Presentation is loading. Please wait.

Presentation is loading. Please wait.

Kitakami-site-specific CFS Study update

Similar presentations


Presentation on theme: "Kitakami-site-specific CFS Study update"— Presentation transcript:

1 Kitakami-site-specific CFS Study update
version pub Kitakami-site-specific CFS Study update H. Hayano (KEK) for the CFS team (Tohoku-ILC, KEK) The slides are based on the report in the review, held on 26 September 2017 at KEK. But the cost values are excluded.

2 CFS design studies, specific to Kitakami-site
The design base is TDR and TDR-updated design. Targets Make the CFS-civil design study, specific to Kitakami Candidate Site Make the CFS-utility design study, specific to Kitakami Candidate Site By designing the detailed utilities arrangement, estimate the amount, footprint and connection length of utility devices and the most updated Cost for CFS, for the staging case, especially for option-C.

3 Staging Option C ECM=250GeV SRF 31.5MV/m m m 3489.0m m 4795.2m 2516m PM-12 PM-10 PM-8 PM+8 PM+10 PM+12 (PM-0)drain tunnel 583m space 583m space IR Ecm=250GeV BC BC e+inj e-inj module space margin for option C, 31.5MV/m 51 90 189 189 module space margin for option C, 31.5MV/m 24 module space 24 180 189 90 51 51 45 189 189 cryomodules 180 189 45 51 24 24 17 10 42 42 8 RF unit 8 40 42 10 17 e GeV = 10.0 12.8 53.5 53.5 5.0 E gain (GeV) 5.0 51.0 53.5 12.8 10.0 = e GeV +5.8%margin Total tunnel length = m (20.5km) The reference design for this study is TDR staging option-C

4 Staging Option D

5 Tunnel Access design study
Site-specific CFS design were based on TDR including some updates by 2016, TDR-staging study and site-studies with optimized arrangement of utilities.

6 Access Tunnels Option D Site-specific design of Access tunnels
total length=6992m simple tunnel PM-12 AT-12: 1393m PM-10 Total tunnel length = 33,503.5m (33.5km) Total Accelerator tunnel length = 20,549.5m (20.5km) electron linac AT-10: 1503m PM-8 Interaction Region AT-8: 691m AT・DR (access point to DR):763m AT・DH (branch to detector hall):693m PM+8 damping ring AT+8: 283m positron linac PM+10 AT+10: 943m drain tunnel (0.13%gradient): 4335m PM+12 AT+12: 723m simple tunnel

7 Access Tunnels Option C Site-specific design of Access tunnels PM-10
AT-10: 1503m electron linac PM-8 Total Accelerator tunnel length = 20,549.5m (20.5km) AT-8: 691m AT・DR (access point to DR):763m AT・DH (branch to detector hall):693m Interaction Region damping ring drain tunnel (0.13%gradient): 4335m PM+8 AT+8: 283m positron linac AT+10: 943m access tunnels 5  total length 4876m Detector shaft 1     φ18m depth 75m PM+10 Drain tunnel  1  total length 4335m Utility shaft     φ10m depth 75m

8 Surface Access Stations
Option C Site-specific design of Surface Access stations. arrangement can be optimized and re-arranged site-by-site. PM-10 electron linac AS-10 PM-8 surface design   IP area 78,500m2 1area to be further discussed specially with LCC-MDI. AS-8 Area of surface building (Tohoku Study) surface design access stations   16,600m2 5 area to be further discussed. AS-0a AS-0 Interaction Region AS+10: 4778m2 damping ring AS-10: m2 PM+8 AS+08: 3706m2 river AS+8 AS-08: m2 positron linac AS-0: m2 AS-0a: m2 PM+10 AS+10

9 to be further discussed specially with LCC-MDI.
154kV receive surface design IP area 78,500m2 1 to be further discussed specially with LCC-MDI. 154kV to 66kV Trans 66kV co-generation Water chiller & pumps Air intake/exhaust LNG for co-generation research building He compressor & tanks IP detector assembly building ILD&SiD detector preparation building computing building

10 to be further discussed.
surface design access stations   16,600m2 5 area to be further discussed. Access Tunnel AC power Air intake/exhaust He compressor & tanks Temporary Crane Water chiller, tanks & pumps Rey.Hori/KEK

11 Proposal Underground Access Hall
Site-specific design of Access Halls with detailed utility design. PM-10 Option C electron linac PM-8 To be further discussed with LCC-MDI Interaction Region damping ring PM+8 river positron linac Underground access halls for Immediate access of Helium, Electrics, Waters, and Airs. Direct access of utlities from IP surface to underground hall, through utility shaft. Utility Hall next to the detector hall PM+10 5-floor construction is different from just a cavern. It will be applied the control of “building standards law”. Need to clear the inspection of design, proof of strength. Can we clear them?

