National Department Of Human Settlements Q3 Performance

Similar presentations


Presentation on theme: "National Department Of Human Settlements Q3 Performance"— Presentation transcript:

1 National Department Of Human Settlements Q3 Performance
Mr. M. Tshangana Acting Director-General

2 PRESENTATION OUTLINE Overall Performance Programme Performance
Sector Delivery Financial Performance Challenges Recommendations

3 OVERALL PERFORMANCE (OCTOBER – DECEMBER 2015)

4 THIRD QUARTER PERFORMANCE PER PROGRAMME

5 Delivery Past 12 Yrs to Dec 2015 - Sites + Houses
2015/16 Annual target is: Orange = Ministerial Term 2004/05 – 2008/09, Blue = Ministerial Term 2009/10 – 2013/14, Green - Current Serviced Sites represent 31.9% (34 344) of the total and completed Houses are 68.1% (73 380) of the total housing delivery ( ) for 2015/16 to date (Target for the year is – to make up in Q4). Note: 2015/16 delivery figures are up to end December 2015 and are preliminary.

6 2015/16 Delivery and Expenditure For April – December 2015
Annual Targets for 2015/16 (as per Biz Plans May 2015)

7 HSDG Expenditure Performance as at 31 December 2015
Provinces Voted Funds Roll Overs Total Available Year to date (1 April December 2015) Transferred Funds Spent by Provinces Variance Spent vs. Transferred Variance Spent vs. Total Available Transferred as % of voted funds Spent as % of Total Available Spent as % of Transferred Funds Unspent as % of Total Available R'000 Eastern Cape - 90 100 10 Free State 74 82 111 18 Gauteng 76 61 80 39 KwaZulu-Natal 85 92 108 8 Limpopo 59 50 104 Mpumalanga 70 380 6 507 106 15 Northern Cape -681 88 471 77 23 North West 86 89 11 Western Cape 87 710 70 94 30 Total 79 98 24

8 Quarter 3 Delivery Versus Q3 Targets in Biz Plan
Annual Targets for 2015/16 (as per Biz Plans May 2015)

9 Q3 Delivery Performance For Oct – December 2015 - Biz Plan Targets for Quarter 3
Annual Targets for 2015/16 (as per Biz Plans May 2015)

10 HSDG Expenditure Performance October 2015 – December 2015
Provinces Expenditure ( October - December 2015) Transferred Funds Unspent as at 30 Sep 2015 on previous transfers Roll overs Total available Spent by Provinces Spent as % of Total Available R'000 Eastern Cape - 100 Free State 22 194 160 Gauteng 67 KwaZulu-Natal 131 Limpopo ( ) 55 Mpumalanga 51 148 70 380 98 Northern Cape 84 054 29 728 North West ( ) 110 Western Cape 83 953 85 Total 88

11 Delivery Trend: Deliver 55 930 in Q4 2016 To Meet Target of 163 654
Q4 AVERAGE OVER 7 YEARS OF (Delivery of between AND Housing opportunities YEAR QUARTER DELIVERY (Sites + Houses) TOTAL Housing opportunities delivered 2008/09 Q4 60, 212 2009/10 57, 530 2010/11 47, 490 2011/12 57, 953 2012/13 59, 230 2013/14 61, 370 2014/15 41, 931 2015/16 Q1 Q2 Q3 28, 813 43, 159 35, 752 ? to Dec

12 Serviced Sites Delivered Since 1998/99 - 987 232
Note: 2015/16 delivery figures are up to end December 2015 and are preliminary.

13 Houses/Units Delivered Since 1994 - 3 003 221
Note: 2015/16 delivery figures are up to end December 2015 and are preliminary.

