Download presentation
Presentation is loading. Please wait.
1
INDOT Culvert Sizing Policy
Purdue Road School March 9, 2011
2
Your Presenters: John Bartolo, PE & Crystal Weaver, PE
INDOT Office of Hydraulics
3
The Goal for Policy is a Clear Understanding!
4
Design Storm Frequency
Existing roadway serviceability should be maintained. For example: if roadway serviceability for a lightly traveled two-lane facility is already above Q100, then the Q10 or Q25 should not be used.
5
Allowable Headwater New Alignment
0.14 ft. Maximum Backwater Special Cases: Backwater Dissipates 0.14 ft. or Less at R/W Backwater is Contained in the Channel Remember to Check Outlet Velocity! Flood easements are purchased Very rare and only on large projects 0.14 ft maximum backwater is required by DNR, if a DNR Construction in a Floodway permit is required. 0.14 ft maximum backwater is also required per INDOT policy, if a DNR Construction in a Floodway permit is not required. DNR will accept backwater dissipating to 0.14 ft at the R/W and flood easements, but will probably not accept backwater above 0.14 ft, even if it remains within the channel.
6
Allowable Headwater Replacing an Existing Culvert
Match or Reduce Existing Backwater Exception: Existing Backwater Exceeds 1 ft. If existing backwater exceeds 1 ft, the maximum proposed backwater is 1 ft.
7
Allowable Headwater Other Constraints
Grade of Adjacent Driveways Finished Floor Elevation of Adjacent Buildings Elevation of Surrounding Crop Land Grade of adjacent driveways – don’t want water flowing backwards down the driveway. Finished Floor Elevation of adjacent buildings – if less than 2’ higher than Q100, can trigger the need for a DNR permit. Also may limit the amount of backwater we can accept for a proposed structure. Elevation of surrounding crop land – don’t want water sitting on crops for more than 24 hrs – will cause damage.
8
Allowable Headwater Other Constraints
9
Roadway Serviceability
For a Q100 Design Storm 2 ft. Below Edge of Pavement For Design Storms Less Than Q100 Headwater Can Not Exceed Edge of Pavement
10
Maximum Outlet Velocity
Revetment Riprap < 6.5 ft/s Class 1 Riprap > 6.5 ft/s < 10 ft/s Class 2 Riprap > 10 ft/s < 13 ft/s Energy Dissipator > 13 ft/s See Chapter 34 in the Indiana Design Manual Prefer to keep maximum velocity below 13 ft/s
11
Minimum Outlet Velocity
Typical Minimum Outlet Velocity 3 ft/s Minimum outlet velocity helps prevent silting.
12
Do Not Consider Storage at the Culvert
Storage at the culvert should not be considered because it is generally outside of INDOT’s control. Since there is no guarantee that the storage facility will be present through the entire life of the structure, the culvert should be sized as if it were not present. This is a conservative solution.
13
Priority System Trial 1 - Single Circular Pipe
Trial 2 - Single Deformed Pipe Trial 3 - Single Specialty Structure Trial 4 - Multiple Circular Pipes Trial 5 - Multiple Deformed Pipes Trial 6 - Multiple Specialty Structures Generally speaking, the designer won’t go back down a step in the Priority System. i.e. If the Structure is already a box culvert (Trial 3), a Single Circular Pipe (Trial 1) is probably not going to be a feasible option. Multiple pipes should be avoided, if at all possible. They present a maintenance problem, due to the twinned structures catching debris in the middle. Also, they can catch debris at high flow and lead to culvert failure.
14
Pipe Culvert Interior Designation
Smooth Interior: Manning’s n = 0.012 Corrugated Interior: Manning’s n = 0.024 Smooth interior - Manning’s n of should also be used for CIPP and HDPE liners.
15
Minimum Culvert Size Structure Application Minimum Circular Pipe Size
Deformed Pipe Size Driveway Culvert 15 inch 1.1 ft2 Mainline/Public Road Approach Culvert (2 lanes) (3 + Lanes) 36 inch 6.7 ft2
16
Culvert Extension Process
Match Existing Culvert Size and Type Perform Appropriate Hydraulic Analysis
17
Culvert Sumping Three Sided Structures
Sump structure 18 inches for sand 12 inches for other soils 3 inches for rock or till Structure should not increase in size See standard drawing for stream bed and scour information
18
Culvert Sumping Boxes and Pipes
19
Culvert Sumping Boxes and Pipes
Structure may increase in size, if sump is more than 3 inches Hydraulic modeling may be needed to check capacity.
20
Approved Design Methods
Computer Method FHWA Program HY-8 Hand Method Nomographs From FHWA Publication HDS #5 “Hydraulic Design of Highway Culverts” Available as a Printed Manual, on CD ROM or online
21
Design Responsibility
All Types of Projects Consultant Will Size the Culvert(s) INDOT Hydraulics Will Review Computations
22
Where Do I Get More Information?
INDOT Design Manual Part IV Hydrology and Hydraulics FHWA Hydraulics Home Page Hydraulics Engineering Publication List Hydraulics Engineering Software Reference List
23
Questions
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.