12 proposals of underground facility Design
To be further studied and discussed with LCC

13 Proposal of Utility Cavern Movement at Interaction Point
Considering power flow, water flow and air flow between utility shaft and the devices, TDR updated (two vertical shafts) Proposed design of Utility cavern Utility hall Floor Area 50m x 20m = 1000 m2 volume 50m x 20m x 10m =10,000m3 Tunnel volume 53m2 x 200m =10,600 m3 TDR updated in 2015 Utility hall Floor Area 25m x 25m x 5floors = 3125 m2 hall volume 25m x 25m x 43m =26,875m3 Bypass Tunnel volume 13m2 x 200m =2,600 m3 Required Utilities footprint Device Footprint = 1305 m2 Elevator footprint x 5 floors = 780 m2 Carry-in space = 296 m2 connection tunnel between Utility and DR To be discussed w/ LCC-MDI Bypass tunnels between Utility and ML, DH, BDS, dumps Utility-IP distance 66.5m (vibration issue) Utility-IP distance 109m (vibration issue) Q: How simple is Energy flow? what is the effect of mechanical vibration to IP?

14 Consideration of one-way power-flow, water-flow, air-flow at IP
Considering power flow, water flow and air flow between the surface through utility shaft and the accelerator devices, location of Utility Cavern is reconsidered. Surface Facility to DR to DR Energy Flow Vertical shaft Utility Cavern to DR to DR Energy Flow tunnel to RTML to RTML Underground accelerator to ML, BDS, BD to ML, BDS, BD to DH

15 Energy Flow of TDR updated

16 TDR updated

17 Helium system TDR updated DR-SRF, SC-wiggler spin rotator, QCS
Detector

18 Electric system TDR updated 6.6kV 6.6kV 6.6kV 6.6kV 6.6kV 6.6kV 66kV

19 TDR updated secondary level Cooling Water system Primary level

20 TDR updated Air system

21 Energy Flow of Tohoku Study

22 Tohoku study

23 Helium system Tohoku study DR-SRF, SC-wiggler spin rotator QCS
Detector

24 Tohoku study 6.6kV Electric system 6.6kV, 420V, etc. 66kV 66kV 66kV

25 Tohoku study Cooling water system

26 Tohoku study Air system

27 Proposal of New Access Hall shape for Main Linac
TDR Access Hall Proposal of New Access Hall shape for Main Linac direct access of Electric, Water/Air, Helium to Main Linac Tunnel. separate halls for electric, water, helium. Keep enough connection room for cables, pipes, ducts, and helium trasfer lines. Proposed Access Hall to accommodate detail designed utilities Hall:2858 m2 tunnel: 904 m2 total area=3762 m2 total volume=38426m3 125m go to surface 70m After cryogenics change request 135m 48m Hall:135m x 20m = 2700 m2 hight=13m, tunnel:2284 m2 hight=7.5m total area=4984 m2 , volume=52230m3

28 Water drain, RI drain, local maintenance station Upper Cold-Box Lower Cold-Box Electricity Station Cooling Water System Cryomodule/Klystron Access Main Linac Cryomodules Air handling Unit

29 Main Linac Tunnel Assume pre-casting method
for shield wall, to make constructing time short. Waveguide RTML LPDS CRYOMODULE 2,200 1,800 Shielding Wall KRYSTRON Transport Vehicle 4,000 1,500 4,000 9,500

30 Electric Power Distribution Design Study
Detailed design of electric-power utilities were based on TDR power list and TDR accelerator design.