14 Status Quo At December 2015 (Q3) and Required Q4 Performance
Annual Targets for 2015/16 (as per Biz Plans May 2015)

15 Looking forward into Q4 Post January 2016 Delivery…..
Annual Targets for 2015/16 (as per Biz Plans May 2015)

16 ACTUAL PERFORMANCE PER PROGRAMME - Communication -
The Department participated in a number of Ministerial outreach programmes as noted in the next slides. During these campaigns, face-to-face communication was done with communities (on 18 October N2 Gateway Presidential Visit, 06 November Presidential Siyahlola Monitoring visit and on 18 November Youth Build Contractor) The campaigns included the use of the help desk and information desk where 30 individual queries were referred for further investigation. The roll-out of the help desk was done in partnership with Municipalities and Provincial Departments of Human Settlements

17 COMMUNICATION AND OUTREACH Quarter 3: October – December 2015
Date Province Municipality Activity 18 October 2015 Western Cape City of Cape Town N2 Gateway Presidential Housing Project Launch 30 November 2015 Eastern Cape Nelson Mandela Metropolitan Municipality Handover of Military Vets House - Walmer 04 December 2016 Clean up Campaign - Walmer 10 December 2015 Free State Mangaung Metropolitan Municipality Launch of Military Veterans Assistance Housing Programme 16 December 2015 Launch and Reception of the Youth Brigade in the Western Cape 29 December 2015 Housing handover at Walmer

18 COMMUNICATION AND OUTREACH Quarter 3: October – December 2015
Date Province Municipality Activity 12 October 2015 Gauteng Boksburg, Birchwood Human Settlements & the Banking Association of South Africa Plenary session 15 October 2015 Western Cape City of Cape Town A Presidential Imbizo and official launch of the N2 Gateway by the President 06 November 2015 Mpumalanga Bushbuckridge Presidential Siyahlola Programme – Water and Sanitation Programme and Housing Handover 18 November2015 North West Klerksdorp, Kanana Youth Contractor Build 07-08 December 2015 Eastern Cape Kirkwood, Sundays River Valley Local Municipality in the Sarah Baartman District Municipality Stakeholder Engagement programme 16 December 2015 Launch and Reception of the Youth Brigade in the Western Cape

19 COMMUNICATION AND OUTREACH Quarter 3: October -December 2015
During all these visits publications were handed out to assist communities to have a source of reference at any time they need information about the Department: Human Settlements Programmes and Subsidies Economic Opportunities created by the Department Guide to owning a government subsidised house.

20 ACTUAL PERFORMANCE PER PROGRAMME Consolidation of DFI’s For A Single DFI
The draft DFI policy foundation was tabled at the DFI steering committee and will be presented to the Portfolio for noting. Consultations with Policy Task Team conducted and the SEIAS questionnaire completed on the DFI policy foundation A “buy and sell” agreement has been drafted and approved in principle and will be effected in March post the Budget Speech. The target date for consolidation is still to ensure completion of the process by 2017.

21 ACTUAL PERFORMANCE PER PROGRAMME Policy Review and Implementation Support
Consultations with provinces on the development of the Draft White for Human Settlements i The Daft Framework on the Policy For Land Inclusive Development 2 Municipalities Assessed for Accreditation Consultation on rational for amending the Housing Act in progress Mine worker strategy implemented and housing opportunities yielded in Marikana Proposed Backyard Policy programme is in its final stages for adoption and implementation by the sector The Human Settlements Intervention to support the Human Settlements development at the Nelson Mandela Bay Municipality has been implemented and yielding results

22 ACTUAL PERFORMANCE Per PROGRAMME Sector Delivery
subsidy Houses delivered as at end September 2015 title deeds were registered for new development title deeds were registered for pre- and post-1994 properties. 1 239.0 ha of land were released for human settlements development,  101.9 ha has been rezoned 128 Informal Settlements Assessed and Categorized 9 Informal Settlements Upgrading Plans developed households upgraded to Phase 2 of the informal settlements upgrading programme

