Els de Wolf 20 February 2012, Catania
WPF/L Els de Wolf 20 February 2012, Catania
2
PPMs The Pre-Production Models are deliverables of KM3NeT-PP
PPM of the optical module PPM of the calibration system PPM of the readout/DAQ system PPM of a ‘small scale’ detection unit Final deliverable: description of the Production Models
3
PPM-objectives Questions to be answered with these PPMs:
Can we deploy? Can we calibrate? Can we measure signals? Can we get the signals to shore? Can we measure muon signals? What do we learn for the PM? December 2010: Report delivered to EC describing the PPM models (KM3NeT_FL_REP_PPM_description)
4
PPM 20 storeys, 6m bars, for DU distance of 180m
2 storeys with ‘active’ DOMs To be deployed and connected at….?
5
Components
6
Adjusted PPM test programme for in-situ validation of technology
PPM-PMTunit: ‘mini-DOM’ in ANTARES Singles rate and coincidence measurements with 3” PMTs PPM-DOM: ‘full’ DOM in ANTARES Long term benchmark of the optical module Test of KM3NeT readout electronics DU deployment tests in Toulon area (5 storeys) Test of the design and integration of the detection unit (DU) Test of deployment method PPM-DU-Mechanics: deployment tests in Toulon area (20 storeys) Test of full unfurling and stability of tower PPM-DU-Backbone: Deployment of mechanical DU in Pylos area (20 storeys) Test of reliability of backbone handling and DOM penetrators PPM-Operation Deployment and connection of ‘mini-tower’ at Capo Passero Test of KM3NeT fibre optics and data transmission Test of detector operation Using the facilities and services of the ANTARES, Capo Passero, Pylos sites i.e. An operational telescope, cables to shore, shore stations, RoVs, deployment vessels, calibration devices time
7
PPM-PMTunit: ‘mini-DOM’ in ANTARES
Objective: Measurement of singles rates and coincidences with 3” PMTs Delivery of info for simulation software and PMT specs for tendering Implementation: 5 PMTs only (limited by ANTARES readout) Integration of mini-DOM in ANTARES instrumentation line
8
PPM-DOM: ‘full’ DOM in ANTARES
Objective Long term benchmark of DOM Test of KM3NeT readout electronics Delivery of Production Models for DOM, calibration, readout/DAQ, transmission network Implementation: Install a DOM in Instrumentation Line of ANTARES Adapt optical data transmission to ANTARES network
9
PPM-DU mechanics and deployment
Objective Test of deployment and unfurling of full detection unit Test of handling of backbone cable during deployment and unfurling Delivery of Production Models of DU mechanics Delivery of Production Model of backbone Implementation Several test deployments with smaller DU models Test deployments with 20 storey DU model
10
PPM-DU backbone Objective Implementation
Test of handling of backbone cable during deployment and unfurling Test of penetrators Delivery of Production Models of backbone Implementation Shallow water tests with backbone unfurling Install backbone with autonomous fibre monitoring devices on 20 storey DU If possible, use Delta Berenike for deployment/recovery
11
PPM-Operation: ‘mini-tower’ at Capo Passero site
Objectives Test of KM3NeT fibre optics and data transmission network Test of detector operation Delivery of Production Modules of all components (update) Implementation Install 3 DOMs (two with ETEL, one with Hamamatsu PMTs) Install ‘active’ backbone cables Install ‘active’ storey cables Connect to the existing seabed infrastructure and use the shore station facilities at the Capo Passero site
12
Prelim planning PPM projects
Deployment Production Models Delivered Mini-DOM in ANTARES Mar-Jul 2012 PMTs (Jun-Aug 2012) Full DOM in ANTARES Jul 2012 DOM/calibr./readout/DAQ (Sep 2012) DU-test deployments Apr 2012 Mechanical DU Sep 2012 DU mech. unfurling/Backbone (Oct 2012) Mini-tower Oct 2012 Update on PMs (Dec 2012) Planning needs to be updated during the WPF/L parallel sessions
13
PPM-objectives Questions to be answered with these PPMs:
Can we deploy? Mechanical DU Can we calibrate? DOM in Antares, mini-tower Can we measure signals? idem Can we get the signals to shore? idem Can we measure muon signals? mini-tower What do we learn for the PM? next slides….
14
WPF/L today PMTs mini-DOM in Antares DOM in Antares Calibration
Optical network Timing
15
Tomorrow Electronics DU mechanics and deployment Backbone
Assembly and integration
16
14:30 Intro Els de Wolf 14:15 PMT measurements at ECAP Oleg Kalekin 14:40 PMT measurements at Nikhef Maria Tselengidou 15:00 PMT specs for tendering and alternative for glass PMT lense Paul Kooijman 15:20 CoCo chip on PMT base Eric Heine 15:40 PPM-PMTunit: status and planning mini-DOM in Antares Vlad Popa 16:00 PPM-DOM: planning DOM in Antares 16:20 16:50 PPM-DOM: acoustics Giorgio Riccobene 17:10 PPM: Optical time calibration Umberto Emanuele 17:30 PPM: optical network Jan Willem Schmelling 17:50 Timing of the optical network Henk Peek