Presentation is loading. Please wait.

Presentation is loading. Please wait.

Tracker cooling loop “check out” draft for discussion

Similar presentations


Presentation on theme: "Tracker cooling loop “check out” draft for discussion"— Presentation transcript:

1 Tracker cooling loop “check out” draft for discussion
22 August 07 P. Tropea 22 August 07 Cooling segment characterization

2 Cooling segment characterization
CONTENTS The cooling plant layout Mapping of cooling circuits Pressure test Continuity test First circulation: balancing, Dp & DT measurements 22 August 07 Cooling segment characterization

3 COOLING PLANT GENERAL LAYOUT
3 cooling loops in cascade (chiller, brine, fluorocarbon) 7 detector cooling unit (2 for Silicon Strip Tracker, 2 for Thermal Screen, 1 for Pixels and 2 for Preshower) 22 August 07 Cooling segment characterization

4 DETECTOR COOLING UNIT LAYOUT
22 August 07 Cooling segment characterization

5 Cooling segment characterization
DETAILS OF MANIFOLDS MAIN DISTRIBUTION LINE SINGLE COOLING LOOPS Manual regulation valve to set flow rate Cold C6F14 Pneumatic shut-off valves Detector Calibrated orifice to allow flow rate measurement on the basis of the differential pressure. Return C6F14 22 August 07 Cooling segment characterization

6 Cooling segment characterization
Mapping of circuits All info from Linda and the cooling system collected (thanks to Paolo F.) in: ..\Public\TkCooling\070810_TkCoolingMapping.xls On each cooling plant: the Scraeder valves on inlet and outlet are labeled with the cooling plant name and the Tracker name of the cooling loop (thanks to Paolo again!) N.B.: There is no symmetry between cooling plant distribution and sectors, one cooling plant serves both +Z and –Z Tracker sides! 22 August 07 Cooling segment characterization

7 Mapping on top of patch panels
22 August 07 Cooling segment characterization

8 Cooling segment characterization
Pressure & leak test Line by line (inlet or outlet, # x 180), ok up to 10 bars PLC: all lines locked, cooling plant in STOP mode (better) Cooling plant: check valves not installed, pipes plugged Ar supply on valve SV-I1#, manometer on valve SV-I2# for inlet pipes Manifold with both Ar and manometer on SV-O# for outlet pipes Equipment needed: Ar supply and manometer with schraeder valve, small manifold with both 22 August 07 Cooling segment characterization

9 Connectivity test – with gas
One complete circuit at a time (# x 90) PLC: all lines locked, cooling plant in STOP mode (better) Cooling plant: check valves not installed, pipes plugged N2 supply on valve SV-I1# Manometer on valve SV-O# Equipment needed: N2 supply and manometer with schraeder valve 22 August 07 Cooling segment characterization

10 First circulation tests
Set a preliminary flow regulation (temporary or not depending on the nb of circuits available) Measure Delta p along complete circuit Measure Delta T Installation of safety valves At least a few circuits completed Temperature gauges available outside and inside Tk 22 August 07 Cooling segment characterization

11 Draft procedure for balancing and Dp reading
PLC: Stop mode, all circuits locked PLC: Run mode, wait until the temperature is stable (~2 hours if starting from scratch, ~10 minutes if cooling plant in stand-by) CP: Close manual regulation valve CP: Connect differential pressure transmitter on SV-I1# and SV-I2# PLC: unlock the circuit, then open it after a couple of minutes with no alarms CP: open manual valve up to Dp = nominal (PLC reading, nominal values on mapping) CP: record manual valve position CP: disconnect Dp transmitter, put two manometers on SV-I2# and SV-O#, record 22 August 07 Cooling segment characterization

12 Draft procedure for DT reading
PLC: Run mode, T stable, nominal flow (ok if immediately after balancing and Dp measures) CP: Install T gauge on return pipe inside CP TK: Switch on heat source for that circuit PLC: Register time to stabilize T PLC & CP & TK: Once T stable, record T supply of the cooling plant, T return on the pipe, every possible T inside the TK! 22 August 07 Cooling segment characterization

13 DETECTOR COOLING UNIT REQUIREMENTS
22 August 07 Cooling segment characterization


Download ppt "Tracker cooling loop “check out” draft for discussion"

Similar presentations


Ads by Google