TGP Outages Remainder of the Year (Sept. thru Dec.)
6/26/2018 3:03 AM TGP Outages Remainder of the Year (Sept. thru Dec.) Customer Webex September 20, 2016 © 2007 Microsoft Corporation. All rights reserved. Microsoft, Windows, Windows Vista and other product names are or may be registered trademarks and/or trademarks in the U.S. and/or other countries. The information herein is for informational purposes only and represents the current view of Microsoft Corporation as of the date of this presentation. Because Microsoft must respond to changing market conditions, it should not be interpreted to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any information provided after the date of this presentation. MICROSOFT MAKES NO WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS PRESENTATION.
2
Agenda Review of Upcoming Outages September October
6/26/2018 3:03 AM Agenda Review of Upcoming Outages September October Remainder of the Year Q&A Callers are automatically muted in order to minimize outside noise during the presentation. Should you have a question during the WebEx, please: Press ‘*6’ on your phone to unmute, or On the pull down bar on the top of webex, hit the unmute icon © 2007 Microsoft Corporation. All rights reserved. Microsoft, Windows, Windows Vista and other product names are or may be registered trademarks and/or trademarks in the U.S. and/or other countries. The information herein is for informational purposes only and represents the current view of Microsoft Corporation as of the date of this presentation. Because Microsoft must respond to changing market conditions, it should not be interpreted to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any information provided after the date of this presentation. MICROSOFT MAKES NO WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS PRESENTATION.
3
6/26/2018 3:03 AM Disclaimers Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. Unless otherwise stated, all scheduled dates represent gas days as defined in the Tennessee Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time). © 2007 Microsoft Corporation. All rights reserved. Microsoft, Windows, Windows Vista and other product names are or may be registered trademarks and/or trademarks in the U.S. and/or other countries. The information herein is for informational purposes only and represents the current view of Microsoft Corporation as of the date of this presentation. Because Microsoft must respond to changing market conditions, it should not be interpreted to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any information provided after the date of this presentation. MICROSOFT MAKES NO WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS PRESENTATION.
4
Disclaimers Scheduled dates are subject to change.
6/26/2018 3:03 AM Disclaimers Scheduled dates are subject to change. Projects may be added, altered, delayed or cancelled. TGP will provide notice of such additions or changes via DART postings. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this presentation. © 2007 Microsoft Corporation. All rights reserved. Microsoft, Windows, Windows Vista and other product names are or may be registered trademarks and/or trademarks in the U.S. and/or other countries. The information herein is for informational purposes only and represents the current view of Microsoft Corporation as of the date of this presentation. Because Microsoft must respond to changing market conditions, it should not be interpreted to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any information provided after the date of this presentation. MICROSOFT MAKES NO WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS PRESENTATION.
5
Color Key for Maps Yellow Red
Restrictions are possible, but not likely With extended duration, restrictions could be necessary from time to time (M) denotes that meter(s) may be impacted, refer to EBB posting Red Restrictions are probable
6
Zone 0 and L (September) ILI/Cleaning Pig
MLV 9-1S to1-1D (9/22/2016 & 9/24/2016) Capacity of 698,000 reduced to 580k (seg. 109 BH) Pipe Replacement/ Pipe Painting (M) MLV (9/14/2016 – 11/1/2016) Emergent Repair Sta. 9 (9/25/2016 – 9/26/2016) Capacity of 698,000 reduced to 430k (seg. 109 BH) Drip Removal/Hydrotest MLV 9-2 (One Line at a Time) (8/6/ /26/2016) Capacity 0f 698,000 reduced to 620k (seg. 109 BH) Hydrotest MLV to (9/27/ /31/2016) Capacity of 425,000 reduced to 180k (seg. 409 MLV 404)
7
Capacity of 1,588 reduced to 1,200 (seg. 548 BH @ Sta. 860)
Zone 1 (September) Valve Replacement Sta. 555 (9/28/2016 – 10/5/2016) Capacity of 1,588 reduced to 1,200 (seg. 548 Sta. 860) Trap Modification Sta. 550 (9/15/2016 – 10/20/2016)
8
Zone 2 & 3 (September) Emergent Repair
