Download presentation
Presentation is loading. Please wait.
1
EVM 202—Lesson 2 EVM in the Acquisition Strategy
September 2016 EVM 202—Lesson 2 EVM in the Acquisition Strategy
2
Lesson 2 Learning Objectives
Terminal Learning Objective Apply DoD Earned Value Management (EVM) policy to assemble the EVM elements of an acquisition strategy and pre-contract activities Enabling Learning Objectives Demonstrate the EVM applicability to a contract Identify Request for Proposals (RFP) sections affected by EVM application Given MIL-STD-881 and a risk assessment, choose the appropriate Contract Work Breakdown Structure (CWBS) level for EVM reporting Distinguish between the EVM-related Defense Federal Acquisition Regulation Supplement (DFARS) clauses Apply appropriate Integrated Program Management Report (IPMR) tailoring
3
What Is Earned Value Management (EVM)?
Program management tool that utilizes a contractor’s Earned Value Management System (EVMS) to integrate the work scope, schedule, and cost parameters of a program, providing objective performance measurement and management As work is performed, the corresponding budget value is “earned” (EV) Acronym Term Definition EVM Earned Value Management An integrated program management tool the program manager (PM) uses to track specific contract cost, schedule and performance objectives to support the Acquisition Program Baseline (APB) goals EVMS Earned Value Management System The contractor-specific internal control system(s) used to meet EVM requirements EV Earned Value The value of completed work expressed in terms of the work’s assigned budget, or budgeted cost for work performed (BCWP)
4
Earned Value Management System (EVMS)
5
Earned Value Management Gold Card
6
Powerful Quantitative Reports
7
EVM within the Contracting Process
8
Statutes Related to EVM
Law Purpose Government Performance and Results Act of 1993 (GPRA) Requires strategic planning and performance standards for Federal Government Federal Acquisition Streamlining Act of 1994—Title V (FASA V) Requires programs to achieve 90% of cost, schedule, and performance goals Information Technology Management Reform Act of 1996 (ITMRA/Clinger-Cohen) Requires executive agencies to report performance of information system acquisitions Weapon System Acquisition Reform Act of 2009 (WSARA) Requires DoD to describe current EVM implementation and recommend policy changes
9
Office of Management and Budget (OMB) EVM Policy
Policy Guidance OMB Circular A-11 Supplement—Capital Programming Guide Purpose Unified guidance to support OMB reporting to Congress Circular A-11 Policy Agencies must establish cost, schedule, and performance goals for major acquisitions and achieve on average 90% of those goals Provides guidance on integration of EVM, Integrated Baseline Reviews (IBRs), and risk management As an OMB Circular, applies to DoD and all executive branch agencies
10
For more on Better Buying Power 3.0, visit http://bbp.dau.mil/.