23 ACTUAL PERFORMANCE Per PROGRAMME Sector Delivery
23 441 households upgraded to level 2 of the informal settlements upgrading programme Subsidy units delivered 257 New Title Deeds Pre- and post Title Deeds properties transferred 716.5 ha released for Human Settlements Development

24 DEPARTMENTAL EXPENDITURE 3rd QUARTER
PRESENTATION TO THE PORTFOLIO COMMITTEE:

25 Transfer Payments as at 31 December 2015
Total Allocation Expenditure Variance % Spent Grants 71% Human Settlements Development Grant 79% Urban Settlements Development Grant 58% Municipal Human Settlements Capacity Grant - 100% Entities 38% Social Housing Regulatory Authority: Operational 34 560 Social Housing Regulatory Authority: Institutional Investment Grant 41 936 0% Social Housing Regulatory Authority: Capital Restructuring Grant Community Schemes Ombuds Services 39 521 National Housing Finance Corporation National Urban Reconstruction and Housing Agency 61 000 Housing Development Agency 71 568 59% Departmental Transfers 11 575 7 590 3 985 66% Bursaries Scheme 8 719 4 520 4 199 52% UN Habitat 1 368 1 488 1 701 (214) 114% Total 70%

26 Expenditure by Programme as at 31 December 2015
Branch Total Allocation R' 000 Commitments Expenditure Variance % Spent 1. Administration 34 644 66% 2. Human Settlements Policy, Strategy and Planning 73 538 1 780 55 387 18 151 75% 3. Programme Delivery Support 13 004 81 515 85 285 49% 4. Housing Development Finance 433 70% Total 49 861

27 Operational Expenditure by Programme as at 31 December 2015
Branch Total Allocation R' 000 Commitments Expenditure Variance % Spent 1. Administration 34 644 66% 2. Human Settlements Policy, Strategy and Planning 72 170 1 780 53 848 18 322 75% 3. Programme Delivery Support 13 004 76 504 81 078 49% 4. Housing Development Finance 19 880 433 14 460 5 420 73% Total 49 861 63%

28 Projections by Programme as at 31 December 2015
Branch Projections R' 000 Commitments Expenditure Variance % Spent 1. Administration 34 644 11 980 96% 2. Human Settlements Policy, Strategy and Planning 53 444 1 780 55 387 -1 943 104% 3. Programme Delivery Support 13 004 81 515 36 271 69% 4. Housing Development Finance 433 Total 49 861

29 Human Settlements Development Grant as at 31 December 2015
Presentation to Portfolio Committee 23 February 2016

30 HSDG Expenditure Performance as at 31 December 2015
Provinces Voted Funds Roll Overs Total Available Year to date (1 April December 2015) Transferred Funds Spent by Provinces Variance Spent vs. Transferred Variance Spent vs. Total Available Transferred as % of voted funds Spent as % of Total Available Spent as % of Transferred Funds Unspent as % of Total Available R'000 Eastern Cape - 90 100 10 Free State 74 82 111 18 Gauteng 76 61 80 39 KwaZulu-Natal 85 92 108 8 Limpopo 59 50 104 Mpumalanga 70 380 6 507 106 15 Northern Cape -681 88 471 77 23 North West 86 89 11 Western Cape 87 710 70 94 30 Total 79 98 24

31 Interventions The remaining R1.2 billion was withheld from Gauteng Province R908 million was stopped from Gauteng province and reallocated as follows; R308m KwaZulu Natal R100m Northern Cape R100m North West (Mining Towns) R400m Eastern Cape and to be ring fenced for Nelson Mandela Bay Municipality R300 million to be transferred to GP, and the province has to transfer to HDA. HDA and GP to enter into an Implementation Protocol All the processes regarding compliance of the Division of Revenue Act (DORA) were followed All the necessary documents were forwarded to National Treasury to gazette the reallocations

32 Interventions continues…….
Still awaiting for the gazetting by National Treasury, funds will be transferred once National Treasury has gazetted the amounts, however R300m for HDA was transferred on 02nd February 2016. Contractors workshop was held on the 28th January 2016; Certain provinces e.g. Eastern Cape, KwaZulu Natal and Free State indicated that they are experiencing Cash flow problems and are unable to pay contractors in time A decision was taken to bring forward the final tranche to February March tranches were transferred to EC (R62m), FS (R16 m)and KZN (163 m) on the 05 February 2016.

