1
Jim Pinson ACACSO November 14, 2013
Event Reporting Jim Pinson ACACSO November 14, 2013
2
Agenda Industry trends Missing events Out of sequence events
Erroneous events
3
Industry trends Automated audits Centralized car hire
Reclaims countered because of missing events Centralized car hire Central processor cannot respond to events not reported Event data provided to shippers
4
Missing events
5
What events are missing?
Event Time From Road To Road Posting Road Liable Road City LCS Code Status ARIL 9/10/2013 2:51 GPRR City A A E DFLC 9/10/2013 3:10 9/10/2013 4:56 City B 9/10/2013 5:15 City C 9/10/2013 5:39 City D 9/10/2013 5:58 City E 9/10/2013 7:30 City F 9/10/2013 8:16 City G
6
Answer: Arrivals are missing
7
Possible impacts Internal systems must compensate for missing records
Shippers may not have visibility into car location From 9/10 – 08 until 9/10 – 14 Rule 22 reclaims may be countered Under CCH Rule 22 relief may not be created
8
Out of sequence events
9
Which events are out of sequence?
Event Time From Road To Road Posting Road Liable Road City LCS Code Status ARRI 8/28/2013 2:20 GPRR GP Yard A L PACT 8/28/2013 2:30 RMTY 8/29/ :17 E 8/29/ :19 PFPS 8/30/ :30 DFLC 8/30/ :40 RLOD 8/30/ :42 ARIL 8/30/ :45 City A
10
Answer: Release loaded (RLOD) was reported after the car departed GP yard
11
Possible impacts Internal systems must compensate for the out of sequence record Shipper/consignee may be given inaccurate car location data Car release 8/30 – 23:42 vs. Car arrived City A 8/30 – 23:45
12
Another possible impact
For a car being loaded, Rule 22 calculation may be incorrect
13
Erroneous events Event Event Time From Road To Road Posting Road
Liable Road City LCS Code Status BOHR 8/13/ :20 GPRR GP Yard A E STSU 8/16/ :50 BFRM 8/16/ :23 HQ OSTH 9/6/2013 7:46 DFLC 9/13/2013 8:53 ARIL 9/13/2013 8:54 City A 9/13/ :04
14
Which events are erroneous?
Release from bad order (BFRM) should be at GP yard, not HQ
15
Possible impacts Invalid car location information may be provided to shipper/consignee Mileage may be calculated from GP yard to HQ and back
16
Erroneous events Event Event Time From Road To Road Posting Road
Liable Road City LCS Code Status ARRI 8/17/2013 9:27 Road A City A A E ICHD 8/17/2013 9:28 GPRR GP Yard X 8/18/2013 7:29 AARG B ICHR 8/19/2013 5:30 ARIL 8/20/ :30 V L 8/20/ :00 Road B I
17
Which events are erroneous or missing?
Place, release and pull on GPRR – missing Interchange (ICHD) from GPRR to Road B
18
Possible impacts Incomplete information may be given to shipper or consignee Reclaims – either special or Rule 22 – may be challenged
19
Conclusion Accurate and timely event reporting is required to support current processes Internal systems Shipper/consignee information As industry moves toward more automation and centralization, accurate and timely event reporting will become more critical
20
Questions?