Presentation is loading. Please wait.

Presentation is loading. Please wait.

T1 status (a selection from EDR presentations)

Similar presentations


Presentation on theme: "T1 status (a selection from EDR presentations)"— Presentation transcript:

1 T1 status (a selection from EDR presentations)
Enrico Robutti I.N.F.N. Genova TOTEM T1 Collaboration Meeting CERN, March 8, 2006

2 Chamber mechanics and support structure (S. Cuneo)

3 T1 CSCs MECHANIC DESIGN (1)
LAYOUT OPTIMISATION YIELD TO CSCs OF 10 DIFFERENT GEOMETRY ALL DETAILED MECHANICAL DRAWINGS FOR CONSTRUCTION (> 100!) ARE AVAILABLE ON EDMS SINCE NOV. ’04. NEXT, FINAL RELEASE, WITH LAST CHANGES SUGGESTED BY PNPI IMPLEMENTED, WILL BE ISSUED SOON COMPOSITE, GLUED CONSTRUCTION: 2 SANDWICH PANEL (NOMEX CORE + PCB SKINS), ONE CARRIES THE WIRES, THE OTHER THE GAS CONTAINEMENT FRAME (SEE EXPLODED VIEW) SEVERAL PROTOTYPES HAVE ALREADY BEEN ASSEMBLED AT INFN-GE (PANEL FLATNESS mm) AND OPERATED ON CERN TEST BEAM TOTEM Collaboration Meeting, March 8, 2005

4 DRILLING TOOL DESIGN, CONSTRUCTION AND TEST
DOWEL PIN HOLES MUST BE MACHINED ON CMS OUTERMOST YOKE RINGS ONCE THE TRUSS HAS BEEN ALIGNED GIVEN THE INTEGRATION SCENARIO, A SPECIAL TOOL IS REQUIRED TO POSITION APPROPRIATELY THE DRILLING MACHINE A SORT OF CART, THAT SLIDES ALONG TRUSS RAILS, HAS BEEN DESIGNED, ASSEMBLED AND SUCCESFULLY USED DURING TRUSS QUALIFICATION TESTS DETAILED DRAWINGS ARE AVAILABLE ON EDMS ID /814/829/832/833/835 TOTEM Collaboration Meeting, March 8, 2005

5 MOCK-UP DESIGN, CONSTRUCTION AND TEST
A HALF T1 TELESCOPE MOCK-UP HAS BEEN DESIGNED, IN ORDER TO REPRODUCE THE SAME EXPECTED MOMENTA AND FORCES DISTRIBUTION OF THE ACTUAL HALF TELESCOPE DETAILED DRAWINGS ARE AVAILABLE ON EDMS ID /82/83/84 THE ITEM HAS BEEN ASSEMBLED AT CERN AND USED DURING TRUSS QUALIFICATION TESTS AFTER LAST DETECTOR MASS ESTIMATE, MOCK-UP MASS (290 kg) IS 1.5 TIMES DETECTOR MASS TOTEM Collaboration Meeting, March 8, 2005

6 T1 SUPPORTING TRUSS QUALIFICATION (1)
THE TRUSS HAS BEEN ANCHORED TO CONCRETE BLOCKS WITH PURPOSE-DESIGNED INTERFACE PLATES, TRYING TO REPRODUCE ACTUAL FINAL INSTALLATION CONDITION THEN IT HAS FIRST BEEN SUBMITTED TO A 800 kg LOAD (NEARLY TWICE LAST DETECTOR MASS ESTIMATE) POSITIONED ON THE SYSTEM CENTER OF GRAVITY THEN, C. OF G. LOAD HAS BEEN REMOVED AND HALF T1 LOAD MOCK-UP (290 kg – 1.5 TIMES HALF DETECTOR) HAS BEEN INTRODUCED QUALIFICATION TESTS ALLOWED ALSO TO PRACTICE WITH LIFTING AND DRILLING TOOLS, AND START THE STUDY OF AN INTEGRATION PROCEDURE TO BE CHECKED DURING CMS INTEGRATION TEST FORESEEN BY THE END OF MARCH 2006 BUT, UNFORTUNATELY, THE MEASUREMENTS DONE BY CMS SURVEY GROUP SHOWED DEFLECTIONS MUCH LARGER THAN EXPECTED A FIRST PROBLEM HAD BEEN IDENTIFIED IN THE UNCONTROLLED MOTION OF THE CONCRETE BLOCKS A SECOND LOAD TEST, WITH THE BLOCKS BETTER LEVELLED, SHOWED SMALLER BUT STILL TOO LARGE MOTION OF THE TRUSS TOTEM Collaboration Meeting, March 8, 2005