33 HSDG Expenditure Performance as at 31 December 2015 with Reallocations
Provinces Voted Funds Reallocated Funds Adjustment Roll Overs Total Available Year to date (1 April December 2015 Transferred Funds Spent by Provinces Variance Spent vs Transferred Variance Spent vs Total Available Transferred % voted funds Spent % Total Available R'000 Eastern Cape - 90 72 Free State 74 82 Gauteng 76 75 KwaZulu-Natal 85 84 Limpopo 59 50 Mpumalanga 70 380 6 507 Northern Cape -681 77 61 North West 86 89 Western Cape 87 710 70 Total 79

34 Finance Linked Individual Subsidies
Report as at 31 December 2015 Province Annual Targets Delivery Performance Sites Units Funds Allocated Expenditure R'000 Eastern Cape - 200 12 442 176 9 310 Free State 37 5 100 Gauteng 90 1 293 677 184 KwaZulu-Natal 2 000 350 81 750 296 23 956 Limpopo 300 24 900 7 1 080 Mpumalanga 100 8 700 24 Northern Cape 30 2 182 North West 277 23 359 Western Cape 145 6 250 307 19 608 Total 2 090 2 732 1 487 54 138

35 Rectification Report as at 31 December 2015 Province Annual Targets
Delivery Performance Sites Units Funds Allocated Expenditure R'000 Eastern Cape - 2 487 2 786 Free State 280 93 453 Gauteng KwaZulu-Natal 2 273 2 224 98 407 Limpopo 500 43 500 Mpumalanga 18 400 Northern Cape 11 019 49 5 944 North West 320 44 998 880 13 067 Western Cape 479 11 200 163 199 Total 6 059 6 400

36 Operational Capital Budget
Report as at 31 December 2015 Province Annual Targets Delivery Performance 5% allocation Funds Allocated Expenditure R'000 Eastern Cape 98 119 88 373 42 202 Free State 52 864 35 889 Gauteng KwaZulu-Natal 92 539 Limpopo 64 194 30 938 23 377 Mpumalanga 63 258 60 344 44 893 Northern Cape 19 020 19 019 North West 51 908 38 132 Western Cape 98 756 64 452 Total

37 Disaster Relief Programme
Disaster Relief Grant Disaster Relief Programme Province Annual Targets Delivery Performance Sites Units Funds Allocated Expenditure R'000 Eastern Cape - 301 253 33 964 Free State Gauteng 40 000 KwaZulu-Natal 614 92 774 Limpopo 34 332 182 Mpumalanga 34 098 282 35 593 Northern Cape North West 38 507 338 37 352 Western Cape 5 077 Total 1 487

38 OVERVIEW OF PROVINCIAL NON-FINANCIAL PERFORMANCE AND HUMAN SETTLEMENTS DELIVERY TRENDS (HSDG) FOR THE PERIOD 2015/16: 1 April – 31 December Note: Analysis dates reflected are informed by the data source used: Live data, month old provincial backed-up data in NDHS warehouse, or statistics reported by PDHSs Ver: 20 January 2016

39 Where we are as at December 2015 (Q3) in relation to Annual Targets and what’s left to be done in Q4
Annual Targets for 2015/16 (as per Biz Plans May 2015)

40 Quarter 3 Delivery versus Q3 Targets in Biz Plan
Annual Targets for 2015/16 (as per Biz Plans May 2015)

41 Q3 Delivery performance (Oct – December 2015 only) in relation to Biz Plan Targets for Quarter 3
Annual Targets for 2015/16 (as per Biz Plans May 2015)

