1 Marina and Mooring Field
Tuesday, July 25, 2017

2 Mooring Field 2013 Mooring Field Established
2013 Marina Management Contract 2014 Dingy Dock Installed 2016 Dockwa Software 2017 Dockwa Software Expansion

3 Management Contract Services
Enforcement of Mooring Regulations Operation of the Mooring Field (i) Collect and Report registration information and payment from customers, Fees (i) Contractor shall retain 75% of funds collected from daily mooring fees as the ONLY form of compensation from Town. No fees or expenses (whether maintenance, insurance, or otherwise) (ii) Town receives 25% of daily mooring fees collected by Contractor. Maintenance of the Mooring Field (i) Contractor shall keep all moorings and associated tackle in workable condition (ii) Contractor shall promptly submit maintenance reports to the Town

4 Rules Mooring registration. Fees. Securing to a mooring.
a. All vessels shall register with the Town and provide name, residence, mailing address, captain of vessel, vessel registration number, homeport, overall length, beam and draft, and duration of stay. Fees. a. $20.00 per night b. All fees shall be nonrefundable. c. No vessel shall be authorized to occupy a mooring for more than ten days. Securing to a mooring. a. Vessels shall attach by provided pennant line to the bow of the vessel. Pennant line shall not be longer than 15 ft. Vessels shall not moored at the stern or be tied to more than one buoy or points on a vessel. There shall be no dropping or placement of additional anchors or anchor systems from any vessel. c. Vessel owners are responsible for ensuring/reporting mooring lines are in good condition and are maintained tangle free. Vessels allowed in the mooring field. a. Permitted vessels shall be no less than 26 feet and no greater than 55 feet in length. All vessels must be in serviceable condition. b. Every vessel with an enclosed cabin and berthing facilities shall be equipped with a toilet. c. It shall be unlawful for any person or entity to operate a personal watercraft within the mooring field, except for the limited purpose of ingress or egress to or from a vessel for which a permit has been granted for use of the mooring field. d. Vessels engaged in commercial activities are prohibited from utilizing the moorings.

5 Dockwa Online Registration and Payment System - Free
Dockwa Delight - $2,800 s – Pre-Arrival, During Stay and Post Stay Assignments – Electronic way to Track Vessels Long Term Marina License Tracking

6 Next Steps Move toward 100% Online System
Utilize Assignment Function to Identify Non-registered Vessels Executive Office will manage reservations, Police will help with enforcement Town receives 100% of nightly fee.

7 Marina Update Phase I – Emergency Repair
Bulkhead Installation Complete Concrete Cap Installed Water and Electric Rerouted for Future Phases Railing Design Under Review Applied for Reimbursement for Hurricane Matthew Phase II – Remaining West Side Planning for Repositioning Existing Slips Conducted Design Review for Future Phases CAMA Major Permitting Design and Specification Development Underway for Phase II