7 T1 SUPPORTING TRUSS QUALIFICATION (2)
ACTUAL TRUSS WOULD ALLOW T1 TO DEFLECT RADIALLY TOWARDS THE BEAM PIPE BY 5.2 mm (1.5 mm EXPECTED) THE EXPECTED FURTHER MASS REDUCTION OF T1, DUE TO THE USE OF FIBRE OPRTICS INSTEAD OF COPPER, WOULD LIMIT THAT VALUE TO 3.8 mm FURTHER INVESTIGATION IS ONGOING AT INFN GENOVA A KNOWN LOAD HAS BEEN APPLIED TO THE STRUCTURE, AND DEFLECTIONS HAVE BEEN MEASURED ALONG IT WITH A MICROMETER AN IMPORTANT DISCREPANCY BETWEEN THEORICAL (0.30 mm) AND MEASURED (2.4 mm) DEFLECTIONS HAS BEEN CONFIRMED COARSE MEASUREMENTS ALLOWED TO IDENTIFY THE PROBLEM IN THE REGION AROUND THE CONSTRAINTS, THAT SEEMS NOT TO WORK PROPERLY A SOLUTION TO IMPROVE THE CONSTRAINT IS UNDER STUDY TOTEM Collaboration Meeting, March 8, 2005

8 Chamber production at PNPI (A. Krivchitch)

9 General technology chain of the TOTEM CSC manufacturing at PNPI
Building No.66A Storing Input quality control Gluing Set of components for each of CSC Data base CSC storing CSC package CSC components delivery from Italy through CERN at PNPI Building No.2 Anode wiring CSC assembling CSC test No.1 CSC test No.2 Data base CSC shipping from PNPI at CERN TOTEM Collaboration Meeting, March 8, 2005

10 Quality Control Procedures
QC after CSC assembling at PNPI Test station No.1 Test station No.2 QC procedures during CSC manufacturing Input QC procedures QC after CSC transportation at CERN Test station No.3 TOTEM Collaboration Meeting, March 8, 2005

11 Sensor network integrity
Test station No.1 Measure sensor connectivity (should be measured on anode and cathode sides). To measure anode wire connectivity send test pulse to the cathode strip and check response of the test pulses at the anode terminals. To measure cathode strip connectivity send test pulse to the anode wire and check response of the test pulses at the cathode terminals. Apparatus: Pulse generator (~15ns rise time, ~1s pulse width, >1V amplitude). Oscilloscope. Sensor network integrity Check sensor capacitance both anode and cathode (the capacitance value and tolerance should be set). Apparatus: Capacitance measuring tool (manual or automated). TOTEM Collaboration Meeting, March 8, 2005

12 Current and counting rates measurements.
Fill the chamber with real gas mixture. Measure via high voltage: - dark current and counting rate; - current and counting rate with source. Apparatus: Nanoamperemeter. Set of readout electronics (32 channels) for anode and cathode. Test station No.2 Measure gas gain uniformity. Fill the chamber with real gas mixture. Apply normal value of HV. Put radioactive source (caesium-137) at the special selected points. Measure collected charge (current) at the anode outputs at each point. Apparatus: Nanoamperemeter.        TOTEM Collaboration Meeting, March 8, 2005

13 Test station No.3 (at CERN)
Cosmic tests ? Check grounding and shielding quality. Assemble all front-end electronics, connect read out electronics. Set thresholds voltages for working value. Start readout run (no HV applied). The noise count should not exceed threshold. Apparatus: complete set of real electronics, DAQ test version. Check of CSC parameters after its transportation at CERN Re-measure all CSC parameters obtained at PNPI TOTEM Collaboration Meeting, March 8, 2005

14 Electronics (S. Minutoli)

15 TOTEM Collaboration Meeting, March 8, 2005

16 TOTEM Collaboration Meeting, March 8, 2005

17 TOTEM Collaboration Meeting, March 8, 2005

18 TOTEM Collaboration Meeting, March 8, 2005

19 TOTEM Collaboration Meeting, March 8, 2005

20 TOTEM Collaboration Meeting, March 8, 2005

21 TOTEM Collaboration Meeting, March 8, 2005

22 TOTEM Collaboration Meeting, March 8, 2005

23 TOTEM Collaboration Meeting, March 8, 2005

24 TOTEM Collaboration Meeting, March 8, 2005

25 TOTEM Collaboration Meeting, March 8, 2005

26 TOTEM Collaboration Meeting, March 8, 2005

27 TOTEM Collaboration Meeting, March 8, 2005

28 Schedule

29 TOTEM Collaboration Meeting, March 8, 2005
Chamber production Jan 06 Feb 06 Mar 06 Apr 06 May 06 Jun 06 Jul 06 Aug 06 Sep 06 Oct 06 Nov 06 Dec 06 Jan 07 Feb 07 Mar 07 Apr 07 May 07 Jun 07 tool design material procurement input control pre-production test of pre-production full production TOTEM Collaboration Meeting, March 8, 2005

30 TOTEM Collaboration Meeting, March 8, 2005
Electronics Jan 06 Feb 06 Mar 06 Apr 06 May 06 Jun 06 Jul 06 Aug 06 AFEC design AFEC prototype CFEC design CFEC prototype ROC design ROC prototype TOTEM Collaboration Meeting, March 8, 2005


Download ppt "T1 status (a selection from EDR presentations)"

Similar presentations


Ads by Google