42 Urban Settlements Development Grant as at 31 December 2015

43 USDG Expenditure Performance as at 31 December 2015
( YEAR TO DATE EXPENDITURE (01 JULY DECEMBER 2015) Municipality Voted Funds Rollover from 2014/15 Total Available Funds Actual Transfer Spent by Municipali Variance Spent vs. Total Available Funds Transferred as % of Voted Funds Spent as % of Total Available Funds Spent as % of Transferred Funds Unspent as % of Total Available Funds Unspent as % of Transferred Funds R'000 Buffalo City - 70.0 41.6 59.4 58.4 40.6 Nelson Mandela Bay 64.0 46.1 72.0 53.9 28.0 Mangaung 77 536 80.7 35.7 49.2 64.3 50.8 Ekurhuleni 58.0 29.1 63.4 70.9 36.6 City of Johannesburg 54.0 43.2 80.0 56.8 20.0 City of Tshwane 36 868 50.0 34.7 71.1 65.3 28.9 eThekwini 65.0 44.8 55.2 City of Cape Town 44.9 27.7 69.0 72.3 31.0 Total 58.5 34.3 62.9 65.7 37.1

44 Consolidated Funds utilisation as at 31 December 2015
Description Allocated Budget % of Total Allocated Budget Spent by Municipality % Spent Variance % Unspent R'000 Land acquisition 1.7 37 753 20.1 79.9 Housing 29.7 31.2 68.8 Roads and Stormwater 12.4 37.4 62.6 Transport 12.2 36.0 64.0 Water and Sanitation 25.4 36.4 63.6 Electricity 5.6 43.8 56.2 Waste Management 2.7 44.5 55.5 EPMO-Project Management Funding 32 648 0.3 14 425 44.2 18 223 55.8 Economic and Rural Development 5 696 0.1 - 0.0 100.0 Planning 56 468 0.5 14 330 42 138 74.6 Re Aga Tshwane 1.3 72 252 48.2 77 748 51.8 Economic Development and Planning 89 909 0.8 13 750 15.3 76 159 84.7 Office of City Manager 2 460 98.3 Spatial Planning and Urban Design 7 022 5 932 84.5 1 090 15.5 Unaccounted Roll over 44 197 0.4 100 Total 34.3 65.7

45 Interventions Intention to Withhold letters were sent to City of Cape Town, eThekwini and Ekurhuleni Metros Ekurhuleni Responses R365m was spent in December 2014 which was 18% and this year by December the spending is 29.1% Other projects are starting to yield benefits (Leeuwpoort) The Metro is working with EDA to acquire properties and also with HDA to acquire land Senior Manager seconded to Human Settlements as it has the biggest budget of USDG ( R519 m)

46 Interventions continues
City of Cape Town responses Historic trends ( They exceeded 90%) in all the years except 2013/14 The city has implemented a Portfolio Project Management methodology and systems to assess and review all projects Outcomes in case of stopping the grant Breach of contract claims from contractors Legal costs Infrastructure and Informal settlements targets delays

47 Interventions continues
Ethekwini responses The Interim services and Ablution facilities experienced large volumes of applications received for tender. The municipality has remedied the situation and the contracts have been awarded The Western and the Northern Aqeduct has experienced challenges during the year relating to community unrest

48 Recommendations R150m be stopped for COCT and be reallocated to identified Metros that have moving projects and have capacity to absorb the additional funding R300m be stopped from EMM and be reallocated to identified Metros that have moving projects EMM, DHS, HDA and SHRA to discuss the properties and land parcels that are in the process of being acquired eThekwni to give the scheduling of the projects, projections etc on the delayed projects

