Presentation is loading. Please wait.

Presentation is loading. Please wait.

Panama City – Bay County International Airport Project Update

Similar presentations


Presentation on theme: "Panama City – Bay County International Airport Project Update"— Presentation transcript:

1 Panama City – Bay County International Airport Project Update
December 6, 2006

2 1970 1942 1995 Source: Panama City – Bay County Airport Authority

3 Sector Overlay Plan Land Uses

4 Economic Development Airline / General Aviation
Aviation Related Industry Thru-the-Fence Aviation Operations West Bay Area Sector Plan Regional Economic Development

5

6 Major Milestones Feasibility Study Site Selection Study
Sector Plan and DSAP State Permits FAA Environmental Impact Statement (EIS) Land Donation Agreement Design USCOE 404 Permit Permit Challenge Zoning Regulations Existing Airport Sale Finalize Funding Construction

7 Design – Percent Complete
Site Development - 95% Paving/Lighting/Navaids – 50% Utilities – 50% Terminal Building – 50% Facilities (Rental Car, ATC, Maint., General Aviation, Public Safety) – 10% Landscaping, Irrigation, & Signage – 30%

8 Terminal Design Leadership In Energy and Environmental Design (LEED) Certification Silver Level – U.S. Green Building Council 20% reduction in energy use required (30% design goal) Approximately 100,000 sq. ft. (56,000 existing) Includes Customs and Immigration