Better Buying Power 3.0 Achieving Dominant Capabilities through Technical Excellence and Innovation Achieve Affordable Programs Continue to set and enforce affordability caps Achieve Dominant Capabilities While Controlling Lifecycle Costs Strengthen and expand “should cost” based cost management Incentivize Productivity in Industry and Government Employ appropriate contract types, but increase the use of incentive type contracts Ensure effective use of Performance-Based Logistics Incentivize Innovation in Industry and Government Eliminate Unproductive Processes and Bureaucracy Emphasize acquisition chain of command responsibility, authority, and accountability Remove unproductive requirements imposed on industry Promote Effective Competition Create and maintain competitive environments Improve DoD outreach for technology and products from global markets Increase small business participation, including more effective use of market research Improve Tradecraft in Acquisition of Services Strengthen contract management outside the normal acquisition chain—installations, etc. Improve requirements definitions for services Improve the effectiveness and productivity of contracted engineering and technical services Improve the Professionalism of the Total Acquisition Workforce Establish stronger professional qualification requirements for all acquisition specialties Improve our leaders’ ability to understand and mitigate technical risk For more on Better Buying Power 3.0, visit
11
Integrated Program Management Report (IPMR)
Format 1: Work Breakdown Structure The level of detail to be reported normally will be at level three of the Contract Work Breakdown Structure (CWBS), but lower levels may be specified for high-cost or high-risk items. CWBS elements and levels reported shall be those specified in the contract. Format 2: Organizational Categories This format shall be used to collect organizational cost information at the total contract level for organizational elements that reflect the contractor's internal management, rather than for individual CWBS elements structure. Format 2 shall also identify each major subcontractor as defined in the contract. Format 3: Baseline Format 3 lists all significant baseline changes that have occurred by CWBS during the reporting period, to include the contract changes and supplemental agreements, allocations from management reserve (MR) and undistributed budget (UB), and any significant re-phasing of budgets. Format 4: Staffing Format 4 includes staffing forecasts in months by the organizational categories. Format 4 categories may differ from those reported in Format 2 and shall be addressed during negotiations. Format 5: Explanations and Problem Analyses Format 5 is a narrative report prepared to amplify and explain data in the other IPMR formats. Format 6: Integrated Master Schedule Format 6 defines and contains the contractor’s IMS. It integrates with Format 1 WBS, Format 2 OBS, Format 3 Baseline, and Format 5 Analysis. Format 6 contains both the baseline and forecast schedules, and predicts the contract completion date and all interim milestones. Format 7: Electronic History and Forecast File Format 7 provides supplemental historical and time-phased information. Format 7 shall normally address the following: monthly historical time-phased budgeted cost for work scheduled (BCWS), BCWP, actual cost of work performed (ACWP), estimate to complete (ETC), by control account (CA) WBS; future forecast of BCWS and ETC.
12
DoDI 5000.02 EVM Policy Guidance Enclosure 1 Table 8 EVM Application Requirements
Enabling Learning Objective ELO 2.1: Demonstrate the EVM applicability to a contract ELO 2.5: Apply appropriate Integrated Program Management Report (IPMR) tailoring Instructor Guidance Walk students through the DoDI EVM policy shown on this slide. Briefly discuss EVM policy as it relates to other types of contracts (e.g., major modifications; LRIP, etc.) Notes This slide reflects the DoDI EVM requirements, including the Defense Procurement and Acquisition Policy (DPAP) Interim Deviation. This policy grew out of a March 2005 policy that requires an EVMS on cost or incentive contracts, subcontracts, and intra-government work agreements greater than or equal to $20 million then-year (TY). For efforts greater than or equal to $100 million TY, the EVMS must be formally approved by the contracting officer. Implementing EVM on contracts less than $20 million is a risk-based decision at the discretion of the program manager and requires a cost-benefit analysis. EVM policy also requires use of a common Work Breakdown Structure (WBS) in accordance with the DoD MIL-STD-881 (current version), which is now incorporated into the Data Item Description (DID). EVM is discouraged for DoD firm-fixed-price (FFP), level of effort (LOE), and time-and-materials (T&M) contracts, as well as contracts less than or equal to 12 months in duration. Note that: DFARS Clause , Earned Value Management System (DEVIATION) (SEP 2015) raised the compliance review threshold from $50 million to $100 million. DI-MGMT (current version) supersedes the Contract Performance Report (CPR) and Integrated Master Schedule (IMS) DIDs for contracts awarded based on solicitations or RFPs issued on or after July 1, 2012 (See the next slide for details). The IPMR DID is required for contracts where DFARS applies.
13
DoDI 5000.02 EVM Policy Guidance Enclosure 1 Table 9 EVM Reporting Requirements
Enabling Learning Objective ELO 2.1: Demonstrate the EVM applicability to a contract ELO 2.5: Apply appropriate Integrated Program Management Report (IPMR) tailoring Instructor Guidance Walk students through the DoDI EVM policy shown on this slide. Notes This slide reflects the DoDI EVM Reporting The IPMR DID is required for contracts where DFARS applies. IPMR Formats Formats 1-5 are the former CPR formats. Format 6 is the IMS. It applies to all development, major modification, and Low Rate Initial Production (LRIP) efforts whether or not DFARS is applicable. Format 7 provides the WBS-level detail for the Budgeted Cost for Work Scheduled (BCWS), BCWP, Actual Cost of Work Performed (ACWP), and Estimate to Complete (ETC) throughout the contract.
