miniDOM report Vlad Popa
KM3NeT General Meeting, Marseille January 2012
2
The miniDOM story started with a proposal…
3
… and many people from various labs contributed:
Michel Ageron Marco Circella Antoine Couchner Paschal Coyle Maarten de Jong Eric Heine Sylvain Henry Aauke Korporaal Patrick Lamare Ovidiu Maris George Mogildea Marian Mogildea Vlad Popa Bertran Vallage … and many others in different moments.
4
The prototyping started in 2011 in ISS for the electronics…
5
… and at NIKHEF, for all the rest.
6
In 2012 the job moved to CPPM,
7
… while pressure tests were completed in Catania.
8
Various problems were identified and solved:
High currents at power on Noisy output Low signal amplitude (electronics sent back to ISS and fine tuned in summer 2012) … And other details, “not to be mentioned”
9
Today status: Tests and calibrations in the dark room, using the “flower pots” OK!
10
Today status: The miniDOM integration completed (the mechanics design changed in order to ease the connections)
11
Today status: The miniDOM (as the DOM) integrated on IL12F1, minimizing the LCM shadow.
12
Next steps: IL12 deployment and connection (starting February?) miniDM software installed at IMP Definition of the procedures (to be included in the ANTARES shfter’s manual) Decision on the miniDOM use: find a PhD student or a postdoc? Voluntaries from us? Any other suggestions? Thank you!