Baltimore City Department of Public Works
2
Water Contract No. 1204, Druid Lake Finished Water Tanks
Design Notice to Proceed: October 2013 60% Design Completed: July 2015 100% Design Completion: November 2015 Construction: Est. 4-5 years Existing Druid Lake Reservoir will remain as recreational feature of Druid Hill Park
3
Water Contract No. 1204, Druid Lake Finished Water Tanks
400’ and 550’ diameter underground tanks in Pressure Zone 1
4
Water Contract No. 1204, Druid Lake Finished Water Tanks
BCRP Druid Hill Park Master Plan Rendering
5
Water Contract No. 1204, Druid Lake Finished Water Tanks
Project Components
6
Water Contract No. 1204, Druid Lake Finished Water Tanks
Aeration System
7
Water Contract No. 1204, Druid Lake Finished Water Tanks
NEW DICS EXISTING DICS DICS Site Plan
8
Water Contract No. 1204, Druid Lake Finished Water Tanks
Proposed Landscape Concept
9
Water Contract No. 1204, Druid Lake Finished Water Tanks
Rendering of Proposed Tanks at Druid Lake Proposed Sitting Wall and Entrance to Area Above Tanks Looking Northeast
10
Water Contract No. 1204, Druid Lake Finished Water Tanks
Rendering of Proposed Tanks at Druid Lake Looking Northwest
11
Water Contract No. 1204, Druid Lake Finished Water Tanks
Rendering of Proposed Tanks at Druid Lake Looking Southwest
12
Water Contract No. 1204, Druid Lake Finished Water Tanks
Rendering of Proposed Tanks at Druid Lake Looking West
13
Water Contract No. 1204, Druid Lake Finished Water Tanks
Rendering of Proposed BCRP Pavilion at Druid Lake Looking Southeast