31 Electricity Access Redundant power supply from (1) Local electric company and (2) LNG-CGS Mizusawa Station 154 kV, 15 km Aerial wire Energy Management Service (20 years contract, 5-oku-yen/year added in the electricity fee) 154kV 66kV 275kV 154kV trans co-generation trans ~15km Mizusawa Station ILC IP Site

32 Design of Electric Power Line System (1)
Main subsation 66 kV Co-generation Substation 66 kV Lines 154 kV receive at AS-0 surface 66 kV receive at every AH in the tunnel Energy Management Service 6.6 kV Lines Local Station 66 kV Lines Distribution in tunnel 6.6 kV receive at Main Linac Klystron Tunnel (400V, 200V, 100V distributed) option C Main subsation

33 Design of Electric Power Line System (2)
Main subsation 66 kV Co-generation Substation at Access Hall 66 kV Lines 6.6 kV Lines 154 kV receive LNG space Energy Management Service Local Station AH tunnel AS surface Number of local substation 54 in total splittable racks, distribute in-between Klystrons Linac RF tunnel

34 Cooling Water, Air Distribution Design study
Detailed design of water&air utilities were based on TDR power list and TDR accelerator design.

35 Cooling Water Supply from Oshu-city
Water supply system from the Isawa dam facility to the access stations through pipe in the linac tunnel (250 A) Banshouji point Frontier Park point ~13km Isawa Dam Sakura-yashiki  point Option-C ILC Construction fee between water branch to ILC site can be included in the annual water fee. 10,000m3/day From Oshu-city Banshouji Point, Frontier-park point, Sakura-yashiki point, are under consideration for water supply. IP

36 Design study of Cooling Water, air conditioning
(1) To make more smaller water-pipe diameter Cooling Water Temperature; 35 ℃ supply, DT = 30 ℃ (DT=15 ℃ for racks and WG, 5 ℃ for He compressor), T control = +/- 1℃ ordinary device (2) To make more smaller air-duct diameter Air ventilation; 1/3 of circulation air is exhausted out with HEPA filter, 1/3 fresh air is taken in. put air into RF tunnel, exhaust air from accelerator tunnel, through holes of shield wall. (3) To make tunnel air-temperature control more economical Air conditioning temperature setting; for emphasis on economical operation Temperature of the under-ground (13.4℃) + α =18 〜 22℃ (under study) Distributed Fan-coil unit in RF power-supply tunnel.

37 Recent Site specific Cost study

38 Public works cost & construction cost
CFS & Utility Cost study was done by company estimation This cost study for CFS-civil refer 2014 base of MLIT construction reference. 2014 TDR 5.4% up 2014 TDR 0 – 20 % up 国交省 建設工事費デフレーター 日本銀行企業物価指数 建設資材価格 推移 MLIT construction cost deflater Japan Bank construction materials cost change This cost study for utility refer 2016 base by company. Cost base for estimation of CFS-civil is 2014, after 2011 Big earthquake. Inflation of construction materials vary 0-20%. It is difficult to make average inflation. Electric and Mechanical Utility cost is based on 2016. Comment: we recognize note , but it is too early to take this number as a solid update, because it is also unclear how it change after few or several years, to scope the project budget.

39 Site-specific Option C
Changes TDR Option C Site-specific Option C cost base before 2011-earthquake 2014 for civil, 2016 for others CFS-Civil tunnel 9.5m width & 1.5m shield wall for ML, same to TDR for BDS, DR on-site construction of shield wall pre-cast shield wall & fabrication on site access tunnel 1km for 5 access tunnel assumed site-dependent 5 access tunnel, total length=4876m, same cross-section shape to TDR drain tunnel no cost cosideration 1 drain tunnel with 0.13% & 4335m to the river. natural drain for emergency (for long time AC down) underground access hall 180m x 20m x 14m cavern for 4 access halls new design: separate 4 caverns for 5 access halls detector hall TDR updated design 108m x 25m x 42m φ18 x 70m: 1 vertical shaft Detector hall combined with-Utility-hall 133 x 25 x 42m φ18 x 75m: 1 vertical shaft Utility hall 80m x 20m x 10m: 1 cavern φ10 x 98m: 1 vertical shaft included to detector hall 2 new 3m-width bypass tunnel are added φ10 x 75m: 1 vertical shaft surface access station 5000m2 x 4 stations, with land-dvlp, w-bldg 18000m2 x 5 stations, with land-dvlp, w/o-bldg surface IP 20000m2 x 1, land-dvlp, w-bldg 80000m2 x 1, with land-dvlp, w/o-bldg new surface building design, costed by MEXT rule manage engineering +5.5% including in the estimation CFS-others Electric 275kV recv, 10MW emergency generator are included. Wire is excluded. 154kV recv & 10MW co-gneration, excluded (later, pay in operation) Mechanical (water, air) cooling water for accelerator: ⊿T=10C, whole-vol air excg, tunnel temp=29C water-line to ILC, excluded(later, pay in operation) cooling water for accelerator: ⊿T=30C, 1/3-vol air excg, tunnel temp= 18-22C handling, safty, survey as TDR TEL & Crane are excluded (lease) , accelerator handling & survey are excluded Different points in RED