MLV to MLV (8/24/2016 – 10/31/2016) Capacity of 714k reduced to 450k (seg. 114 BH) Trap Modification MLV to 122-1(9/5/2016 – 9/29/2016) Pipe Replacement /Spike Tests Station 96 Area – Multiple Lines (6/8/2016 –12/10/2016) Capacity of 2,363 reduced to 2,250 (seg. 187 BH)
9
Zone 4 (September) Unit Maintenance
Sta A (9/12/2016 – 10/17/2016) Capacity of 1,594 reduced to 1,530 (seg FH) ILI/ Cleaning Pig (M) MLV 313-2A to (9/28/2016 & 9/29/2016) Capacity of 1,774 reduced to 1,120 (seg. 315 BH) Hot Tap MLV & (9/20/ /21/2016) Capacity of 1,774 reduced to 1,600 – 1700 (seg. 315 BH) Station Maintenance Sta. 317 (9/7/ /21/2016) Capacity of 1,774 reduced to 1,680 (seg. 315 BH) Emergent Repair Sta A (9/8/2016 – 9/24/2016) Capacity of 1,846 reduced to 1,746 (seg FH) Unit Maintenance Sta A & 5A (9/6/2016 – 10/4/2016) Capacity of 1,846 reduced to 1,800 (seg. 204 BH)
10
Zone 5 (September) Jacket Water Replacement
Sta. 229 (9/13/2016 – 9/26/2016) Capacity of 743k reduced to 550k (seg. 229 FH) Capacity of 1194k reduced to 1094k (seg. 224 FH/ seg. 299 FH) Unit Maintenance Sta. 245 (8/11/2014 – 8/14/2014) Control Panel Replacement Sta. 241 (8/15/2016 – 10/21/2016) Capacity of 1,030k reduced to 940k - 960k (seg. 245 FH)
11
Zone 6 (September) Block Valve Replacement
Sta. 261 (9/15/2016 – 9/22/2016) Capacity of 1,136 reduced to 880 (seg FH) Control Panel Replacement Sta C (9/5/2016 – 10/3/2016) Capacity of 1,136 reduced to 1000 (seg FH)
12
Zone 0 and L (October) Pipe Replacement/ Pipe Painting (M)
MLV (9/14/2016 – 11/1/2016) Pipe Replacement MLV (10/17/2016 – 11/3/2016) Hydrotest MLV to (9/27/ /31/2016) Capacity of 425,000 reduced to 180k (seg. 409 MLV 404)
13
Zone 1 (October) ESD Test Sta. 87 (10/18/2016)
Capacity of 2,363k reduced to 1,800k (seg. 187 FH) Valve Replacement Sta. 555 (9/28/2016 – 10/5/2016) Capacity of 1,588 reduced to 1,18 0 (seg. 548 Sta. 860) Trap Modification Sta. 550 (9/15/2016 – 10/20/2016)
14
Zone 2 & 3 (October) ESD Test Sta. 114 (10/12/2016)
Capacity of 714k reduced to 375k (seg. 114 BH) Emergent Repair MLV to MLV (8/24/2016 – 10/31/2016) Capacity of 714k reduced to 450k (seg. 114 BH) Trap Modification MLV to 122-2(10/3/2016 – 10/21/2016) Pipe Replacement /Spike Tests Station 96 Area – Multiple Lines (6/8/2016 –12/10/2016) Capacity of 2,363 reduced to 2, ,280 (seg. 187 BH)
15
Zone 4 (October) Unit Maintenance Sta. 323-1A (9/12/2016 – 10/17/2016)
Capacity of 1,594 reduced to 1,530 (seg FH) Hot Tap MLV & (10/10/2016 & 10/13/2016) Capacity of 1,191reduced to 830 (seg. 307 BH) Efficiency Pig MLV to Day TBD (10/3/2016 – 10/17/2016) Capacity of 1,191k reduced to 820k (seg. 307 BH) Efficiency Pig MLV to Day TBD (10/3/2016 – 10/17/2016) Capacity of 1,191k reduced to 540k (seg. 307 BH) Station Outage Sta. 204 (10/18/2016 – 10/24/2016) Capacity of 1,846 reduced to 1,500 (seg. 204 BH) Unit Maintenance Sta B (10/6/2016 – 10/14/2016) Capacity of 1,846k reduced to 1,670k (seg. 204 BH)
16
Zone 5 (October) Unit Maintenance Sta. 245 (8/11/2014 – 8/14/2014)
Control Panel Replacement Sta. 241 (8/15/2016 – 10/21/2016) Capacity of 1,030k reduced to 960k – 1,000k (seg. 245 FH) Maintenance Pig MLV to (10/19/2016) Capacity of 1,030 reduced to 770k (seg. 245 FH)
17
Zone 6 (October) Unit Maintenance
Sta C & 2C (10/3/2016 – 10/7/2016 & 10/10/2016 – 10/11/2016 ) Capacity of 950 reduced to 705 (seg FH) Unit Maintenance Sta A, 1C & 1D (10/3/2016 – 10/7/2016) & (10/17/2016 – 10/19/2016) Capacity of 1,121 reduced to 980 (seg FH) Control Panel Replacement Sta C (9/5/2016 – 10/3/2016) Capacity of 1,136 reduced to 1000 (seg FH) Hydrotest (M) Knollwood Lateral (10/18/2016 – 10/26/2016)
18
Remaining Projects Zone 6
6/26/2018 3:03 AM Remaining Projects Zone 6 Station 265E – Station Outage (11/5/2016 through 11/12/2016) Storage Shut-In test Hebron/Harrison – (10/10/2016 through 10/14/2016) Bear Creek – (10/18/2016 through 10/24/2016) Ellisburg – (10/31/2016 through 11/4/2016) © 2007 Microsoft Corporation. All rights reserved. Microsoft, Windows, Windows Vista and other product names are or may be registered trademarks and/or trademarks in the U.S. and/or other countries. The information herein is for informational purposes only and represents the current view of Microsoft Corporation as of the date of this presentation. Because Microsoft must respond to changing market conditions, it should not be interpreted to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any information provided after the date of this presentation. MICROSOFT MAKES NO WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS PRESENTATION.
19
We welcome your feedback/questions
Suggestions for improvements to this meeting Are the meetings beneficial? Is additional information needed? Questions after the meeting? Other? to one of the following: Your scheduler DART Portal