Download presentation
Presentation is loading. Please wait.
1
Activities Status and Plan for the week
D. Giugni / INFN Milano Monday Meeting D. Giugni
2
Harnesses Stacking Set 0 left UN-USED Set 1 Set 2 Set 3
Decided so far to grab from the set only spares (if required). Considered not “for production” Set 1 General Set has been assigned to C34 (X0) One Harnesses non conformal one taken from Set 2 Status All the Harnesses “Prepared” and tested IPS, IHV-NTC, OIH-NTC are Stacked and tested OPS stacking planned today Open Issues Need to repair the swapped harness Set 2 Set has NOT been assigned to nSQP Decided to put in hold: too many faults. Only 2 Harnesses “Prepared” and tested Need repairs Set 3 General Set assigned to C12 Status All IHV-NTC and OHV-NTC “Prepared” IHV-NTC, OHV-NTC Redy to stack (Today) Open Issues None D. Giugni Monday Meeting
3
Soldering Agreed sequence IF PP0 OSP boards are not released:
ISP C34 (X0) started ISP C12 (X1?) will start next Monday (new soldering team) ISP C56 (X2?) will start ~Feb 20th with the 3rd soldering team ISP C78 (X3?) will start when ISP C12 is done (< Feb 20th) D. Giugni Monday Meeting
4
Post Soldering Assembly (General)
This activities is referring, at the moment, only to the Trail C34 (X-1) Main operations: Bond ER bundle organizers at PP0 Bond E_boards peek pins Bond type0 cable stabilizer (only for ISP) Bond PP1 Flanges Bend harnesses at the dogleg Testing Load ER bundles (on the OSP bottom a/o ISP) and mount some ancillary parts Load the E-Boards (on the OSP bottom a/o ISP) Functionality test Secure the E-boards D. Giugni Monday Meeting
5
Post Soldering Assembly (Status)
OSP C4 (X-1) Completed. Panel is not functional due to the extensive wire cut required to put it together OSP C3(1) (X-1) Not done yet. Panel has been just released from the Soldering ISP C4 (X-1) Completed. Panel is functional. ISP C3 (X-1) Bond ER bundle organizers at PP0 Bond E_boards peek pins Bond type0 cable stabilizer (only for ISP) Bond PP1 Flanges Bend harnesses at the dogleg Testing Load ER bundles (on the OSP bottom a/o ISP) and mount some ancillary parts Load the E-Boards (on the OSP bottom a/o ISP) Functionality test Secure the E-boards D. Giugni Monday Meeting
6
Final Assembly Referring only to the trial (X-1). Main operations:
Set up the backbone Load the cooling pipes Load OSP L and R Load the ER_Bundles on the OSP’s Top Load the E_Board on the OSP’s Top Flip the assembly up side down Dress up the ER_Bundles at PP1 and on the Flowers Functionality Test Load the ENV sensors Flip the nSQP Secure the Top E_Boards Dress up the bundles at the PP1 can D. Giugni Monday Meeting
7
Schedule for this week Schedule presented last week has been significantly reshuffled due to same missing parts. Mainly: OSP PP0 boards, some ISP Cx and all A side boards. PP0 stiffeners The original nSQP assembly sequence: has been changed to: C34 ISP C12 ISP ISP C56 ISP C78 … D. Giugni Monday Meeting
8
Schedule for this week (2)
Corrugated panel bonding: Delay in SLA parts. 2 panels done for the C34. Restart the production as soon as parts a delivered (this week?) . PP0 boards stiffening and Alu Block bonding Received C2, C5, C7 ISP board loaded. Received ISP stiffeners Laminate and test the boards within this week ISP C12 (really needed by Fri!) Soldering Keep going with the ISP C34 (X0) HV-NTC (Main Team) Prepare the second Team by next Mo for the ISP C12. Post Soldering Assembly On ISP C3 (X-1): Bond cable stabilizer Bend Harness, Test, Load ER-Bundles and dummy E-Board On OSP C4 (X-1): Start the full procedure. Final Assembly Trial (X-1) Work out better flipping tool Load pipes in C3 Sort out ENV sensor location Be prepared to receive the ISP C3 and ISP C3
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.