Presentation is loading. Please wait.

Presentation is loading. Please wait.

AMRU Release 2 Release Report

Similar presentations


Presentation on theme: "AMRU Release 2 Release Report"— Presentation transcript:

1 AMRU Release 2 Release Report
30 October FY 03 Rusty Prentiss

2 Contents Release Plan within Larger JTAMS Integrated Master Schedule
AMRU Release/Block Plan: Releases 1 & 2 make up Block 1 Release 2 & 3 & 4 = Block 2 Release 5 = Block 3 Risks Progress Graphic for Release 2: Cumulative Flow Diagram Burn Up / Burn Down charts Story Aging Graphic for Release 2: Histogram Summary of Progress

3 Engineering and Manufactuing Demonstration
Joint Training and Maintenance System (JTAMS) Increment 1 Government Roadmap Schedule Showing STIM (in green) TODAY is 19 Oct FY3 FY 00 FY 01 FY 02 FY 03 FY 04 FY 05 FY 06 FY 07 FY 08 MDD MSA TECH DEV Engineering and Manufactuing Demonstration PROD & DEPLOYMENT Milestones & Phases MS A MS B MS C FRP DECISION IOC Post CDR Assessment JTAMS-1 IOC Final RFP Release TD EMD Contract Award TD TD EMD SSR Technical Reviews ITR ASR SRR PDR PDR CDR PRR FCA PCA Block 1 Block 3 MRU Development Block 2 Prototype Testing DT&E EDMs Development Testing LFT&E Operational Testing EOA OA IOT&E Deliveries (Prototypes / EDMs) 3

4 MRU S/W Release Schedule
TODAY is 19 Oct 03 FY 02 FY 03 Q 1 Q 2 Q 3 Q 4 Q 1 Q 2 Q 3 Q 4 PDR PDR CDR OA 1 2 3 4 5 AMRU Milestones 5 Sprints 5 Sprints Block 1 complete MRU on contract STIM S/W Release 4

5 Risks Likelihood 1 2 3 4 5 Consequence Likelihood 1 2 3 4 5
Number: FY02-1 Risk: STIM will be the first involvement with an agile development approach for V-Robotics (and for the government program office Impact: A lot of time may be required to explain our process and how we fit in to the bigger acquisition picture Mitigation Strat: Offer training to key V-Robotics and PMO staff Number: FY02-13 Risk: OBD interfaces specs have not been provided to AMRU Impact: Re-work may be needed if assumptions prove to be wrong – should have minimal schedule impact Mitigation Strat: Postpone Firebird and JUGV as long as possible. Assume interfaces will be same as on Global Hawk. Likelihood Consequence Likelihood Consequence

6 MRU Block 1 Implementation Progress
Based on the AMRU STIM Release 2 report, cut and paste the measurement visualization that provides a holistic picture of AMRU’s development progress. Add in vertical lines that mark Release 1 and Release 2 from AMRU. Note on the chart when AMRU stopped waiting for the mobility data and started working mobility based on their assumptions.

7 How to Read Cumulative Flow Diagram
The Cumulative Flow Diagram (CFD) uses an area graph to chart the transition of items from one state to another. The states that are summarized here (within our Agile management tools there are more states than summarized here for use at the team level) Readywe have converted the requirements received from V-Robotics into epics and stories, and their value has been estimated as story points Dev (Development)the work represented by those story points is actively being coded and unit tested Testthe work represented by the story points is in integration test and regression tests (the automated ones within MRU; not the manual ones at the integration lab) Ready for V-Roboticssoftware and related compliance documentation is ready to be delivered to V-Robotics upon request and is available to all authorized stakeholders within the MRU sandbox area (contact Margaret Wilson for access permission). At minimum, software is delivered to V-Robotics at the completion of the Block. The sum of Dev and Test is the work being conducted at any given time. Looking horizontally, you can see the cycle time of stories across the time span, both holistically and for each state Looking vertically, you can see the amount of work that is in different parts of the life cycle at any particular time

8 Block 1 Burn Down

9 Block 1 Burn Up

10 How to Read Burn-down and Burn-up Charts
A burn down chart is a graphical representation of showing the amount of work remaining on a vertical and a timeline on a horizontal axis. If the tasks increase during a sprint at the same rate as the team completes them, a burn-down chart will give the impression that no work was performed. This is the reason burn down charts are typically used for internal team management and not shared outside the sprint team. A burn-up chart shows how much work was actually accomplished (as opposed to how much work remains to be completed) and how much total work the project contains. Burn-up charts are extremely useful to understand team progress even if the scope changes.

11 Story Aging AMRU Release 2
Note to V-Robotics: the 20 story points represented by >9 sprints category all relate to JCCS interface information that is needed for MRU to work the Mobility aspect of the model. We have proceeded without this data based on best information available. This introduces a risk of later rework.

12 How to read the Story Aging Histogram
There are six categories that indicate how long the story was in the “Ready” state without being worked. Stories that have been in the Ready state for >2 releases may be candidates for removal from the backlog if the reason they have aged is that they don’t have sufficient value For stories that have been in the Ready state for >1 release due to external information that is not available, the issue should be raised to a management level that can help to resolve the issue AMRU uses a template for characterizing the value and complexity of the item for items that have to raised to higher levels of technical and/or business management

13 Summary Block 1 implementation is on schedule. The remaining items in the backlog are associated with later Blocks. With the exception of the JCCS information related to Mobility, the information needed to implement the STIM model have been available, even if not always timely. We have begun using “best available info” for the Mobility aspects of the model. We are concerned that, if our assumptions are incorrect, we may have to rework part of the model to correct the data we have used. Impact on the architecture and schedule for this kind of rework is unknown at this time Juggernaut and V-Robotics staff were engaged and helpful in both the Release 1 and Release 2 demonstrations. We are pleased that early implementation of the UAV data has helped V-Robotics to refine their designs and interfaces.


Download ppt "AMRU Release 2 Release Report"

Similar presentations


Ads by Google