1
EYETS16-17 ACTIVITIES EN-EL-CF
Patrick Lelong Jean-Marc Lassauce Georgi Minchev Georgiev
2
OUTLINE PS BOOSTER Copper de-cabling/cabling Optical Fibres PS Complex
Copper cabling LINAC2, LINAC3, LINAC4 & LEIR Conclusions 22/07/2016 JML, PL, GMG EN-EL-FC
3
PS BOOSTER - Copper de-cabling/cabling 1/2
2860 unused cables (120km) to be removed 10 weeks (3 weeks in the machine) in 2 shifts needed; 5 teams of 2 persons per shift; Installation of 372 (25 km) new & removal of 484 (12km) cables + 3.5 weeks in 2 shifts needed; 2 teams of 5 persons per shift. This will be possible if no co-activity (slide 5) and full electrical lockout* (slide 6 ). * safety systems & general services should remains ON JML, PL, GMG EN-EL-FC 22/07/2016
4
PS BOOSTER - Copper de-cabling/cabling 2/2
- New LIU cables installation – planned after de-cabling: PLAN Description of task Responsible Group DEC N0 cables to be removed DEC L [m] Pre-DIC N0 cables to be pulled Pre-DIC L [m] DIR Pryority 10068 Wide-band pickup (BTP PS side) J. Belleman BE-BI N/A Received 5 350 P1 10652 Ring pickups 484 33880 224 15680 10438 New wire scanners periods 4&11 B. Dehning 12 900 3 10426 Watchdog BR.TMD8L1 P. Odier 11 290 24 1440 10488 BLMs (2 FLAT-ICs per section) C. Zamantzas 68 4760 96 6720 P2 Partially - Other (Not LIU) cables installation – planned after de-cabling: - 4 cables, EV, TE- ABT, Antoine PROST; - 4 cables, BI.SMV10, TE-ABT, Felipe Cordobes DOMINGUEZ; - 3 Cables BR.VRPA.4L1B, TE-VSC, Jose De La Gama Serrano JML, PL, GMG EN-EL-FC 22/07/2016
5
PS BOOSTER - Copper de-cabling/cabling - co-activity
No co-activity (work in the same area at the same time) is required for the entire duration of the de-cabling campaign. Other EL activity: Renovation of ERD switchboards – to be done before EYETS16-17: Advantage - Removal of all old electrical distribution materials (cables, final power supplies) from false floor during the de-cabling campaign. Start of EYETS cut power to all ERD switchboards in the PSB (Bldg. 361). Final power supplies available from October Removal of ERD 16, 17 &18 all associated cabling from BCER. EYETS 31th Aug. TS3 New Supports & Switchboards Proton-Ion run from 14th Nov. until 12th Dec. Cabling busbars to switchboards. Power on date for new infrastructure 20th March 2017. 22/07/2016 JML, PL, GMG EN-EL-FC
6
Safety aspects PSB PS BOOSTER - Copper de-cabling/cabling
PSB BCER FALSE FLOOR Electrical risk: Some cables are identified only on one end, the second end could be still connected. In PSB the cable trays are mixed. Special procedure under development. CTP with ‘habitation electrique’ H2/B2 needed. Workers with ‘habitation electrique’ H1/B1 needed. ‘Chargés de Consignation’ for each group needed. Courtesy Gerard Cumer 22/07/2016 JML, PL, GMG EN-EL-FC
7
PS BOOSTER – Cable trays installation
New cable trays installation in the false floor of BRF2; Additional cable trays installation in BOR. 22/07/2016 JML, PL, GMG EN-EL-FC
