Transfer lines status 10/11/2016 O.Crespo-Lopez
2
Status Vacuum ports 3D model: Done in accordance with LHCb model
Design report: Done, some minor modifications requested 2D drawings: normally today Material ordering: this week Support design: normally today Vacuum ports O.Crespo-Lopez
3
Thermal & mechanical study
Conclusion: Due to the extreme conditions (-45°C & 130 bar) some bellow are mandatory Bellow example O.Crespo-Lopez
4
Interconnection 26.67mm sleeve Vacuum Armaflex 76.1mm O.Crespo-Lopez
5
Interconnection 104mm protective sheet 100mm Armaflex O.Crespo-Lopez
6
Interconnection bellow O.Crespo-Lopez
7
End points Alcove Cavern O.Crespo-Lopez
8
Next steps Get final documentation (EN-CV)
Support proposal Final bellow design Information about the 10mm supporting Ordering and installation of the support (LHCb) Check of the 1st weld samples (EN-CV) construction schedule (EN-CV) On-site visit??? Installation schedule (EN-CV) PDP or PPSPS + VIC Training organization Weld test Biocell training SIR training Tests O.Crespo-Lopez
9
Conclusion We are late but the company seems re-active and professional Do we organize a factory visit during the construction? We need to think about the final test!! O.Crespo-Lopez