14
Decision Process for EVM Application
Contract = contracts, subcontracts, intra-government work agreements, other agreements All $ thresholds are in TY If contract type is mixed, then apply guidance separately to different parts of contract ID/IQ at task order level
15
Key EVM Inputs in the RFP Development Process
Do you include EVM at all? Where do you address EVM in the RFP? Section C—Description/Specs/Work Statement Section I—General Provisions Section J—Exhibits/Attachments Section L—Instructions to Offerors Section M—Evaluation Factors for Award
16
Section C—Statement of Objectives (SOO) or Statement of Work (SOW)
The SOO or SOW should contain statements requiring: Development of a CWBS at a level adequate for management and contract control The contracted technical effort to use a guidelines-compliant EVMS that correlates cost and schedule performance with technical progress Designation of critical subcontractors by name for EVM compliance and flow down of EVMS compliance to subcontractors An Integrated Baseline Review (IBR) Reference to EVMS data items as part of Integrated Program Management Reporting See the Application of EVM to Contracts job aid for sample SOW paragraphs
17
Section I—General Provisions
Use the DFARS clauses, not the FAR clauses, for EVM. FAR Clauses FAR Notice of EVMS—Pre-Award IBR (July 2006) FAR Notice of EVMS—Post Award IBR (July 2006) FAR EVMS—The Government will conduct an IBR if a pre-award IBR has not been conducted. (May 2014) DFARS Section —Solicitation provisions and contract clause (Dec 2011) Use the provision at DFARS , Notice of Earned Value Management System, in the solicitation instead of the provisions at FAR and FAR Use the clause at DFARS , Earned Value Management System, in the solicitation and contract instead of the clause at FAR Use DFARS , Contractor Business Systems, in the solicitation and contract to allow for withholding payments due to a non-compliant EVMS issue. Includes links to procedures on performing cost-benefit analyses and waivers DoD contracts will not use FAR clauses for EVM.
18
Section J—Exhibits/Attachments
Contract Data Requirements List (CDRL) places data on contract EVM-Related Data Item Descriptions (DID) Integrated Program Management Report (IPMR)—DI-MGMT (current version) supersedes CPR and IMS DIDs, effective July 1, 2012 EVM CDRLs can and should be tailored within bounds of policy Tailoring options are limited for contracts ≥ $50M (frequency, level of detail) Most aspects are tailorable for contracts < $50M (formats, frequency, level of detail, etc.) FM and Cost-Related Data Item Descriptions (DIDs) Contract Work Breakdown Structure—DI-MGMT-81334D Contract Funds Status Report—DI-MGMT-81468A Consider all risk factors when tailoring EVM DIDs Type of contract (determined by cost risk) Technology Schedule Past contractor performance Scope, complexity, risk
19
EVM Central Repository
Provides centralized reporting, collection, and distribution of the Contract Performance Reports (CPRs), Contract Funds Status Report (CFSR), the Integrated Master Schedule (IMS), and the IPMR Mandatory for ACAT 1C, 1D (Major Defense Acquisition Program (MDAP)), and ACAT 1A (Major Automated Information System (MAIS)) programs Available at the EVM Central Repository (EVM-CR) at
20
Section J—EVM Report Details Required
Formats 1-5 Guidance Formats 1 and 2 reporting levels Reporting frequency Submission dates Date of first and last reports Resources shown in dollars or hours Format 5 variance reporting thresholds Fixed number of variances Percentage or dollar thresholds Specific variances Human readable format Format 6 Guidance Degree of networking Reporting frequency Submission dates Date of first and last reports Frequency of schedule risk analysis Electronic data interchange format Format 7 Guidance Reporting levels Subcontractor information Date elements DoD-approved electronic XML format
21
Section L—Instructions to Offerors