49 Non Financial Information as at 31 December 2015

50 BCM PERFORMANCE AS AT 31 DECEMBER 2015
Roads and storm water -Targeted 20 kilometres of roads resurfaced/rehabilitated/resealed achieved 83 kilometres. -Targeted additional 3 kilometres of storm water drainage and achieved 8 kilometres Transport -Targeted 0.80 kilometres of new pedestrian walkways to be constructed and achieved 0.83KM -Targeted 3 new taxi ranks and achieved 3. -Targeted 1taxi stop and achieved 3. Sanitation -Targeted to install 1289 additional toilets for informal settlement dwellers and installed 1490. Solid Waste Management -Targeted 23 areas to be provided with access to weekly refuse removal and provided to 23 areas. -Targeted 5 areas n informal areas to be provide with solid waste removal services and provided to 5 areas.

51 NELSON MANDELA BAY PERFORMANCE AS AT 31 DECEMBER 2015
Access to Basic Services: Sewerage Targeted to provide sewer connections to 350 additional households and managed to provide 321 additional households with sewer connections (1 293 annual target) Access to Basic Services: Solid Waste Management Targeted to provide households with access to weekly refuse removal, provided for households ( annual target) Provided households in informal areas with access to solid waste removal services Provision of Electricity and Associated Infrastructure 850 additional households (RDP) were targeted to be provided with electricity connections, 43 were actually connected (1 945 annual target) 29 streetlights were installed Provision of Socio-Economic Amenities - 1 cemetery developed/upgraded Local Economic Development and Job Creation Targeted to create job opportunities and managed to create a total of EPWP jobs ( annual target)

52 MANGAUNG PERFORMANCE AS AT
31 DECEMBER 2015 Access to Basic Services: Sewerage Targeted to provide sewer connections to additional households and managed to provide additional households with sewer connections (6 410 annual target) Access to Basic Services: Solid Waste Management Targeted to provide additional households with access to weekly refuse removal, and managed to provide for households (4 775 annual target) Targeted to provide households in informal areas with access to solid waste removal services, and managed to provide for households ( annual target) 1 waste minimization project initiated, and the annual target is 1. Provision of Electricity and Associated Infrastructure 1 250 additional households (RDP) were targeted to be provided with electricity connections, were actually connected (annual target is 2 500) Provision Socio-Economic Amenities - No information reported Local Economic Development and Job Creation Created a total of 234 EPWP jobs

53 EKURHULENI PERFORMANCE AS AT 31 DECEMBER 2015
Access to Basic Services: Water Targeted to provide water connections to 200 water service points and managed to install 435 water service points Targeted to connect 270 households to water and actually connected 1 080. Access to Basic Services: Sewerage Targeted to provide 200 additional sanitation service points and achieved 435 Spatial Development and the Built Environment Performance was as follows: 2 informal settlement targeted for upgrading, upgraded 2 Targeted to transfer 151, transferred 229 Title deeds Provision of transport and roads infrastructure The performance was as follows: Targeted 12km paved roads, achieved 24km of Targeted to install 7km storm water drainage , installed 34km Targeted to construct 3km pedestrian walkways, actually constructed 3km Targeted to construct 4 bus stops and actually constructed 2 bus stops

54 CITY OF JOBURG PERFORMANCE AS AT 31 DECEMBER 2015
Access to Basic Services: Sewerage 1 177 sanitation service points planned to be installed, but 543 sanitation service points were installed (2 527 annual target) Access to Basic Services: Solid Waste Management 9 259 additional households were provided with access to weekly refuse removal households in informal areas with access to solid waste removal services 6 waste minimisation projects were planned to be initiated, and the metro overachieved and initiated 12 waste minimisation projects. Provision of Electricity and Associated Infrastructure 347 additional households (RDP) were provided with electricity connections, but the target was to connect 750 households to electricity. 450 streetlights were targeted for installation, but 213 streetlights were actually installed Provision of Socio-Economic Amenities 33 libraries planned for development/ upgrade, and 2 were actually done (33 annual target) 14 safety and emergency facilities upgraded/ developed (30 annual target)

