Download presentation
Presentation is loading. Please wait.
1
Critical Chain Project Scheduling
Chapter 11 Critical Chain Project Scheduling
2
Chapter 11 Learning Objectives
After completing this chapter, students will be able to: Understand the differences between common cause and special cause variation in organizations. Recognize the three ways in which project teams inflate the amount of safety for all project tasks. Understand the four ways in which additional project task safety can be wasted.
3
Chapter 11 Learning Objectives
After completing this chapter, students will be able to: Distinguish between critical path and critical chain project scheduling techniques. Understand how critical chain methodology resolves project resource conflicts. Apply critical chain project management to project priorities.
4
Theory of Constraints & Critical Chain Project Scheduling
A constraint limits any system’s output. The Goal – Goldratt TOC Methodology Identify the constraint Exploit the constraint Subordinate the system Elevate the constraint Repeat the process
5
FIGURE 11.2 Five Key Steps in Theory of Constraint Methodology
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall
6
Variation Special Cause Due to a special circumstance Managers should
Common Cause Inherent in the system Special Cause Due to a special circumstance Managers should Understand the difference between the two types Not adjust the process if variation is common cause Not include special cause variation in risk simulation Not aggregate discrete project risks
7
CCPM and the Causes of Project Delay
How safety is added to project activities Individual activities overestimated Project manager safety margin Anticipating expected cuts from management time 25% 50% 80% 90% Gaussian (lognormal) Distribution
8
Wasting Extra Safety Margin
The Student Syndrome Immediate deadlines Padded estimates High demand Failure to pass along positive variation Other tasks Overestimation penalty Perfectionism Multitasking Path Merging
9
Student Syndrome Model
FIGURE 11.6 Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall
10
Effects of Multitasking on Activity Durations
FIGURE 11.7 Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall
11
Effect of Merging Multiple Activity Paths
FIGURE 11.8 Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall
12
Critical Chain Solutions
Central Limit Theorem Activity durations estimated at 50% level Buffer reapplied at project level Goldratt rule of thumb (50%) Newbold formula Feeder buffers for non-critical paths
13
CCPM Changes Due dates & milestones eliminated
Realistic estimates – 50% level not 90% “No blame” culture Subcontractor deliveries & work scheduled ES Non critical activities scheduled LS Factor the effects of resource contention Critical chain usually not the critical path Solve resource conflicts with minimal disruption
14
Critical Chain Solutions
Bob Feeder Buffer ProjectBuffer Buffers protect constraints and prevent delays
15
Critical Chain Project Portfolios
Drum – system-wide constraint that sets the beat for the firm’s throughput company policy one person a department/work unit a resource Capacity constraint buffer – safety margin between projects Drum buffer – extra safety before the constraint
16
Applying CCPM to Project Portfolios
Identify the drum Exploit the drum Prepare a schedule for each project Determine priority for the drum Create the drum schedule Subordinate the project schedules (next slide) Elevate the capacity of the drum Go back to step 2
17
Subordinating Project Schedules
Schedule projects based on drum Designate critical chain Insert capacity constraint buffers Resolve any conflicts Insert drum buffers so the constraint is not starved
18
CCPM Critiques No milestones used
Not significantly different from PERT Unproven at the portfolio level Anecdotal support only Incomplete solution Overestimation of activity duration padding Cultural changes unattainable
19
Summary Understand the differences between common cause and special cause variation in organizations. Recognize the three ways in which project teams inflate the amount of safety for all project tasks. Understand the four ways in which additional project task safety can be wasted. Distinguish between critical path and critical chain project scheduling techniques. Understand how critical chain methodology resolves project resource conflicts. Apply critical chain project management to project priorities.
20
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.