Guidance to bidders for the assembly of their proposals Each offeror’s proposal shall include a description of the EVMS to be used in accordance with the appropriate RFP DFARS clauses Compliance with system approval requires: Reference to a “Proof of System Approval” (e.g., Contracting Officer Final Determination (COFD) Letter and a copy of the approved EVMS description); or A plan to obtain EVMS approval to include how the system will be approved Compliance only requires a written summary of the proposed EVMS reference in sufficient detail to show how it addresses all 32 EIA-748 EVMS guidelines
22
Section M—Evaluation Factors for Award
Evaluation of the proposed EVMS is normally undertaken as part of the proposal evaluation process to determine the probability of the system meeting the guidelines For Existing Systems—Evaluation may consist of a confirmation that the referenced system approval is accurate and current. The system should be in use currently, and surveillance should not have identified significant, uncorrected problems. For EVMS (Without approval)—The EVMS description should be evaluated for completeness against the EIA-748 guidelines An on-site examination of a proposed EVMS should not normally be required during proposal evaluation. But if deficiencies are identified, written communications or an on-site visit may be required when approved by the Source Selection Board and Procuring Activity The Defense Contract Management Agency (DCMA) should be requested to provide insight regarding EVMS capability, quality, and past performance
23
DoDI 5000.02 EVM Policy for Cost and Incentive Contracts < $20M TY
EVM optional; based on risk assessment Requires cost-benefit analysis Requires program manager approval DFARS clauses—If you decide to use EVM, use these DFARS clauses: DFARS —Notice of EVMS DFARS —EVMS DFARS —Contractor Business Systems EVM Data Requirements DI-MGMT (current version)—IPMR (Formats 1 and 5 recommended; Format 6 may be recommended) IBR conducted ASAP but not later than 180 calendar days after contract award
24
DoDI 5000.02 EVM Policy for Cost and Incentive Contracts ≥ $20M TY and < $50M TY
Comply with EIA-748 No formal EVMS approval DFARS clauses DFARS —Notice of EVMS DFARS —EVMS DFARS —Contractor Business Systems EVM Data Requirements DI-MGMT (current version)—IPMR (Formats 1, 5, 6, and 7 are mandatory) IBR conducted ASAP but not later than 180 calendar days after contract award
25
DoDI 5000.02 EVM Policy for Cost and Incentive Contracts ≥ $50M TY and < $100M TY
Comply with EIA-748 No formal EVMS approval DFARS clauses DFARS —Notice of EVMS DFARS —EVMS DFARS —Contractor Business Systems EVM Data Requirements DI-MGMT (current version)—IPMR (All seven formats are mandatory) IBR conducted ASAP but not later than 180 calendar days after contract award
26
DoDI 5000.02 EVM Policy for Cost and Incentive Contracts ≥ $100M TY
Comply with EIA-748 EVMS formally approved by cognizant contracting officer DFARS clauses DFARS —Notice of EVMS DFARS —EVMS DFARS —Contractor Business Systems EVM Data Requirements DI-MGMT (current version)—IPMR (All seven formats mandatory) IBR conducted as soon as possible (ASAP) but not later than 180 calendar days after contract award
27
DoDI 5000.02 EVM Policy for Firm-Fixed-Price (FFP) Contracts
EVM discouraged regardless of dollar value Requires Milestone Decision Authority (MDA) approval and cost-benefit analysis If MDA decides to implement EVM, need same EVM DFARS clauses EVM Data Requirements DI-MGMT (current version)—IPMR Formats 1 and 2—Performance in hours (versus dollars) or reported at price rather than cost Format 3—Optional Format 4—Not recommended Format 5—If concerned with schedule risk, focus on schedule variance; rely on IMS variance analysis Format 6—IMS. Consider alternatives: Contractor internal reports, status meetings, or use line of balance schedule Format 7—Not recommended IBR conducted ASAP but not later than 180 calendar days after contract award
28