40 Subjects for discussion
(1) Necessity of connection of Utility cavern with Detector hall is required for more discussion. Utilities for detectors should be considered and included. (2) The connection of Utility vertical shaft with constructed 5 floors in the cavern requires control of “the building standards law”. Just a cavern with no floors is no application of “the building standards law”, will make inspection simpler. (3) Necessity of natural drain tunnel is required for more discussion. (4) Surface building cost is required for more discussion. Comment: IR area, Detector Hall, and surface area/hall needs to be discussed and assessed with LCC-MDI (including experimental groups) before fixing the design-update !

41 Summary of Kitakami-site specific CFS Design study and Cost
(1) Design studies for ILC CFS, specific to Kitakami-site, have been done for access tunnel, surface area, AC power line, Water line, Air-conditioning, and so on. (2) Several new arrangement proposals are presented, we will continue to discuss them. (3) Cost estimation with 2014-base and this utility study have been made, and made comparison with TDR-option-C cost estimation. When we compare them with TDR scheme, this cost study with modification of TDR scheme has resulted 7.8% increase from TDR. To make it consistent with the original TDR scheme, followings cost adjustment are considered; Drain tunnel is excluded, same as TDR,    post-paying-HV station & co-generation are included, put-aside-Accelerator handling & survey are included, (4) Further detailed discussion and further cost-down effort are necessary and on a way.

42 General Comment/Remark
The new site-specific CFS study and cost-estimates with Tohoku-KEK cooperation has been basically agreed with the estimates by ILC-GDE which is including some updated agreeable designs, if it could be based on the same material (specially for Civil-Engineering) cost basis. The new cost estimate is finding about 7.8 % cost increase, if the material cost change effect included. The new study is finding the way to keep the TDR cost by introducing new solutions proposed. Further optimization shall be made, reflecting the general material cost status to be possibly, dynamically moved even in coming years.

43 Contributers Tohoku-ILC (site-specific cost estimation) M. Yoshioka, T. Sanuki, T. Onuki, S. Narita, T. Okamura, H. Hayano, H. Yamamoto, Y. Murakami, H. Aoki, I. Kumagai, Y. Kamezawa, J. Sasaki, S. Yamashita, A. Suzuki, < Committee of underground facility > Y. Onishi, T. Kyoya, K. Takeuchi, K. Fukuda, H. Ohyama, M. Nago, H. Hamajima, S. Hiramatsu, M. Shimo, K. Tamamura, K. Akiyoshi, T. Matsuda, T. Nishi, H. Tanimura, H. Hattori, K. Kamemura, T. Takagishi KEK (TDR & TDR-updated comparison) H. Hayano, M. Miyahara, N. Terunuma, Y. Sugimoto, S. Araki, S. Michizono, A. Yamamoto Note: The discussion with LCC global-CFS,Cryogenics and MDI groups shall be well closely organize to establish the optimum technical solutions with keeping the cost to be stable .