8
(no de-cabling activity)
PS BOOSTER - Copper de-cabling/cabling - planning Test AUG (no de-cabling activity) 14&15/01/17 Electrical lockout , VIC & False floor consolidation Work during Xmas break & Saturdays included 17/12/2016 25/03/2017 22/07/2016 JML, PL, GMG EN-EL-FC
9
PS BOOSTER - Optical Fibres
Installation BWS: 2 cables 6 fibres entre BAT41 et 4L1. Installation Radiation Monitoring: boucle fibre et environ 6 m de chemin de câble. Les installations seront réalisées en même temps. Mise en place d’un tube équipé de 7 mini-tubes. Une dérivation sur la boucle permettra le raccordement en 4L1 (Installation, soufflage et raccordements: 3 jours). 22/07/2016 JML, PL, GMG EN-EL-FC
10
PSR - Copper cabling (GSM)
PROJET PLAN ZONE NBRE CABLE QTE. CABLE (m) LOCALISATION ACTIVITE TRAVAUX GROUPE DEMANDEUR GSM_CPS 10046 PS 34 1372 BAT 350 CABLAGE CABLES ANTENNE RING ET TUNNELS IT-CS CHAPRON 34 cables / 1.4km 22/07/2016 JML, PL, GMG EN-EL-FC
11
PSR - Copper cabling (BLM)
PROJET PLAN ZONE NBRE CABLE QTE CABLE (m) LOCALISATION ACTIVITE TRAVAUX GROUPE DEMANDEUR LIU-PS 10647 PS 200 44084 BAT PS CABLAGE SLOW BLM PS BE-BI ZAMANTZAS 10061 34 1586 CABLAGE FAST BLM SUITE (PS-BLO) 234 cables / 45km All Straight Sections to be cabled Connexion on BLM’s side Cable extensions from center ring to Bld 359 Bld 359, cabling in the shaft! 22/07/2016 JML, PL, GMG EN-EL-FC
12
PSR - Copper cabling (Others)
PROJET PLAN ZONE NBRE CABLE QTE. CABLE (m) LOCALISATION ACTIVITE TRAVAUX GROUPE DEMANDEUR LIU-PS 11100 PS 2 228 BAT363 - PS CABLAGE BEAM STOPPER F16.STP152 + F16.STP176 EN-STI LENDARO 11088 13 2340 BAT PS CABLAGE BGI VERTICAL BE-BI STOREY 10924 40 BAT 350 FAST TUNER SS08 BE-RF ROSSI 10434 20 3400 RENOVATION BWS SS54 EMERY 37 cables / 6km 22/07/2016 JML, PL, GMG EN-EL-FC
13
PSR - Copper cabling (If possible or partially )
PROJET PLAN ZONE NBRE CABLE QTE CABLE (m) LOCALISATION ACTIVITE TRAVAUX GROUPE DEMANDEUR 10362 PS 6 1200 / 355-PS CABLAGE CABLAGE RF 25KV TE-EPC DE MALLAC LIU-PSB ? 45 11000 BAT DIVERS CABLAGE SYSTÈME VIDE (TRANSFERT LINE) TE-VSC DE LA GAMA 3 1000 BAT BAT 350 CABLAGE SYSTÈME VIDE (LBS) RF 25kV Cable to be defined! Vacuum cabling not in priority 1, the campaign will be prepared and pulled if possible (or partially) 22/07/2016 JML, PL, GMG EN-EL-FC
14
PS outside - Copper cabling
PROJET PLAN ZONE NBRE CABLE QTE CABLE (m) LOCALISATION ACTIVITE TRAVAUX GROUPE DEMANDEUR CTF 4 950 BAT BAT 2009 CABLAGE CABLAGE DI (RENOVATION Z24) - SUITE BE-ICS RAFFOURT LIU-PS 11169 DIVERS 1 30 BAT 250 ETHERNET LIU QFO215 TE-EPC GOMEZ COSTA 10355 PS 21 420 BAT 355 RENOVATION CABLAGE DC DVT PITTET 10354 40 800 RENOVATION CABLAGE DC QSK 50 1500 BAT 368 RENOVATION CABLAGE DC DHZ 14 300 ETHERNET PFW - RF25KV 54 546 ETHERNET LIU DHZ 2 60 DEPLACEMENT OU REMPLACEMENT CABLES 64 620 ETHERNET LIU DVT ET QSK 10967 20 600 BAT 353 CABLAGE RF SOURCES BE-RF DAMERAU CABLE DC QFO215 PAPASTERGIO 272 cables / 6km Bat 353: RF Source Bat 157: DI (Z24 suite) Bat 368: Renovation DC DHZ Ethernet DHZ Bat 2009: DI (Z24 suite) Bat 355: Renovation DC DVT / QSK Ethernet DVT / QSK Ethernet PFW / RF25kV Bat 250: Ethernet QFO215 DC QFO215 22/07/2016 JML, PL, GMG EN-EL-FC
