Presentation is loading. Please wait.

Presentation is loading. Please wait.

NSLS-II 2016 PMI Project of the Year

Similar presentations


Presentation on theme: "NSLS-II 2016 PMI Project of the Year"— Presentation transcript:

1 NSLS-II 2016 PMI Project of the Year
PMI Rochester Professional Development Day 3 May 2017 Erik D. Johnson BNL NSLS-II Peer Recognition for Excellence in Project Management

2 National Synchrotron Light Source - II
Project at completion - 10,000 times brighter than NSLS with ultra‐low emittance and exceptional beam stability Delivers world leading capability to image single atoms Total Project Cost (TPC) = $912M, TEC= $791.2M; OPC=$120.8M $150M ARRA accelerated funding profile (did not increase TPC) LINAC, 3.0 GeV Booster, 500mA Storage Ring 791.5m circumference 7 Insertion Device Beamlines (capability for over 58 beamlines) Various buildings totaling 628,000 gross square feet (~58,000 m2) Completed 6 months early, added $68M scope from CD‐2 baseline Why and How?

3 Brookhaven National Laboratory
RHIC NSRL BLIP BNL Scientific Data and Computing Center Interdisciplinary Energy Science Building CSI (NSLS site) ATF CFN NSLS-II Long Island Solar Farm

4 Mission Drivers U.S. Department of Energy
The mission of the Department of Energy is to assure America’s security and prosperity by addressing its energy, environmental and nuclear challenges through transformative science and technology solutions. Office of Science mission is the delivery of scientific discoveries and major scientific tools to transform our understanding of nature and to advance the energy, economic and national security of the United States.

5 Office of Science FY17 Request: $5.7B
Largest Supporter of Physical Sciences in the U.S. Research: 42%, $2.4B ~40% of Research to Universities > 20,000 Scientists Supported Funding at >300 Institutions including all 17 DOE Labs Facility Operations: 36%, $2.06B >30,000 Scientific Facility Users $1.8B Mission Innovation Office of Science FY17 Request: $5.7B Slide Courtesy of Stephen W. Meador – Office of Science Director of Office of Project Assessment

6 SC PM Culture Projects are typically ‘build to cost’ with a goal of maximizing science capability Project designs consider potential enhancements and future upgrades—programs and projects take a long view Facility users (and science community) are engaged throughout the project lifecycle Project advisory committees (technical, ESH, management) are thoughtfully appointed and valued SC peer reviews are regular, recognized by the science community, and facilitate sharing of lessons learned SC expectation that PM systems be rigorous and performance be continually improved Slide Courtesy of Stephen W. Meador – Office of Science Director of Office of Project Assessment

7 NSLS-II Mission Need Early 2000’s
Office of Basic Energy Sciences Advisory Committee (BESAC) Development of nanoscale materials – as well as the methods to characterize, manipulate, and assemble them – critical for developing future energy technologies At the time, no light source facility on Earth was capable of addressing this challenge Needed a highly optimized x-ray source to deliver extremely high brightness and flux; exceptional beam stability; suite of advanced instruments, optics and detectors to capitalize on these special capabilities. ~1 nm spatial resolution ~0.1 meV energy resolution Single Atom sensitivity

8 NSLS-II Scope Accelerator Systems Conventional Facilities
Storage Ring (~ ½ mile in circumference) Linac and Booster Injection System Conventional Facilities Ring Building and Service Bldgs (400,000 gsf) 5 Laboratory/Office Bldgs (190,000 gsf) Experimental Facilities Initial suite of seven insertion device beamlines Capable of hosting at least 58 beamlines Research & Development Advanced optics & accelerator components

9 NSLS-II Floor Plan L- LINAC B- Booster RF- RF facility 1-5 – Pendant #

10 Injector and Storage Ring
LINAC BOOSTER STORAGE RING INSERTION DEVICE

11 Beamlines and Endstations

12 Overall Schedule Early completion including all scope additions at the end of December 2014

13 Stakeholder Relations
Sponsor – DOE Office of Science - Basic Energy Sciences Project Execution Plan formalizing relationships and expectations Core group – Integrated Project Team with members from DOE HQ, the local DOE site office, BNL NSLS-II Staff Met frequently – weekly calls with DOE IPT known for robust frank dialogue on project issues User Community As an open access user facility NSLS-II maintained ongoing dialogue with users through workshops (more than 20 before CD-2) User participation in project Advisory teams External Stakeholders and Staff Engagement with the community at large – BNL Executive Round Table BNL Community Advisory Council Frequent outreach to the public during the project