44 Tohoku-ILC (site-specific cost estimation)
Acknowledgement to Obayashi corp., Shimizu corp., Kajima corp., Taisei corp., Oyo corp., Fukada G-inst., Tohoku Electric, Toshiba, Yurtec, Takasago Thermal Eng, Atox, Maekawa, Tobishima, ARUP/CERN, AAA, Iwate Pref., Oshu City, Ichinoseki City, Ichinoseki Fire Station, AAA-civil, LCC/ILC, KEK, Tohoku-ILC-preparation-office LCC/ILC KEK (TDR & TDR-updated comparison) J-power-Electric Power Development co., Nikken Sekkei LTD, Taiyo-Nippon-Sanso corp. ARUP/CERN,

45 End of Slide

46 ( Backup Slides )

47 surface facility Design
( Backup Slides )

48 Collision Point Surface
AS-0 surface Collision Point Surface Total Area ha each zone is splittable, Area shape can be modified

49 Damping Ring Access Surface
AS-0a surface Damping Ring Access Surface Total Area ha each zone is splittable, Area shape can be modified

50 Main Linac Access Surface
AS-12 surface Main Linac Access Surface Total Area 1.66 ha each zone is splittable, Area shape can be modified

51 Cryogenics Arrangement Design
( Backup Slides )

52 Design of Helium Cryogenics System Layout
Surface Facility Cold Box in Access Hall Accelerator Tunnel side Access Tunnel side

53 underground facility Design
( Backup Slides )

54 Proposal of Functions of Utility Cavern extension at Detector Hall
25m Extension of Detector Hall 5th Floor 3rd Floor 4th Floor 1st Floor 2nd Floor Concerns accelerator/detector effect from mechanical vibration, AC power lines effect on utility device from detector magnetic field leakage

55 Proposal of pipes(He, Water and air), power cables arrangement
in the access tunnel This figure shows only the required space in access tunnel for cable and rack This is not the actual installation plan Access tunnel: Required space for Piping Cable rack

56 Electric power facility Design
( Backup Slides )

57 Electric Power from Tohoku Electric Co, Mizusawa Station
ILC Trans Yard (reserved!) Reserved Trans Yards Two 154kV Trans Yards

58 Electric Power Load Table

59 Water, Air facility Design
( Backup Slides )

60 Design of Cooling Water System
Chiller and pumps Main Linac Cooling Water Schematics Access Station Access Hall Main Linac He compressor cooling Design conditions; 35 degree supply, DT = 30 degree (15 degree for racks and WG, 5 degree for He compressor), T control = +/- 1degree ordinary device, Pressure-forward,backward = determined from flow rate and pipe diameter, required flow-rate = from sum-up of RF unit power, assumed values for BDS and DR Water reservoir & supply

61 Design of He Compressor Cooling Water System
Circulation pump 32℃ 8 compressor for one cryo plant DT =5C 37℃ Ground surface Access station Outdoor yard Closed water cooling type cooling tower Machine room Compressor room Circulation pump 32℃ 37℃

62 Design of Water Drainage System
Access Station (surface) Access Hall (tunnel) Design conditions; drainage spring water from tunnel surface to the surface, use spring water as cooling water, or just dump

63 Design of Main Dump Water Cooling System
Pump and Chiller Unit in Surface Pump Unit in Tunnel

64 Design of RI Water Drainage System
undergorund surface

65 Design of Ventilation System
RF tunnel accelerator tunnel Design conditions; 1/3 of circulation air is exhausted out with HEPA filter, 1/3 fresh air is taken in. put air into RF tunnel, exhaust air from accelerator tunnel, through holes of shield wall.

66 Temperature Settings Matters to consider
Water temperature measurement by ground water observation hole as a function of elevation (by Iwate Prefecture/Tohoku Univ./Yachiyo Engineering) Matters to consider Cooling water temperature setting with emphasis on economical operation RF: 35℃⇒65℃ Cryo: 32℃⇒37℃ ・・・・・ Air conditioning temperature setting with emphasis on economical operation Temperature of the under-ground (13.4℃) + α = 18℃ - 22℃ elevation(m) ILC

67 Design of Air Conditioning System
Air handling Unit at the Surafce Cooling water system for air conditioning in the ML tunnel (1) Distributed Fan Coil Unit. (2) 7degree chilled water is supplied for FC (piping with 200A). (3) Chilled water is produced with Chiller unit located at the AS. Air handling Unit in Tunnel Distributed Fan-Coil Unit in RF Tunnel, no FC in accelerator tunnel.


Download ppt "Kitakami-site-specific CFS Study update"

Similar presentations


Ads by Google