needed from camera SE during commissioning? eTraveler transfer of knowledge? NCR handling? Sensors/Science RAFTs Transfer of fixtures from BNL to LSST? Transfer/maintenance of knowledge? On sky sensor data/performance evaluation. Handling colors of money is very important to get right.
10
Summary of inputs from camera team
Corner RAFT* Like SR only digital access at commissioning Wavefront data and guide data! Optics All the filters will be fully characterized by the vendor by direct measurements on the actual optics across the entire aperture. r-filter, at least, also well tested at SLAC. Float indicates all filters tested at SLAC but possible summit work needed (CCOB thin beam at summit is currently planned) Optics handling expertise at LLNL needs transfer to camera I&T and commissioning (not just a piece of paper with procedure) L3 integrated at delivery L1/L2 assembly (likely) reintegrated and aligned in Chile
11
Summary of inputs from camera team
Shutter Well tested at I&T prior to delivery Shutter swaps at summit during commissioning? On sky performance input/feedback First shutter refurbish as part of commissioning? Filter exchange* Autochanger swaps at summit during commissioning? On sky/telescope input/feedback First autochanger refurbish as part of commissioning? Cryostat/refrigeration* Pathfinders during ComCam Commissioning systems (2) at summit
12
Summary of inputs from camera team
CCS Pathfinders Need CCS prior to ComCam More than any subsystem (I think) CCS will be asked to add many things not in their original list of requirements. Significant manpower needs during commissioning. Calibration telescope ? DAQ Need DAQ prior to ComCam Calibration telescope? Network issues/boundaries (summit, summit to base, etc)
13
Summary of verbal inputs from camera team
I&T I&T ends with camera ready to ship I&T has scope ( ) to design, build or design/build shipping container for camera But not all the other things that need to ship. Nominal plan has been to reuse the L1/L2 shipping container from Optics/Ball Aerospace and ship rest of camera as one piece Filters back in their shipping containers Commissioning must cover shipping costs All of camera I&T goes to Chile Fixtures and a-frame crane for clean room in I&T budget Alumalift, RAFT level test stands, computers Everything else? (tools, clean room gear, etc) are not.
14
LSST Commissioning: Camera Time FrameS
15
Time Frames: Camera Perspective
Pathfinders for CCS and DAQ ~2018 ComCam era Early 2019, merge T&S/Cam hardware Mid 2019 to early 2020 – On telescope Refrigeration pathfinders Camera Ready at SLAC Feb. 14, 2020 Camera on summit (camera maintenance area) Spring/Summer 2020 Camera on telescope! Fall/Winter 2020 (Dates approx. from gantt charts) What did I miss? These are mine based on my vision (with a lot of discussion with others)
16
Time Frames: Camera Perspective
Pathfinders for CCS and DAQ Needed before ComCam arrives Discussion Note to discuss more
17
Time Frames: Camera Perspective
ComCam era Add missing scope in LSE-199 Or at least clarification of scope and responsibilities @SLAC I&T SLAC Union of I&T scope and T&S SLAC Unified SLAC Shipping On Summit Testing on floor before going on telescope In mass simulator on telescope Parallel refrigeration pathfinder in mass simulator What did I miss?
18
Time Frames: Camera Perspective
Camera Ready at SLAC Camera I&T done Pre-ship/Acceptance review ( ) Camera into/next to shipping container ( ) Camera project (DOE MIE) done! Ship camera Ship fixtures Ship test stands, tools, etc Transfer verification data, procedures, etc “Commissioning activities involving the Camera begins with shipping from SLAC to Chile and re-verification on the Cerro Pachon summit. Re-verification activities of the Camera will be lead (led) by DOE personnel, but coordinated through the Commissioning team and plan. These activities are currently scheduled to start February 14, 2020 with a Camera Pre-Ship Acceptance review at SLAC.” What did I miss?
19
LSST Commissioning: Logistics and Existing Plans
20
9 3? Logistics of shipping I&T fixtures prior to camera indicates that some fixtures arrive with camera thus requiring time to install fixture before reassembling camera.
21
Receiving the Camera from SLAC
Camera Shroud installed as protection for auto changer L1-L2 removed These slides from Joint Technical Meeting: Santa Cruz Thanks: Travis Lange
22
Telescope 3rd Floor Camera Staging and Test Area White Room Clean Room
Utility Area Walkway Mirror Coating Facility
23
Equipment Flow Diagram—Receiving the Camera
“Camera I&T needs to be repeatable at summit” requirement has required real work already.
24
Receiving the Camera and Prepping for Install
Raft Integration Camera Integration Stand BOT Camera Staging and Test Area Clean Room (class 10,000) White Room (class 100,000)
25
Time Frames: Camera Perspective
Camera on summit (camera staging/test area) Camera on camera integration stand (install that first) Is nominal shipping plan of L1/L2 + rest of camera the right plan? Re-align L1/L2 assembly with camera CCOB thin beam tests Refrigeration at Camera Maintenance area How much throughput testing? Under CCS control here Camera in front end assembly Move to OCS control Pump down/cool down Flat field, darks, etc What did I miss?
26
Camera Staging and Test Area
Camera Integration Stand
27
Receive Camera from SLAC on Saddle Stand
Camera Saddle Stand
28
Move Camera Into White Room
29
Camera in White Room (Rotated 180°)
Camera in Saddle Stand L1-L2 Support Stand
30
Bring L1-L2 Container into White Room
L1-L2 Shipping Container L1-L2 Support Stand
31
Prep L1-L2 L1-L2 Shipping Container L1-L2 on Support Stand
32
Remove L1-L2 Shipping Container
33
Integrate L1-L2 and Shroud to Camera
34
Move Camera into Staging Area
35
Prep Camera for Move to Integration Stand
36
Camera Testing & Alignment
Utilities Needed: Camera Power 380V, 3 phase 44A Integration Stand Power 230V, 3 phase 30A Refrigeration DAQ Fibers Glycol Nitrogen gas Compressed dry air
37
Prep Hexapod/Rotator Assembly
Camera Support Assembly Stand Camera Support Assembly
38
Integrate Camera on Hexapod/Rotator Assembly
Complete Camera Support Assembly ready for integration on telescope
39
CAD Image of Facility The CAD model of Camera Equipment in the Camera Maintenance Facility is a WIP Camera Saddle Stand Camera Integration Stand
40
See JTM talk by Travis Lange
More plans in place See JTM talk by Travis Lange Cryostat level work on summit support RAFT replacement, for example
41
Time Frames: Camera Perspective
Camera on telescope! Full verification of all systems Mini surveys Data flowing What did I miss?
42
Camera: Conclusions
43
Camera Commissioning: Conclusions
I have no conclusions, we are just getting started We need your help! Let’s talk!