14 Project Organization Closely Aligned with the WBS
Accelerator Experimental Conventional Very helpful in execution of the three major sub projects

15 Project Controls Stood up a Project Controls Organization for NSLS-II
Cost Estimate Data Base – captured basis of estimate Set up robust EVMS communication and tracking Integrated Project Database (IPD) Captures performance, variance analysis Tools and information used to develop the integrated project baseline as well as monitoring performance against the baseline during execution

16 Monthly Cost At its peak NSLS-II was spending ~$1M each day
Risk management and mitigation is really important!

17 Risk Management Tracked and managed risk very carefully
Integrated top-down risk registry yielded 28 key risks Registry was owned and updated by the CAMS as work progressed

18 Risk Management Tracked and managed risk very carefully
Integrated top-down risk registry yielded 28 key risks Registry was owned and updated by the CAMS as work progressed

19 Risk Management Tracked and managed risk very carefully
Integrated top-down risk registry yielded 28 key risks Registry was owned and updated by the CAMS as work progressed

20 Risk Management Baseline changes were tracked as the project progressed EAC was tracked independently, including projections of risk that was anticipated to materialize Scope was added only if available contingency remained above 25% of remaining work Had planned for the mature facility scope on a technically limited schedule Adjusted to anticipated budget and funding profile When ARRA funds became available plans were ‘ready’ Advanced portions of conventional work by 1 year Risk mitigation was ~15.7% of planned work Left $68.1M for scope enhancements

21 Contingency Obligation History
Scope Additions: $68.1M (CD-2 BAC $719M) Added 9% to CD-2 plan Cost Plan ~ $787.1M Total Utilization: $191.6M from CD-2 Utilization for mitigation: EAC $910.6M Plan $787.1M $123.5M $M Contingency utilization for mitigation was 15.7% of Planned work ($123.5M/$787.1)

22 Lessons Learned Catalogued successes and opportunities for improvement Developed “Project Execution Guide” to capture “how to” information Project reviews are the most important management tool to ensure that the project is staying on track. If you are not required to have them, you should inflict them on yourself. From CD-1 to completion NSLS-II had 54 major reviews Resulted in 1,359 recommendations – all tracked to closure

23 Producing High Impact Science
General User Operations CSX-1, CSX-2, XPD, HXN, SRX, IXS, CHX, LiX, AMX, FMX, ISS Science Commissioning XFP, TES, CMS Technical Commissioning ESM, ISR, SMI, NYX, SIX Completion in FY17 BMM, QAS, XFM Completion in FY18 SST-1, SST-2, PDF, FXI, FIS, MET CSX and CMPMSD NSLS-II ABBIX NEXT BDN NPB High coherent flux facilitated the first ever speckle and XPCS measurement of charge stripes in a cuprate X.M. Chen, et al. PRL (2016) 19 beamlines in operations or commissioning Only 2 years beyond CD-4!

24 Keys to NSLS-II Project Success
Basic Energy Science’s (project sponsor) unwavering commitment Top Priority for Brookhaven National Laboratory Strong and continuing interaction with the Stakeholder Community Technical capabilities of the Project Team Excellent Integrated Project Team Adherence to sound project management principles Consistent and frequent peer review (54 major reviews!) Openness of the project team to taking and acting upon advice “The NSLS-II project exemplified the value of strong partners executing complex projects as well as the wide-ranging benefits that diligent exercise of sound project management principles can yield.” Dr. Harriet Kung Dr. Doon Gibbs Associate Director of Science for Basic Energy Science Laboratory Director U.S. Department of Energy, Office of Science Brookhaven National Laboratory Project Management Institute: 2016 Project of the Year Submittal


Download ppt "NSLS-II 2016 PMI Project of the Year"

Similar presentations


Ads by Google