JUSD Facilities Program Update February 16, 2016
2
Progress Report on Active Projects
Glen Avon Elementary- Utility Infrastructure Project Contractor installed new underground electrical and low voltage conduit. When Glen Avon’s modernization project begins this infrastructure will be ready. Stone Avenue Elementary- New Two-Story Building Project Contractor will complete final details of new building at the end of this month. Jurupa Valley High School Stadium Renovation Project Increment 1 of project (artificial turf, new track and hardscape improvements) wrapping up. Increment 2 of project (bleacher screening, new scoreboard and monument sign) scheduled to begin at the end of this month.
3
Glen Avon Utility Infrastructure Upgrades
4
Stone Avenue Two-Story Project
5
Before and After – JVHS Stadium Turf
Removed approximately 93,000 sq. ft. of natural turf
8
Plans to Expand Sunnyslope Elementary
Why? New housing developments Successful Dual Immersion Program How? Move existing relocatable classrooms on site to new area and construct a 2-story modular building on a permanent foundation with restroom facilities.
10
RHS Measure EE Façade Improvements
2007 Partial Modernization New Project Scope in Design Development Stage: Design and build rigid and durable wall soffit panels to provide a modernized appeal to buildings Storefront window system replacement in various wings Campus-wide accessibility upgrades Modernization of 1000, 1200A and B Street façade improvements .
11
Measure EE Projects – Status Update
Glen Avon Elementary (DD) Ina Arbuckle Elementary (DSA) Mission Bell Elementary (DD) Troth Street Elementary (DD) Jurupa Valley High School Innovation Lab (DSA) Jurupa USD Data Center (DD) Jurupa USD Parent Center (DD) New K-8 School # 5 (DSA)
12
Safety First- School Construction
Directives to Contractors via Contract Prior to Work Commencing Contractors complete background check certification- DOJ clearance or adequate barriers in place to limit contact. Site Secured with screened fencing. Site Project Superintendent present to ensure work safety. Project Manager on site to communicate daily with Principal regarding site impacts and work scope. Workers badged or wear shirts to identify as construction workers. Workers not allowed to talk with site staff or students. All communication between Project Manager and/or Site Superintendent and Principal. Minimal disruptions to sites. Movement of heavy equipment is required to be escorted by construction staff on-foot to ensure safety while on campus.