IWAA2014, 13th – 17th October 2014, IHEP, Beijing
Establishing Control Survey Network for Long Beamlines at Diamond Light Source William Hoffman DLS,UK IWAA2014, 13th – 17th October 2014, IHEP, Beijing
2
William Hoffman IWAA2014, 13th – 17th October 2014, IHEP, Beijing
OUTLINE INTRODUCTION Measurement of Survey Network Pre-Analysis conclusion William Hoffman IWAA2014, 13th – 17th October 2014, IHEP, Beijing
3
INTRODUCTION Diamond Light Source is the UK’s National synchrotron 25 Operational Beamlines
4
I13& I14 Beamlines The I13 beamline comprises two branchlines(Imaging and Coherence) which provide complementary X-ray imaging techniques A Scanning Hard X-ray Nanoprobe beamline is to be built on sector I14 This beamline is dedicated to delivering very small beamsizes for phase-sensitive imaging and spectroscopy. The principal branch is scheduled to be ready for users in mid-2016 Switch between image and
5
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
The longest beamline at Diamond Light Source is 250m. IWAA2014, 13th – 17th October 2014, IHEP, Beijing
6
MEASUREMENT OF SURVEY NETWORK
Transfer Storage Ring Datum 250m Baseline 23m
7
The SR datum was transferred to the I13 Optics Hutch(OH) at 13m and Experimental Hutch(EH) at 36m on the Experimental Hall Floor. A concern was that there could be a potential yaw (swing) error relative to the straight beamline. To enhance the network, several measurement setups were made from 2 operational beamline networks Beamline I18 and adjacent I12 would act as to act as a constraint to any swing error Switch slides All measurements were taken with a TDA5005 and imported to Spatial Analyzer(SA
8
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
SR Network I18 Network I12 Network P5 P6 P131 P141 P142 P137 P143 P145 P132 P136 P144 P133 P135 P134 IWAA2014, 13th – 17th October 2014, IHEP, Beijing
9
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
Measurement Setups IWAA2014, 13th – 17th October 2014, IHEP, Beijing
10
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
RESULTS 2D USMN Point Max Err Ux Uy Uz Umag P131 0.415 0.4 0.383 0.554 P132 0.17 0.465 0.361 0.589 P133 0.497 0.314 0.344 0.466 P134 0.386 0.565 0.684 P135 0.12 0.404 0.381 0.556 P136 0.647 0.302 0.321 0.441 P137 0.464 0.254 0.3 0.393 P5 0.41 0.185 0.232 0.297 P6 0.984 0.192 0.231 0.301 IWAA2014, 13th – 17th October 2014, IHEP, Beijing
11
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
PROOF Achieved First Light: Nov 2010 Number of users: 627 IWAA2014, 13th – 17th October 2014, IHEP, Beijing
12
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
In 2013 the Survey and Alignment team was invited to discuss the positioning of a survey network for I14 beamline IWAA2014, 13th – 17th October 2014, IHEP, Beijing
13
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
Using CAD drawings of building elevations and contours the positions and sightlines of the pillars were established Beam in天河way IWAA2014, 13th – 17th October 2014, IHEP, Beijing
14
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
Pre-Analysis First took all the TDA5005 measured data from I13 Beamline and run a pre-analysis using STAR*NET software MicroSurvey STAR*NET Station Coordinate Error Ellipses (Meters) Confidence Region = 68.26 Station Semi-Maj Semi-Min Azimuth P131 35-42 P132 37-19 P133 36-15 P134 48-36 P135 36-38 P136 36-36 P137 35-28 P5 36-03 P6 34-53 IWAA2014, 13th – 17th October 2014, IHEP, Beijing
15
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
A second Pre-Analysis was run including the new pillar network for I14. The AT401 laser Tracker was used as the measurement instrument. The instrument uncertainties used for the simulation was previously obtained for the SR network surveys Station Coordinate Error Ellipses (Meters) Confidence Region = 68.26 Station Semi-Maj Semi-Min Azimuth P131 128-05 P132 130-17 P133 127-58 P134 129-27 P135 130-32 P136 130-37 P137 132-39 P141 132-31 P142 133-57 P143 136-48 P144 131-20 P145 130-40 P5 131-07 P6 160-39 IWAA2014, 13th – 17th October 2014, IHEP, Beijing
16
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
The Pre-Analysis show a significant improvement in the uncertainty simulation. IWAA2014, 13th – 17th October 2014, IHEP, Beijing
17
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
CONCLUSION The I13 beamline has taken beam successfully. As Beamline I14 is adjacent, it would be advantageous to improve the existing network at I13 by measuring it with the AT401 Laser Tracker The I14 Survey Network an then be established IWAA2014, 13th – 17th October 2014, IHEP, Beijing
18
IWAA2014, 13th – 17th October 2014, IHEP, Beijing
Thank You ! IWAA2014, 13th – 17th October 2014, IHEP, Beijing