Draft IPMR CDRL Exercise
29
Acquisition Strategy Practice Exercise
Is Earned Value Management (EVM) required? (Yes or No) Is EVMS approval required? (Yes or No) Which EVM DFARS contract clause(s) and number(s) should be used in the Request for Proposals (RFP)? Which EVM Data Item Description (DID) number(s) should be used in the RFP? What formats of the EVM DID (if any) would you tailor out with the Contract Data Requirements List (CDRL)? Independent Scenarios
30
Acquisition Strategy Practice Exercise Review
31
Practice Exercise: Scenario 1
Your Integrated Product Team (IPT) is responsible for developing the encryption hardware and encryption software for a new satellite system. The acquisition strategy is based on a complex modification of an existing aircraft system. Risk Assessment Technical risk—High Schedule risk—High Cost risk—Low Contract Details Contract Type: Cost Plus Incentive Fee/Award Fee Period of Performance: 36 months Estimated RDT&E Cost: $80M (TY)
32
Practice Exercise: Scenario 2
You are preparing a Concept Exploration RFP. In source selection, you plan to award at least three eighteen month, cost plus award fee study contracts. Contract Details Contract Type: Cost Plus Award Fee Period of Performance: 18 months Estimated RDT&E: $30M (for all three) (TY)
33
Practice Exercise: Scenario 3
Your IPT is responsible for the development of simulation software. The software will be used for System Qualification Testing, Developmental Test and Evaluation (DT&E), and Operational Test and Evaluation (OT&E) of a major weapon system. The software will be provided as Government furnished property (GFP) to the primary contractor as well as the DT and OT testers. Although this is new software to the Government, most of the modules are game simulations considered commercial-off-the-shelf (COTS). Contract Details Contract Type: Firm-Fixed-Price (FFP) Period of Performance: 18 months Provides six-month schedule padding before GFP need date Estimated RDT&E Cost: $20.5M (TY)
34
Practice Exercise: Scenario 4
Your IPT is responsible for developing an RFP for an ACAT-3 target rocket Low Rate Initial Production (LRIP) contract. The Cost Plus Award Fee (CPAF) Engineering and Manufacturing Development (EMD) contract is experiencing an 8 to 12 percent cost growth and is about six to eight months behind schedule, and a number of technical issues have been identified in DT&E. A two year LRIP has been approved while Initial OT&E (IOT&E) testing continues instead of full rate production. The LRIP contract will be a new contract with both Research Development Test and Evaluation (RDT&E) test items and Production line items. Contract Details Contract Type: Fixed Price Incentive Firm Target Period of Performance: 30 Months Estimated RDT&E: $25M ($10M TY1 and $15M TY2) Estimated Production: $80M (TY2)
35
Practice Exercise: Scenario 5
You are the leader of a proposal development team preparing an RFP to outsource the depot maintenance for a major weapon system. The depot work is dependent on the Government getting the system to the depot as scheduled. The contract will include a base year and five annual options. The Statement of Work (SOW) has two primary tasks: Operate depot facilities—a level of effort (LOE) task Repair, upgrade, and test hardware on a time-and-materials (T&M) task order basis. Contract Details Contract Type: Cost Plus Award Fee Period of Performance: 72 months Estimated O&M Costs: $500M (TY)
36
Lesson 2 Summary Terminal Learning Objective (TLO)
Apply DoD EVM policy to assemble the EVM elements of an acquisition strategy and pre-contract activities Enabling Learning Objective (ELO) Demonstrate the EVM applicability to a contract Identify RFP sections affected by EVM application Given MIL-STD-881 and a risk assessment, choose the appropriate CWBS level for EVM reporting Distinguish between the EVM-related DFARS clauses Apply appropriate IPMR tailoring
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.