15
TT2 - Copper cabling 15 cables / 3.2km 22/07/2016
PROJET PLAN ZONE NBRE CABLE QTE CABLE (m) LOCALISATION ACTIVITE TRAVAUX GROUPE DEMANDEUR GSM_CPS 10046 TT2 6 450 CABLAGE CABLES ANTENNE TT2 IT-CS CHAPRON 9 2800 BAT 361 -TT2 / AD - TT2 DETECTION INCENDIE TT2 BE-ICS RAFFOURT 15 cables / 3.2km Fire Detection: - 5 cables to Bld 854 from Bld 193 (AD) Fire Detection: - 4 cables to bottom of lift from Bat 361 (BCER) 22/07/2016 JML, PL, GMG EN-EL-FC
16
POPS-B - Copper cabling
PROJET PLAN ZONE NBRE CABLE QTE CABLE (m) LOCALISATION ACTIVITE TRAVAUX GROUPE DEMANDEUR LIU-POPSB BOOSTER 40 2848 BAT CABLAGE POPS-B CABLAGE DC TE-EPC GAILLARD 40 cables / 2.9km 271 245 22/07/2016 JML, PL, GMG EN-EL-FC
17
CPS - Copper cabling Total EYETS: 688 Cables / 71 km
To be confirmed (RF 25kV + Vacuum) : 54 Cables / 13 km Planning of co-activities in PS ring and tunnel to be discussed with coordination team (GSM / BLM) Period for cabling activity From 12/12/2016 to 15/03/2017 22/07/2016 JML, PL, GMG EN-EL-FC
18
PS - Optical Fibres Installation PS.BGIV en SS fibres SM (Installation, soufflage et raccordements: 2 jours). Installation BWS OPS and GBT link: 2 cables entre 368 et SS54 (Installation, soufflage et raccordements: 3 jours). 22/07/2016 JML, PL, GMG EN-EL-FC
19
LINAC2, LINAC3, LINAC4 & LEIR 1/2
PROJET PLAN ZONE NBRE THEORIQ. CABLE QTE THEORIQ. CABLE (m) LOCALISATION ACTIVITE TRAVAUX GROUPE DEMANDEUR LIU-IONS LEIR 54 6060 BAT CABLAGE BPM LEIR INJECTION BE-BI SOBY LINAC2 2 100 BAT 363 CABLAGE ETHERNET TE-EPC GOMEZ COSTA 56 cables / 6km From rack F012 to EI, ETL and ITE lines 22/07/2016 JML, PL, GMG EN-EL-FC
20
LINAC2, LINAC3, LINAC4 & LEIR 2/2
LEIR – LINAC4 1 cable BIC, TE-MPE, Christophe Martin. LINAC4 to LINAC2 4 cables BIC, TE-MPE, Christophe Martin. LINAC4 to PS Booster 3 cables BIC, TE-MPE, Christophe Martin. 22/07/2016 JML, PL, GMG EN-EL-FC
21
EYETS16-17 will be very charged in terms of cabling;
Conclusions EYETS16-17 will be very charged in terms of cabling; Execution of all requests flagged as Priority 1 by LIU Work in two shifts in the Booster; No possibilities to accommodate additional requests. 22/07/2016 JML, PL, GMG EN-EL-FC
22
Thank you!
23
BACKUP SLIDES 22/07/2016 JML, PL, GMG EN-EL-FC
24
General de-cabling strategy PSB 1/2 Knots identification 22/07/2016
JML, PL, GMG EN-EL-FC
25
General de-cabling strategy PSB 2/2 Knots untangling
ZONE RF Main cable tray Racks row de-cabling No de-cabling Attention: This is one-way from racks room to the machine, it will be a second phase in reverse direction! ZONE RF 22/07/2016 JML, PL, GMG EN-EL-FC