55 CITY OF TSHWANE PERFORMANCE AS AT 31 DECEMBER 2015
Access to Basic Services: Water 3 803 bulk water pipeline (km) installed Access to Basic Services: Sewerage sanitation service points targeted with no actual output 2 150 sewer connections targeted with no actual output Access to Basic Services: Solid Waste Management The Metro does not report on solid waste management. Provision of Electricity and Associated Infrastructure 81 streets lights targeted with no actual output 5 high mast lights targeted with no actual output Provision of Socio-Economic Amenities The Metro does not report on Socio-Economic Amenities since there are no project linked Local Economic Development and Job Creation Targeted to create job opportunities and managed to create a total of EPWP jobs.

56 ETHEKWINI PERFORMANCE AS AT 31 DECEMBER 2015
Spatial Development and the Built Environment During Quarter 2, the Metro performed as follows: 686 households living in informal settlements were upgraded In terms of sites serviced, a total of 178 sites were serviced instead of the 140 targeted 100 title deeds were transferred to eligible beneficiaries Provision of transport and roads infrastructure 11km paved roads 5km pedestrian walkways constructed Access to Basic Services: Water Targeted to provide water connections to 800 additional households and managed to provide additional households with water connections 5 water service points installed for informal settlements dwellers within 200m radius

57 ETHEKWINI PERFORMANCE AS AT 31 DECEMBER 2015
Access to Basic Services: Sewerage Provided 395 additional households with sewer connections 5 sanitation service points installed Access to Basic Services: Solid Waste Management Provided households in informal areas with access to solid waste removal services 88 waste minimisation projects initiated Provision of Electricity and Associated Infrastructure 4 442 additional households was provided with electricity connections Provision of Socio-Economic Amenities 2 parks/ leisure facilities developed/upgraded 1 Community swimming pool developed/ upgrade Local Economic Development and Job Creation Targeted to create job opportunities and managed to create a total of EPWP jobs

58 CITY OF CAPE TOWN PERFORMANCE AS AT 31 DECEMBER 2015
Access to Basic Services: Sewerage Targeted to install sanitation service points (toilets) for informal settlements dwellers, and an actual of 494 sanitation service points were actually installed (2 800 annual target) Access to Basic Services: Solid Waste Management - No information reported Provision of Electricity and Associated Infrastructure - No information reported Provision of Socio-Economic Amenities 1 pre-school/ ECD centres was planned for development/ upgrade by the end of quarter 2, and 1 was actually developed/ upgraded (annual target is 3) Local Economic Development and Job Creation Targeted to create job opportunities and managed to create a total of EPWP jobs ( annual target)

59 Municipal Human Settlements Capacity Grant as at 31 December 2015

60 Municipal Human Settlements Capacity Grant Expenditure Performance as at 31 December 2015
YEAR TO DATE EXPENDITURE (01 JULY DECEMBER 2015 ) Municipality Voted Funds 2014/15 Rollover Total available funds Transferred funds Spent by Municipality Variance Spent vs Total Available Funds Spent as % of Total Available Funds Unspent as % of Total Available Funds R'000 % Buffalo City 9 253 - 44 9 209 0.5 99.5 Nelson Mandela Bay 9 847 23 235 33 082 6 245 26 837 18.9 81.1 Mangaung 9 206 526 5.7 100 Ekurhuleni 14 313 50 817 65 130 3 877 61 253 6.0 94.0 City of Johannesburg 16 505 59 573 76 078 2 354 73 724 3.1 96.9 City of Tshwane 12 831 16 419 29 250 49 29 201 0.2 99.8 eThekwini 14 342 39 980 54 322 8 145 46 177 15.0 85.0 City of Cape Town 13 703 31 580 45 283 9 544 35 739 21.1 78.9 Total 30 740 9.6 90.4

61 “We have come a long way – Celebrating 20 Years of Freedom!”
Thank You “We have come a long way – Celebrating 20 Years of Freedom!”